ZXG10 iBSC Hardware Installation Guide
1.
Installation Preparations
Installation preparation is the efforts prior to equipment installation, the prerequisite of
equipment installation.
2.
Installing the Cabinet
Carry out cabinet installation first. If raised floor is employed in the equipment rooms,
the cabinet is to be installed on a support; in case of cement floor, the cabinet can be
fixed directly on the cement floor.
3.
Installation of shelves and boards
Then proceed with the installation of shelves and boards. If the shelves and boards
are packed together with the cabinet, just check whether the shelves and boards are
firmly fixed and whether the connecting cables are firmly in position. If the shelves
and boards are separately packed (for example, installation for capacity expansion),
they need to be installed on the site. Verify that the connections of cables meet the
requirement, the installation position is correct and the installation method complies
with the installation flow chart.
4.
Grounding and cable connection
Then lay the cables, including power cables, grounding cables, optical fibers and
Ethernet cables. After laying the cables, paste engineering labels on the cables.
5.
Installation of peripherals
Finally carry out the installation of the peripherals, including the installation and
connection of the alarm box and the background terminal system.
6.
Hardware Installation Check
Upon completion of the installation, carry out hardware installation check. If any item
is not satisfactory, improvement measures must be taken until all the requirements are
met.
2.2 Precautions
Warning!
Non-professionals shall not install or debug the equipment individually, unless instructed
by professionals on site.
1.
Prior to installation, the user shall carefully read this manual and relevant configuration
manuals and shall strictly install the equipment according to the flow process and
specification in this manual.
2.
The person who installs ZXG10 iBSC equipment shall have been trained in relevant
trainings about communication equipment and mastering familiar installation
technology.
2-2
SJ-20110531095035-004|2011-10-28 (R2.0)
ZTE Proprietary and Confidential
Содержание ZXG10 iBSC
Страница 8: ...II ...
Страница 167: ...Figures Figure 11 7 Step 3 of Board Unplugging 11 5 V ...
Страница 168: ...Figures This page intentionally left blank ...