RECOMMENDED MAINTENANCE 

1.

Daily visual checks to be done.

A.

Check all retaining rings, set screws and working parts are in place and in good working condition

 

before operations

B.

Check cylinder and foot valves daily for any air leaks before operation.

2.

Grease all grease 

points

 monthly.  The locations of these are the two frame center pivot shafts and 

the

 

two cylinder pivot shaft under the lift top.

3.

Oil cylinder every 3 months.  Use a 

lanolin spray or similar

.  Unscrew foot valve from air line supply ,

 

squirt oil into air line then screw foot valve back on air supply line and apply air pressure.  This will

 

blow air inside of the cylinder coating the cylinder walls.  This procedure keeps seals soft and pliable.

1.

Center load on table - 

500 Kg

. maximum.

2.

Connect to 110 psi maximum shop air.

3.

Keep safety bar in position at all times - except

 

when lowering.

4.

Keep hands and tools from under carriage.

5.

Do not mount table when in elevated position.

6.

Do not ride vehicle onto lift.

7.

Lift must be in the lowered position when moving.

8.

Only trained persons should operate Air Lift.

9.

The working area should be sufficiently lit.

10.

Foot controller should be at least 3 feet away from

 

Air Lift during raising and lowering operation.

11.

Recommended for indoor use only.

12.

Tie-down straps must be used in conjunction with

 

the holes provided in the lift top.

Summary of Contents for AutoLift 243612

Page 1: ...SE INJURY OR DEATH Specifications subject to change without notice Note While all due care and attention has been taken in the preparation of this document Advance AutoQuip shall not be liable for any inaccuracies or omissions which may occur therein MOTORCYCLE HOIST AutoLift 243612 Model No AL 243612 Air Operated Motorcycle Lift 500Kg Maximum Lifting Capacity Design Registration Approval Number N...

Page 2: ... lubricated at the factory and should be re lubricated every 6 months to prevent falling Grease points are located at each end of frame pivot shaft and at top ends of inside frame assembly 4 Lightly oil cylinder rod when it becomes dry 5 Squirt some oil through bleed hole in plate end of cylinder to lubricate piston and its seal every 6 months 6 Pivot shaft set screws should be checked frequently ...

Page 3: ...ne and apply air pressure This will blow air inside of the cylinder coating the cylinder walls This procedure keeps seals soft and pliable 1 Center load on table 500 Kg maximum 2 Connect to 110 psi maximum shop air 3 Keep safety bar in position at all times except when lowering 4 Keep hands and tools from under carriage 5 Do not mount table when in elevated position 6 Do not ride vehicle onto lift...

Page 4: ...ng 4 25 Piston seal 1 3 1 39 2 1 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 26 27 28 29 30 31 32 33 34 35 36 37 25 38 Edition 1 0 Oct 2009 5 Retaining ring 4 25 Piston seal 1 6 Wheel 2 26 Valve hose w fitting 1 7 Scissor frame A 1 27 Foot valve assembly 1 8 Clevis pin 2 28 Cylinder shaft assembly 1 9 Cotter pin 2 29 Cam roller bearing 4 10 Detent clip 1 30 Cam bearing space 2 11 Nu...

Page 5: ...PECIFIC WARRANTY PROVISIONS FOR UNITS LOCATED OUTSIDE OF THESE COUNTRIES NOTE THE EQUIPMENT IS NOT TO BE USED FOR WASH DOWN PURPOSES OR TO BE INSTALLED IN AN OUTDOOR ENVIRONMENT WHERE IT IS SUBJECT TO WEATHER OR WATER DAMAGE WARRANTY WILL BE IMMEDIATELY VOID STRUCTURAL COMPONENTS ALL STRUCTURAL AND MECHANICAL COMPONENTS OF THIS UNIT ARE GUARANTEED FOR A PERIOD OF FIVE YEARS FROM THE DATE OF INVOIC...

Page 6: ...ety locks tested for correct operation Checked for good working order Supplied with the hoist and in good working order Checked for correct operation Hoist checked with load for correct operation and speed control tested Checked wire ropes for correct installation and tension Concrete floor is a suitable depth for installation Safety Devices Welds Hydraulic Equipment and Controls Pneumatic Equipme...

Page 7: ...onstrated the operation of the vehicle hoist to the owner or operator Lock off isolating switch installed Emergency stop button installed 3 Details of Electrical Contractor Trading Name Address 4 Signature I being the person responsible for completing the commissioning report have exercised reasonable skill and competency when completing the report and herby certify that the vehicle hoist has been...

Reviews: