ZXG10 iBSC Hardware Installation Guide
9.
Horizontal cabling trough
10. Fan Subrack (L5)
11. Service Subrack (L6)
12. Horizontal cabling trough
13. Service Subrack (L7)
14. Horizontal cabling trough
15. Fan Subrack (L8)
16. Busbars
6.2.2 Installing External Power Cable
Steps
1.
Based on engineering design requirements, determine the post connected with ZXG10
iBSC cabinet in DC power distribution cabinet.
2.
Measure the distance from DC power distribution cabinet to the filter on the top of
ZXG10 iBSC cabinet.
3.
Depending on measured data, cut a power cable and grounding cable with proper
length.
Caution!
Remain some margins while cutting the cable.
4.
Make cooper lug at two ends of the cable and paste temp label for identification.
5.
Remove the filter cover on the top of cabinet, as shown in
6-8
SJ-20110531095035-004|2011-10-28 (R2.0)
ZTE Proprietary and Confidential