B. Before testing new floor mats or newly installed floors, 

clean mats/floors per manufacturer's recommendations. 
For testing of floor finishes or monitoring of existing 
floor materials, test in an as-is condition.

C. Perform tests at ambient humidity.

D. Place the Instrument and test weight at the desired test 

location.

E. Connect one lead of the meter to ground with supplied 

clip and the other lead to the test weight.

F. Set meter to 100V.  Place test weight on the surface of 

the material being tested.

G. Push test button and record the resistance after the 

measurement has stabilized or after 15 seconds.  Release 
test button.

H. Repeat the procedure placing the test weight on the 

surface at different locations.

I. Perform a minimum of five tests per contiguous floor 

surface material or a minimum of five tests per 5,000 
square feet (464,5 m

2

) of floor material, whichever is 

greater.  A minimum of three of the five tests should be 
conducted in those areas that are subject to wear or have 
chemical or water spillage or are visibly dirty.

TEST PROCEDURE FOR RESISTANCE 
POINT TO POINT

A. Complete BATTERY TEST and CONTINUITY TEST.

If required clean electrodes as described in Test Weight 
Cleaning section below.

B. Before testing new floor mats or newly installed floors, 

clean mats/floors per manufacturer's recommendations.
For testing of floor finishes or monitoring of existing 
floor materials, test in an as-is condition. 

C. Perform tests at ambient humidity.

D. Place the Instrument and test weight at the desired test 

location.

E. Connect test leads of the meter to the test weights.

F. Set meter to 100V. Place test weights three feet apart on 

the surface of the material being tested.

G. Push test button and record the resistance after the 

measurement has stabilized or after 15 seconds. Release 
test button.

H. Repeat the procedure placing the test weights three feet 

apart on the surface at different locations.

I. Perform a minimum of five tests per contiguous floor 

surface material or a minimum of five tests per 5,000 
square feet (464,5 m

2

) of floor material, whichever is 

greater. A minimum of three of the five tests should be 
conducted in those areas that are subject to wear or have 
chemical or water spillage or are visibly dirty.

MAINTENANCE

GENERAL

This section details the maintenance which may be
performed by the user. 

Performance by the user of any

maintenance not specified here will void the Instrument
warranty

. If it is determined that maintenance beyond the

scope of this section is required, contact your local 3M sales
representative or call 3M Technical Service (Electronic
Handling & Protection Division) at 512-984-3200.

BATTERY REPLACEMENT

Before attempting to replace either battery, place the main
selector switch in the OFF position. 

The circuitry enclosed in the Model 701 produces high
voltages. Make sure that the main selector switch is in the OFF
position before removing the back cover.

A. To open the back cover, remove the screw located in the 

center of the back cover.

B. The batteries are held in place by a metal bracket at the 

top of the Instrument. To release this bracket, turn the 
screw located in the center of the bracket counter 
clockwise until the bracket swings free. The batteries 
will now slide out.

C. Install new batteries as shown in Figure 6-1.

Improper battery installation will damage this Instrument.

D. Replace bracket and tighten bracket screw. Replace back 

cover and cover screw.

TEST WEIGHT CLEANING

The test probes included in this kit are heavy. Exercise care in
handling.

After a period of use, the conductive rubber pads on the test
weights may become soiled, causing the weight to fail the
CONTINUITY TEST. To clean the surface of the
conductive pad, use a 70% Isopropyl alcohol/water mixture
on a clean low-linting cloth. Allow surface to “air dry” 15
minutes before use.

ZERO ADJUSTMENT

On occasion, due to handling, vibration, or other causes, the
pointer on the Model 701 may need adjustment. To zero the
pointer, turn the main selector switch to the OFF position.
Place the Instrument on a level stable surface and turn the
mechanical zero adjust screw until the pointer is over the
left-most mark on the OHMS scale.

Figure 6-1: Battery Replacement

5

Summary of Contents for 2290

Page 1: ...Operator s Manual 701 Test Kit for Static Control Surfaces Megohmmeter ...

Page 2: ... either of two test voltages verify proper Instrument performance and check the electrical continuity of the test set up ACCESSORIES All accessories required for operating the Model 701 are included in the test kit Available replacement parts are listed on page 6 UNPACKING AND INSPECTION Examine the shipping carton for obvious signs of damage If damage is suspected open the carton and inspect the ...

Page 3: ...onds and then read the resistance from the OHMS scale After all readings have been completed return the Main Selector Switch to the OFF position RESISTIVE CHARACTERIZATION OF STATIC CONTROL WORK SURFACES GENERAL This section provides a summary of the types of surface measurements specified and described by ESD S4 1 Measurements are performed for three reasons 1 Periodic performance testing of inst...

Page 4: ...ings are above 1x109 ohms the static control surface may be dirty Clean the surface using the manufacturer s recommended cleaning procedure followed by two clear water rinses and a rinse with 70 Isopropyl alcohol Allow the surface to dry overnight and retest If the resistance reading is infinite there is an interruption open in the ground connection repair and retest 2 QUALIFICATION OF INSTALLED S...

Page 5: ... building ground or other suitable ground If you have questions concerning the correct ground refer to EOS ESD Standard 6 0 and or contact a qualified electrician The Resistance to Ground test is the most important test that can be done on a static control surface because it verifies that the surface is working correctly and will drain a static charge in a reasonable time This test involves measur...

Page 6: ...of five tests per 5 000 square feet 464 5 m2 of floor material whichever is greater A minimum of three of the five tests should be conducted in those areas that are subject to wear or have chemical or water spillage or are visibly dirty MAINTENANCE GENERAL This section details the maintenance which may be performed by the user Performance by the user of any maintenance not specified here will void...

Page 7: ...lative humidity up to 90 for altitudes up to 2000m unless otherwise noted Pollution degree 2 class 3 equipment Resistance Ranges Test Measurement Open Circuit Internal Function Range Voltage Resistance Continuity 0 to 10 M 10V 7V 500 10V Surface 105 to 1011 10V 7V 2 100V Surface 105 to 1011 100V 7V 2 Measurement Accuracy 5 2 of arc Measured internally at voltage source Battery Test Internal test o...

Page 8: ...prohibited by law 3M will not be liable for any loss or damage arising from this 3M product whether direct indirect special incidental or consequential regardless of the legal theory asserted Shipping of Warranty Returns Pack the Instrument carefully and ship it prepaid and insured to the proper destination noted below DO NOT RETURN ANY ITEM WITHOUT HAVING FIRST RECEIVED RETURN AUTHORIZATION FROM ...

Reviews: