List of bushings applicable to this installation guide
Type
Article number
GOE 2600
LF121085-D
GOE 2600
1ZSC902110-AAA
2.2.2 Mechanical loading
Maximum permitted static load on the outer terminal
The load must be applied below the midpoint of the outer terminal. The total cantilever load must be
perpendicular to the bushing axis. The bushing installation angle can be 0° – 30° from vertical.
NOTE!
The loads described in this section are static loads, for dynamic loads such as earthquakes and
extreme wheather conditions, please contact your Hitachi ABB Power Grids sales representative.
G006946
A.
Maximum cantilever load at installation angle 0°
B.
Maximum axial static load
C.
Load applied at the midpoint
Type
Test load 1 minute
(N)
Maximum cantilever load in operation
at installation angle (N)
Maximum axial
static load (N)
0°
>0°
GOE 2600
9500
2500
On request.
20000
Maximum permitted torque on the outer terminal
The maximum torque that is permitted on the outer terminal is 250 Nm.
Summary of Contents for 1ZSC902110-AAA
Page 12: ...12 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...
Page 18: ...18 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...
Page 78: ...78 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...
Page 82: ...82 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...