A.O. Smith Burkay HW-300 Installation & Operation Manual Download Page 19

19

NO.

SUGGESTED ITEMS FOR INSTALLATION

1

Short  pipe  nipple  and  pair  of  boiler  loop  tees  in  piping 

between system supply and return. One set per each group 

of boilers.

2 Boiler pipe loop. See piping sizing data.

3 Boiler circulator. See pump sizing data.

4 Thermometer.

5 Theraltimeter.

6 Plug cock to control flow rate.
7 Safety  flow  switches.  For  interlock  with  other  systems  or 

instead of low water cutoff.

8 Relief valve.

9

With one -300, -399 or -420 item 9 is - sensing element of 

remote control.

With a group of -300's, -399's or -420's, item 9 is - for 1st 

boiler, the sensing element as above. For additional boilers, 

install  a  2nd  limit  control  if  required  by  local  codes.  With 

any -520, -610 or 670 boilers, install 2nd limit control here if 

required by local code.

BOILER INLET - OUTLET SIZES

10 HW-300  -  1-1/4",  HW-399  -  1-1/2",  HW-420  -  1-1/2",  

HW-520 & HW-610 - 2".

10 HW-300 - 1-1/4", HW-399 - 1-1/2", HW-420 - 1-1/2", HW-520 

& HW-670 - 2".

MINIMUM BRANCH SIZES TO BOILERS

11

HW-300 - 1-1/4"               HW-520, 610 (Single boiler

HW-399 - 1-1/2"               per pump) 2"

HW-420 - 1-1/2"               

11

HW-300 - 1-1/4"               HW-520, 670 (Single boiler

HW-399 - 1-1/2"               per pump) 2"

HW-420 - 1-1/2"               

12

Flow  control  valve.  Required  only  if  flow  rate  of  system 

primary is excessive for size of boiler branch tees or if chilled 

water main is above boilers.

13 System supply temperature thermometer.
14 Boiler headers for three (3) boilers can be larger than pipe 

loop, if desired, to aid in balancing.

The  system  flow  rate  is  selected  to  give  the  desired  system 

temperature drop - depending on the design criteria.

The  boiler  generator  flow  rates,  on  the  other  hand,  should  be 

selected to give the temperature rise through the generator that is 

both economical and offers the best generator efficiency.

The boiler temperature rise is normally between 10

0

C and 20

0

C (20

0

and 40

0

F). The system temperature that will be introduced to the 

boiler (inlet temperature) plus the selected boiler temperature rise 

selected from PUMP AND PIPE SIZING DATA should not exceed 

the high limit control setting of 115

0

C (240

0

F).

There should be a relation of the minimum system load to the size 

boiler selected as the first firing or base boiler. This will stabilize 

operation during minimum load periods.

 

B.  Commercial Boiler Replacements

Application of LINEAR-TEMP

®

 to a commercial boiler replacement 

with an old multiple pump installation is an excellent way to modernize 

the system. The A. O. Smith boiler(s) should be installed on a pipe 

loop with a separate circulating pump selected from PUMP AND 

PIPE SIZING DATA TABLE.

Figure 12 shows a line drawing of how the system headers should be 

connected to the pipe loop installed with the replacement boiler(s).  

Make-up water connections and accessories are not shown.

SCHEMATIC OF THE LINEAR-TEMP

®

 SYSTEM

FIGURE 12.

Supply and return headers of the old system should be connected 

to the boiler loop with a pair of tees set close together. The boiler 

loop pump and the boiler(s) should be wired to operate only when 

any of the system pumps are in operation. The number of zone 

pumps that may be in operation at any particular time will take 

their required flow rate out from the first tee in the boiler piping. 

This  water  will  be  circulated  through  the  proper  branches  from 

the supply header to the zones calling for heat. The water will be 

brought back to the return header and then into the second tee in 

the boiler pipe loop. There will be no conflict between the boiler 

pump and the zone pumps when the two tees in the boiler loop 

are placed close together.
Normal  use  of  flow  control  valves  is  required  to  prevent  cross 

circulation of zones as with any multiple pump system. Flow control 

is not required on boiler circuit.
Attention should be given to balancing gas inputs and water flow 

rates. Large systems with multiple boilers should include main water 

temperature control (with or without outdoor reset) to stage the boilers 

on and off in relation to the load on the system.

3. WATER SUPPLY LINE

These boilers can be used ONLY in a forced circulation hot water 

heating system. Since most forced circulation systems will be of 

the closed type, install the water supply line as shown on piping 

diagrams, Figure 7 to 11 on pages 14 and 18.
Fast  filling  of  large  pipe,  old  radiator  installations  and  pressure 

purging  of  series  loop  systems  (where  high  pressures  are  not 

available)  requires  bypassing  of  the  pressure  reducing  valve. 

Generally, pressure purging is not possible with a well pump system. 

High point air venting is essential.
If  the  system  is  of  the  open  type,  a  pressure  reducing  valve 

will not be required as the water supply to the system will be 

controlled  by  a  manually  operated  valve. An  overhead  surge 

tank is required.

4. EXPANSION TANK

 CAUTION

A closed system will exist if a check valve (without bypass), pressure 

reducing valve (without bypass), or a water meter (without bypass) is 

installed in the cold water line between the water heater and street 

main (or well).
Excessive pressure may develop causing premature tank failure or 

intermittent relief valve operation. This is not a warranty failure.  An 

expansion tank or a similar device may be required in the inlet supply 

line between the appliance and the meter or valve to compensate for 

the thermal expansion of water under supply pressure, see Figure 7 

on page 14.
An air separator as shown in the piping diagrams is recommended 

especially for modern commercial hydronic systems.

Summary of Contents for Burkay HW-300

Page 1: ...rty damage personal injury or death Do not store or use gasoline or other flammable vapors and liquids in the vicinity of this or any other appliance WHAT TO DO IF YOU SMELL GAS Do not try to light an...

Page 2: ...s Many safety related messages and instructions have been provided in this manual and on your own water heater to warn you and others of a potential injury hazard Read and obey all safety messages and...

Page 3: ...3 GENERAL SAFETY...

Page 4: ...ns 14 VENTING 14 Venting the Boiler 14 Venting Maintenance 16 Venting Sidewall 16 Venting System 16 Venting Tables 17 SYSTEM INSTALLATIONS 18 Installations 18 Conventional 18 Linear Temp 18 Water Supp...

Page 5: ...to Center Line Gas Inlet 16 1 2 419 16 3 4 425 16 3 4 425 18 457 18 457 18 457 H Overall Depth 29 5 8 753 31 1 2 800 31 1 2 800 36 1 2 927 36 1 2 927 36 1 2 927 J Support Height 9 229 9 229 9 229 9 2...

Page 6: ...765 638 547 478 LPH 7245 3623 2898 2415 2070 1811 HW 420 420 000 123 GPH 2014 1007 806 671 576 504 LPH 7627 3813 3051 2542 2179 1907 HW 520 520 000 152 GPH 2494 1247 998 831 713 624 LPH 9443 4721 3777...

Page 7: ...onnected to the equipment grounding terminal or lead on the boiler CORRECT GAS MAKE SURE THE GAS ON WHICH THE BOILER WILL OPERATE IS THE SAME AS THAT SPECI FIED ON THE BOILER RATING PLATE DO NOT INSTA...

Page 8: ...stment to the gas pressure regulator is required See CHECKING AND ADJUSTING THE INPUT in this manual for inlet and manifold pressure requirements Also due to the input rating reduction required at hig...

Page 9: ...flow switch is a safety device which must be installed at the water outlet of the unit to prevent main burner operation in the event of inadequate water flow through the unit An accessory package cont...

Page 10: ...NG THE PURPOSE OF A SAFETY RELIEF VALVE IS TO AVOID EXCESSIVE PRESSURE OR TEMPERATURE INTO THE STEAM RANGE WHICH MAY CAUSE SCALDING AT FIXTURES TANK EXPLOSION SYSTEM OR BOILER DAMAGE TO AVOID SCALDING...

Page 11: ...CAN CSA B149 TANK TEMPERATURE CONTROL The water temperature in the storage tank is controlled by the Tank Temperature Control The sensing element is mounted inside the hot water storage tank DANGER H...

Page 12: ...iler and tank for draining purposes see installation diagrams in this manual REQUIRED ABILITY Installation or service of this boiler requires ability equivalent to that of a licensed tradesman in the...

Page 13: ...struction air for combustion ventilation and draft hood dilution must be obtained from outdoors When directly communicating with the outdoors or communicating with the outdoors through vertical ducts...

Page 14: ...nd to the requirements of the local code authority having jurisdiction Good practice requires that all heavy piping be supported VENTING A TYPICAL BOILER INSTALLATION FIGURE 7 VENTING THE BOILER STAND...

Page 15: ...lid fuel burning equipment This practice is prohibited by many local building codes as is the practice of venting gas fired equipment to the duct work of ventilation systems Where a separate vent conn...

Page 16: ...verter and vent pipe running to the chimney Check parts and chimney for obstructions and clean as necessary 3 Remove burner from boiler and other metal parts as required to clean and vacuum the heat e...

Page 17: ...ld and Common Vent Diameter in Inches 2 1040 16 16 14 14 14 14 12 12 12 3 1560 20 18 18 16 16 14 14 14 14 4 2080 22 22 20 18 18 18 16 16 14 5 2600 26 24 22 20 20 18 18 18 18 6 3120 28 26 24 22 22 20 2...

Page 18: ...systems have been designed to provide efficient trouble free operation of the boiler sizes covered in this manual with any of the following conditions a Unknown system flow rate b Varying flow rate as...

Page 19: ...installed with the replacement boiler s Make up water connections and accessories are not shown SCHEMATIC OF THE LINEAR TEMP SYSTEM FIGURE 12 Supply and return headers of the old system should be con...

Page 20: ...THE WARRANTY Constant water flow through the unit will wash away the copper s natural protective coating This is called velocity erosion This erosion is not as great a problem when intermittent circul...

Page 21: ...iping system When table 7 is to be used to select the piping size calculate the gas demand in terms of cubic feet per hour for each piping system outlet The gas demand for an appliance can be found by...

Page 22: ...e of 1 000 Btu per cubic foot Solution 2 HW 420 Boilers 840 000 Btuh 2 HW 610 Boilers 1 220 000 Btuh Total Btuh Input 2 060 000 Btuh Total Btuh Input 2 060 000 Btuh 2 060 cf h Btu per Cubic Foot of Ga...

Page 23: ...LOCAL REGULATIONS The boiler when installed must be electrically bonded to ground in accordance with the requirements of the authority having jurisdiction or in the absence of such requirements with t...

Page 24: ...VALVE COIL LIMIT GND 4 X 4 JUNCTION BOX WITH TERMINAL STRIP WHITE GAS VALVE BROWN IGNITION MODULE WHITE YELLOW WHITE RED MV MV PV PV 24V GND GND GND SPARK TO PILOT 24V MV PV MV PV MV PV MV PV THERMAL...

Page 25: ...will normally require an automatic shutdown control if there is a continuous recirculating main and or if the entire building is not under control of space temperature thermostats A single bulb outdo...

Page 26: ...BOILER LINEAR TEMP INSTALLATION WITH TWO CIRCULATORS FIGURE 18 CONTROL APPLICATION DIAGRAM THREE BOILER LINEAR TEMP INSTALLATION WITH THREE CIRCULATORS FIGURE 19 NOTE 1 Building temperature controls...

Page 27: ...ng controls 3 Outdoor thermostat required if building controls do not provide automatic shutdown of reset controls during warm weather Boilers and Secondary Circulator are Controlled by Dual Bulb Dual...

Page 28: ...INSTALLATION FOR HOT WATER SUPPLY APPLICATION CANADIAN MODELS JUNCTION BOX W 6 TERMINALS FIGURE 21 FIGURE 23 CER TEMP 80 1 UNIT INSTALLATION FOR HOT WATER SUPPLY APPLICATION U S MODELS JUCNTION BOX W...

Page 29: ...29 CER TEMP 80 2 OR 3 UNIT INSTALLATION FOR HOT WATER SUPPLY APPLICATION CANADIAN MODELS JUNCTION BOX W 6 TERMINALS FIGURE 24...

Page 30: ...30 SCHEMATIC CANADIAN MODELS JUNCTION BOX W 6 TERMINALS FIGURE 25...

Page 31: ...31 CER TEMP 80 2 OR 3 UNIT INSTALLATION CONNECTION DIAGRAM FOR HOT WATER SUPPLY APPLICATION U S MODELS JUNCTION BOX W 4 TERMINALS FIGURE 26...

Page 32: ...32 CER TEMP 80 2 OR 3 UNIT INSTALLATION SCHEMATIC DIAGRAM FOR HOT WATER SUPPLY APPLICATION U S MODELS JUNCTION BOX W 4 TERMINALS FIGURE 27...

Page 33: ...ES 16 and 17 on pages 24 and 25 INSTALL IN ACCORDANCE WITH ALL LOCAL CODES ONE HW 300 HW 399 HW 420 HW 520 HW 610 OR ONE HW 670 UP FLOW MODEL COMMERCIAL BOILER WITH VERTICAL TANK USE THIS TABLE FOR CO...

Page 34: ...GE PRESSURE RELIEF VALVE RATING SHOULD NOT EXCEED PRESSURE CAPACITY OF ANY COMPONENT IN THE SYSTEM INSTALL THERMOMETER AND PRESSURE RELIEF IN OPENINGS PROVIDED ON HW 520 HW 610 HW 670 DANGER TEMPERATU...

Page 35: ...TEM INSTALLTHERMOMETERAND PRESSURE RELIEF IN OPENINGS PROVIDED ON HW 520 HW 610 HW 670 WIRING FIGURES 21 to 27 on pages 28 to 32 HEATERS SPACED 30 APART INSTALL IN ACCORDANCE WITH ALL LOCAL CODES FIGU...

Page 36: ...ANY COMPONENT IN THE SYSTEM INSTALL THERMOMETER AND PRESSURE RELIEF IN OPENINGS PROVIDED ON HW 520 HW 610 HW 670 DANGER TEMPERATURE SETTING SHOULD NOT EXCEED SAFE USE TEMPERATURE AT FIXTURES SEETANKT...

Page 37: ...URE CAPACITY OF ANY COMPONENT IN THE SYSTEM INSTALLTHERMOMETERAND PRESSURE RELIEF IN OPENINGS PROVIDED ON HW 520 HW 610 HW 670 FIGURE 32 WIRING FIGURES 21 to 27 on pages 28 to 32 INSTALL IN ACCORDANCE...

Page 38: ...ITY OF ANY COMPONENT IN THE SYSTEM INSTALLTHERMOMETERAND PRESSURE RELIEF IN OPENINGS PROVIDED ON HW 520 HW 610 HW 670 WIRING FIGURES 21 to 27 on pages 28 to 32 HEATERS SPACED 24 APART INSTALL IN ACCOR...

Page 39: ...g of radiators or convectors PRECAUTIONS If the unit is exposed to the following do not operate boiler until all corrective steps have been made by a qualified serviceman 1 Flooding to level of burner...

Page 40: ...12mm of the sensing probe tip See Figure 35 FIGURE 35 Check for good terminal connection at the sensing probe at the pilot burner assembly if pilot does not light Check for electrical power to the val...

Page 41: ...6 of the OPERATING INSTRUCTIONS 6 Remove the pressure gauge or manometer from the manifold pressure tapping Replace the screw in plug in the manifold pressure tap 7 Repeat steps 7 thru 11 of the OPER...

Page 42: ...M After 15 sec ignition shut down 5 minute time delay before re try S 8600H After 15 sec ignition system locks out must be manually reset FLAME CURRENT SENSED Spark generator off Second valve operator...

Page 43: ...OSITION FIGURE A ON OFF ON POSITION FIGURE B GAS VALVE CONTROL KNOB HONEYWELL GAS VALVE A B FIGURE C PILOT PILOT FIRING VALVE HANDLE OFF POSITION FIGURE D PILOT HANDLE ON POSITION LIGHTING INSTRUCTION...

Page 44: ...URN MAIN FIRING VALVE COUNTER CLOCKWISE TO OFF FIG C A ND T URN PILO T FIRING VALVE COUNTERCLOCKWISE T O OFF FIG E 4 SET T HE THERMOSTAT TO LOWWEST SETTING 1 STOP READ THE SAFETY INFORMATION ABOVE ON...

Page 45: ...ee from lint and debris Sweeping the floor around the boiler should be done carefully This will reduce the dust and dirt which may enter the burner and pilot air passages causing improper combustion a...

Page 46: ...and impellers It is recommended that after installation the boiler and system when filled should include the proper percentage of cleaning solution related to approximate water volume of the system Fi...

Page 47: ...mostat 20 F 10 C above tank water temperature Circulating pump and burner on Circulating pump on High limit control set too low Replace If problem proven to be at this control by applying jumper to te...

Page 48: ...ceramic insulator surrounding the electrode cracked or broken Replace pilot burner assembly Replace ignition module Turn on gas supply Turn on power supply Securely connect cable and or ground wire Ca...

Page 49: ...ly attached to pilot assembly and GND terminal on module Are ignition cable and ground wire in good condition not brittle burnt or cracked Ensure ground strap is the closest metal to the igniter senso...

Page 50: ...iter sensor rod in good condition not broken or cracked Is the igniter sensor rod in good condition not worn corroded sooted or damaged Replace ignition module Correct the situation by consulting the...

Page 51: ...ground wire firmly attached to the pilot assembly and GND terminal on module Are high voltage cable and ground wire in good condition not brittle burnt or cracked Make sure pilot flame spreader hood i...

Page 52: ...Normal Flame Signal not applicable 2 Weak Flame Signal Sytem will operate reliably but flame signal is less than desired NOTE This indication may flash temporarily during or shortly after lightoff on...

Page 53: ...cks damage or tracking 8 Low secondary voltage supply below 15 5 Vac Control remains in wait mode When the fault corrects control resumes normal operation after a one minute delay Check transformer an...

Page 54: ...tion after a one minute delay Check transformer and AC line for proper input voltage to the control Check with full system load on the transformer 6 2 Failed trial for ignition resulting in lockout Re...

Page 55: ...part from the nearest distributor and returning the claimed defective part to such distributor c All cost necessary or incidental for any materials and or permits required for installation of the repl...

Page 56: ...500 Tennessee Waltz Parkway Ashland City TN 37015 Technical Support 800 527 1953 Parts 800 433 2545 Fax 800 644 9306 www hotwater com...

Reviews: