Maintenance 

 
 

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 

4.1  Preparation for 
 

maintenance 

 
 
 
 
 
 
 
 

4.2  Water-side  
 

maintenance 

 

 

4.2.1 

 

Warning 

Maintenance may only be carried out by a competent person. 

 
At each service, the water heater undergoes maintenance on water side. The 
maintenance must be carried out in the following order. 
1.  Preparation for maintenance 
2.  Water-side maintenance 
3.  Finalising maintenance 
 

Note 

Before ordering spare parts, it is important to write down the installation type, water 
heater model and the full serial number of the water heater. These details can be 
found on the rating plate. Only by ordering with this information can you be sure 
receiving the correct spare parts. 

 
 
 
The preparation for maintenance consists of testing and checking if all components 
are still working properly by completing the following steps: 
1.  Test the operation of the overflow valve of the protected cold supply setup. The 

water should discharge 

2.  Check the drainage pipes from the discharge points of all valves and remove any 

scale deposits that may be present. 

3.  Drain the water heater. 
 
 
 
Water-side maintenance consists of descaling and cleaning the tank and checking 
the anodes. 
 
 

Descaling and cleaning the tank

 

Scale and lime build-up prevent effective conduction of the heat to the water. 
Periodic cleaning and descaling prevents build-up of these deposits. This increases 
the service life of the water heater, and also improves the heating process. 
 
Take the rate of scale formation into account when deciding on the service interval. 
Scale formation depends on the local water composition, the water consumption and 
the water temperature setting. A water temperature setting of maximum 60°C is 
recommended for the prevention of excessive scale build-up. 
 
To guarantee a good, watertight seal around the cleaning opening, replace the 
gasket, washers, bolts and, if necessary, the lid with new parts before reassembly. 
Spare parts are obtainable from the supplier/manufacturer. 
 
To simplify descaling and cleaning of the tank, the water heater is equipped with a 
cleaning opening. 
 

 

Summary of Contents for ITE -1000

Page 1: ...0312 735 Innovation has a name Indirect calorifier ITE 400 500 600 750 1000 ITE Installation User and Service Manual 3917 Wijzigingen voorbehouden Changes Reserved R serve de modifications...

Page 2: ...ampshire GU14 0NR www aosmith co uk A O Smith France 14 all e Charles Path 18000 Bourges www aosmith fr 008008 AOSMITH 2676484 A O Smith Hoofdkantoor Europa De Run 5305 5503 LW Veldhoven www aosmith n...

Page 3: ...ed use use other than that stated in this manual and use other than in accordance with the General Conditions registered at the Chamber of Commerce Refer further to the General Conditions These are av...

Page 4: ...Installation Service and User Manual 4...

Page 5: ...g clearance 7 Packaging 7 Disposal 7 General specifications 8 Dimensions 8 Installation 11 Installation diagram 11 Water connections 12 Filling and Draining 13 Filling 13 Draining 14 Maintenance 15 Pr...

Page 6: ...Installation Service and User Manual 6...

Page 7: ...then the tank protection cannot be guaranteed 4 Warranty For access to the water heater it is recommended that the following clearances are observed around the anode connection 100 cm around the water...

Page 8: ...ameter with insulation mm 740 760 910 930 1080 G Height heat exchanger outlet mm 260 260 310 310 350 H Height heat exchanger inlet mm 775 915 910 970 945 M Height cold water inlet mm 70 70 85 85 95 N...

Page 9: ...0312735_ITE_400 1000_EN_V1 0 2017 09 25 9 Front sectional view of the appliance IMD 1299 R0...

Page 10: ...Installation Service and User Manual 10...

Page 11: ...oints 15 expansion valve mandatory 16 expansion vessel mandatory A cold water supply B hot water supply C circulation pipe F inlet heat exchanger G outlet heat exchanger Installation Diagram IMD 1169...

Page 12: ...icing Circulation pipe See C in the installation diagram 2 1 Installation diagram If an immediate flow of hot water is required at draw off points a circulation pump can be installed This improves com...

Page 13: ...er proceed as follows 1 Open the stop valve 11 in the hot water pipe and if present the stop valves 4 for the circulation pump 6 2 Close the drain valve 9 3 Open the nearest hot water draw off point 1...

Page 14: ...vice and User Manual 14 3 2 Draining 1 Close the stop valve 4 between the cold water head tank and the cold water inlet A 2 Open the drain valve 9 3 Bleed the water heater or installation so that it d...

Page 15: ...ischarge 2 Check the drainage pipes from the discharge points of all valves and remove any scale deposits that may be present 3 Drain the water heater Water side maintenance consists of descaling and...

Page 16: ...d damage to the tank tighten the bolts that fasten the lid with a torque no greater than 50 Nm Use suitable tools for this Checking anodes Anodes ensure the protection of the tank by sacrificing thems...

Page 17: ...uctions for the specific model and the relevant government and local authority installation and building codes rules and regulations in force at the time of installation b The water heater remains ins...

Page 18: ...O Smith pursuant to the specified warranty are limited to free delivery from the warehouse of the replacement assemblies parts or water heater respectively Shipping labour installation and any other...

Reviews: