Inerting the manufacturing chamber
The machine needs a gas to create an inert atmosphere in the manufacturing chamber . This cover gas inhibits any potential
rapid combustion of particulate matter during the process .
The inerting is required for oxidizable or flammable materials, and for better build quality.
When launching, the inerting process will automatically perform the 2 following phases in this order :
manufacturing chamber inerting at first, then external filter vessel inerting. Make sure the filter is well
connected to the printer before starting the inerting process .
To perform the inerting, follow the instructions of the Preparation Assistant "Step 8 : Loading of the manufacturing file and
The start of manufacturing shall be carried out only when the oxygen level is below the required value .
START A MANUFACTURING PROCESS
WARNING: THE MANUFACTURING CHAMBER AND PROCESS FILTER MUST BE INERTED BEFORE STARTING
ANY JOB . REFER TO SECTION "INERTING THE MANUFACTURING CHAMBER" ON PAGE 63 .
Operations described below complement instructions from the "Manufacturing menu" on page 47 .
When all the steps of the machine preparation have been completed, the start procedure of a job is as follows:
•
Run the sintering of layer #0 .
•
Run the layering of layer #1 . Repeat this operation if the layer obtained is not correct (lack of powder for example) .
•
Run the sintering of layer #1 .
•
Run the layering of layer #2 . Repeat this operation if the layer obtained is not correct (lack of powder for example) .
•
Continue step by step as described above, up to layer #5 .
•
If all five layers completed successfully on the first try, then start the full manufacturing in automatic mode.