General safety instructions
Minimize hazards
- Always observe local safety laws and regulations when working with electricity.
Before energizing the drive:
- Remove all foreign objects are from the drive
- Fasten all internal and external covers securely
- Close, lock, and/or bolt all doors
- Move the release dial of the door safety switches into the locked position
Before working on the drive:
- Turn off, lock out, and tag out the main and auxiliary power supplies to
the drive
- De-energize the drive
- Ensure that the safety ground connections are in place
- Ensure that the appropriate personal protective equipment (PPE) is available
and used when required
- Inform the involved personnel about the potential safety hazards
- Wear hearing protection when a drive is running.
Before working simultaneously on the drive and on other drive
system equipment:
- Observe the relevant safety codes and standards
- Turn off all energy sources for the equipment
- Ensure that all lockout and tagout devices are in place
- Install barriers around and use appropriate covers on the equipment that is
still energized
- Inform the involved personnel about the potential safety hazards
In case of fire in the drive room:
- Observe the established rules and regulations for fire safety
- Only allow firefighters with the appropriate PPE to enter the drive room
Summary of Contents for ACS 1013-A1
Page 1: ... MEDIUM VOLTAGE AC DRIVES ACS1000 air cooled User manual ...
Page 3: ...Contents ACS1000 air cooled User manual ...
Page 5: ... 01 About this manual 01 3 14 ...
Page 16: ......
Page 17: ... 02 Important safety information 02 15 26 ...
Page 28: ......
Page 29: ... 03 Power electronics and cabinet features03 27 50 ...
Page 53: ... 04 Control system 04 51 66 ...
Page 68: ......
Page 69: ... 05 Transportation storage and disposal05 67 74 ...
Page 76: ......
Page 77: ... 06 Mechanical installation 06 75 82 ...
Page 84: ......
Page 85: ... 07 Electrical installation07 83 106 ...
Page 108: ......
Page 109: ... 08 Commissioning 08 107 112 ...
Page 115: ... 09 Operation 09 113 126 ...
Page 129: ... 10 CDP control panel 10 127 150 ...
Page 153: ... 11 Preventive and corrective maintenance 11 151 182 ...
Page 185: ......