05 MECHANICAL INSTALLATION
3BHS212794 E01 REV M
ACS6000
USER MANUAL
114/278
3.
Loop a length of the cables and fasten them to the cable tie
mount (circle).
Figure 5-11 Correct and incorrect cable installation
4.
Remove the cover on the roof where the heat exchanger is installed.
5.
Lift the heat exchanger above the opening in the roof and orientate
the heat exchanger with the LEDs (circle) pointing to the front of
the cabinet.
CAUTION!
Hazardous voltage! Make sure that the heat exchanger cables
do not touch the high-voltage carrying DC busbars (2 in Fig. 5-11).
(1) Correct cable installation
(2) DC busbar
(3) Incorrect cable installation
1 x
1
2
2
3