2.2 Unpacking
2.2.1 Pre-installation procedure
Introduction
This section is intended for use when unpacking and installing the robot for the
first time. It also contains information useful during later re-installation of the robot.
Prerequisites for installation personnel
Installation personnel working with an ABB product must:
•
be trained by ABB and have the required knowledge of mechanical and
electrical installation/maintenance/repair work
•
conform to all national and local codes.
Checking the pre-requisites for installation
Action
Make a visual inspection of the packaging and make sure that nothing is damaged.
1
Remove the packaging.
2
Check for any visible transport damage.
Note
Stop unpacking and contact ABB if transport damages are found.
3
Clean the unit with a lint-free cloth, if necessary.
4
Make sure that the lifting accessory used (if required) is suitable to handle the weight
of the robot as specified in:
5
If the robot is not installed directly, it must be stored as described in:
6
Make sure that the expected operating environment of the robot conforms to the
specifications as described in:
Operating conditions, robot on page 47
7
Before taking the robot to its installation site, make sure that the site conforms to:
•
Loads on foundation, robot on page 45
•
Protection classes, robot on page 47
•
Requirements, foundation on page 46
8
Before moving the robot, please observe the stability of the robot:
9
When these prerequisites are met, the robot can be taken to its installation site as
described in section:
On-site installation on page 54
10
Install required equipment, if any.
•
Installation of signal lamp (option) on page 77
11
Weight, robot
The table shows the weight of the robot.
Weight
Robot model
440 kg
IRB 4600
Continues on next page
44
Product manual - IRB 4600
3HAC033453-001 Revision: Y
© Copyright 2009-2021 ABB. All rights reserved.
2 Installation and commissioning
2.2.1 Pre-installation procedure
Summary of Contents for IRB 4600
Page 1: ...ROBOTICS Product manual IRB 4600 ...
Page 8: ...This page is intentionally left blank ...
Page 334: ...This page is intentionally left blank ...
Page 368: ...This page is intentionally left blank ...
Page 376: ...This page is intentionally left blank ...
Page 390: ...This page is intentionally left blank ...
Page 392: ...This page is intentionally left blank ...
Page 398: ......
Page 399: ......