background image

 

 

 

15  

 

 

GDED-IOM-215-A 

9.2.4

 

Products shipped in multiple modular assemblies 

Where product is shipped with  the main  housings  in multiple modular  assemblies, 

with the hoppers and legs separate, proceed as follows: 

 

Follow item 9.2.4.1 to pre-install the legs and then bring in the housing modules in 

turn bolting the first to its legs before bringing in the second. 
  

Pre-apply the sealant to the flanges as 9.2.2 and then bolt the housings together. 

 

Install all the supplied bolts between housings loosely at first. Access to the bolt holes 

is  gained  via  the  porthole  covers  and  the  inlet/outlet  openings  (remove  the  covers  and 
cartridges). When all the bolts are loosely in position they must be tightened in a sequence 

working from the center bolts towards the corners, radiating outwards in opposite side in 
sequence  so  that  the  four  corner  bolts  are  last  to  be  tightened.  This  pulls  the  modules 

together with all the mating flanges flat against each other with no bulges.  

   

9.2.4.1

 

Leg structure 

Assemble  the  leg  structure  onto  the  prepared  foundations  or  steelwork  using  the 

supplied GA drawing which shows the position of all the legs and cross braces. Ensure all 

the nuts and bolts are tightened and the structure is mechanically sound and secure, and 

level before proceeding to the next stage. 

 

Anchors (supplied by others) must comply with local code requirements and must be 

capable of supporting dead, live, wind, seismic, and other applicable loads for the area the 

dust collector is going to be installed.  

 

Consult with a qualified engineer for foundation and anchoring design.  

 

9.2.4.2

 

Hoppers 

Position  the  hopper(s)  onto  the  leg  structure  and  fix  it  into  position  using  the  GA 

drawing as a guide. Level the hopper once installed.  

 

9.2.4.3

 

Collector Housing 

Apply sealant (supplied by AAF) to the upper flanges of the hopper(s) ensuring the 

sealant circles around each bolt hole. 

 

Lift  the  housing  module(s)  using  its  lifting  lugs  and  lower  into  position  onto  the 

hoppers so that the holes in the matching flanges correctly align. 

 

CAUTION: Never stand or work beneath a suspended load.   
 

Summary of Contents for OptiFlo RC Series

Page 1: ...GDED IOM 215 A OptiFlo RC...

Page 2: ...lean REDFiltration and Reliable Efficient Durable are registered trademarks of American Air Filter Company Inc d b a AAF International GDED IOM 215 A TO ORDER SPARE REPLACEMENT PARTS Call 1 800 477 12...

Page 3: ...CT SHIPMENT 11 4 1 How the product ships 11 4 2 Items that ship separately 11 5 PRODUCT RECEIPT AT THE DESIGNATED DELIVERY POINT 11 5 1 Responsibilities of the customer or customer s agent 11 5 2 Rece...

Page 4: ...PLOSION VENTS 20 10 1 Installation of the explosion vent 20 10 2 Assembly 20 10 3 Explosion Vent Burst Sensor 21 10 4 Servicing 22 10 5 Safety distance 22 11 START UP OPERATION 22 11 1 Start up checkl...

Page 5: ...m very large multiple component assemblies which require significant and complex rigging handling and assembly on site to small compact assemblies that are easily handled and maneuvered In addition to...

Page 6: ...l be allowed within the work perimeter 2 3 Dust explosions Dust explosions constitute a serious industrial hazard and may result in death serious injury and or devastating property damage It is the re...

Page 7: ...The equipment shall be oriented so that the vent will discharge to an unoccupied zone Such a zone will be prohibited to personnel and shall not include critical equipment or services such as fuel sto...

Page 8: ...nd moves in a true down flow direction between the filters The airstream passes through the media as the dust is collected on the filter media The clean air then moves through the tube sheet section a...

Page 9: ...arranged three high 4RC modules have filters arranged four high and 5RC have filters arranged five high The RC is nomenclature for Round Cartridge Each series offers standard factory assembled collec...

Page 10: ...is greater than the standard 20 w g design pressure is anticipated lb kg 2RC4 1662 754 2RC8 1763 800 2RC16 2565 1164 2RC24 4328 2072 3RC6 1999 907 3RC12 2103 954 3RC24 3123 1417 3RC36 4205 1908 3RC48...

Page 11: ...Safe and efficient operation of the collector depends on proper installation Know proper laws codes and regulations before installation starts 5 2 Receiving Remove crates tarps shipping straps etc alo...

Page 12: ...ING 6 1 Unloading and lifting into position Failure to lift the collector correctly can result in severe personal injury property damage or even death Connect lifting sling to all supplied lifting lug...

Page 13: ...ed easily See collector drawing for cartridge clearance In the case of hazardous dust consult your local authorities laws codes or regulations for the location of the unit 8 2 Foundations The OptiFlo...

Page 14: ...multiple modules normally have their housings factory pre assembled up to a minimum of 4 modules with legs and hoppers sent for site assembly If more than 4 modules are required or if there are site...

Page 15: ...inst each other with no bulges 9 2 4 1 Leg structure Assemble the leg structure onto the prepared foundations or steelwork using the supplied GA drawing which shows the position of all the legs and cr...

Page 16: ...re within 15ft of the static taps located on either of the OptiFlo RC side panels Usually the Pressure Demand controller is fixed to the leg structure but it can be remotely located if desired Once th...

Page 17: ...il air tight 9 2 8 Installation of accessories When accessories such as sprinklers abrasion resistant inlets and airlocks are ordered with the OptiFlo RC separate installation instructions will be pro...

Page 18: ...electrical connection diagram that is supplied with the specific OptiFlo RC collector ordered The power requirements are 85 270V 50 60Hz 1Ph The operating temperature range is 40F to 140F Continuous c...

Page 19: ...is factory set at a 30 second pulse interval Do not use over 100 psig of compressed air Solenoid valves will not operate and can cause damage to collector components The compressed air connection shou...

Page 20: ...the explosion vent during shipping or handling The OptiFlo RC will have a frame constructed as part of the unit where the explosion vent is mounted The number of explosion vents and location of the ex...

Page 21: ...Sensor All standard explosion vents come with a burst sensor This can be connected to an AAF Control Center or to the customer s controls to shut down the unit when an event occurs The magnetic sensor...

Page 22: ...psig Check that cartridges are properly installed and that the red cam lock handles on the port hole doors are all fully engaged see Section 9 2 7 Ensure the hopper discharge device s if any is operat...

Page 23: ...tomatic and does not require constant supervision The OptiFlo RC is assumed to be part of a system that will include a fan and possibly other components supplied by AAF or other companies For successf...

Page 24: ...ad on the display of the pulse controller After start up the dust collector s differential pressure should settle to approximately 2 3 inches w g The filter cleaning cycle is automatically controlled...

Page 25: ...ir or dust leakage Check for evidence of moisture or dust build up within the collector Moisture in the collector can cause plugging and premature cartridge failure Check all electrical apparatus for...

Page 26: ...llector Do not operate the dust collector with missing or damaged cartridges The working area requires good ventilation Some applications involve hazardous gasses and dusts Check with an authorized pe...

Page 27: ...pping storage or handling DO NOT use damaged cartridges 8 Slide the new cartridges onto the support mandrels normally two cartridges per mandrel gasket end first While installing cartridges be careful...

Page 28: ...ary valve etc referring to the relevant IOM and taking all safety precautions Issue Moisture Condensation Solution Free moisture on the cartridges will inhibit dust release and cause high differential...

Page 29: ...on Ensure filter access door knob is tightened fully and the gasket appears to be air tight Perform a paper test by trying to slide a piece of paper between the gasket and unit surface If a piece of p...

Page 30: ...ck in the hopper Solution Consider changing the process so that less moisture is drawn into the OptiFlo or that some warm dry air is included in the extraction system to drive the combined flow furthe...

Page 31: ...moisture present in collector Date Examine cartridges Examine outer door gasket Examine inner door gasket Check correct electrical operation Examine dust disposal equipment Examine auxiliary equipment...

Reviews: