Model Pool and Spa Heater by Zodiac
®
(1.2 m) horizontally from, or 1 ft (300 mm) above any
door, operable window, or gravity inlet into any build-
ing. In Canada, the heater must be installed so that the
exhaust point of the heater is at least 10 feet (3.0 m)
from any building opening. See Figure 3.
WARNING
United States
Do not install the heater with the top of the vent
assembly within 4 feet (1.22 m) horizontally, 4 feet
(1.22 m) below or less than 1 ft (300 mm) above of
any opening into a building.
Canada
Do not install the heater with the top of the vent as-
sembly within 10 feet (3.05 m) of any opening into a
building.
AVERTISSEMENT
Lorsque vous installez l’appareil de chauffage,
assurez-vous que l’ouverture d’aération se trouve à
un minimum de 10 pieds (3.05 m) de toute ouver-
ture d’un bâtiment.
The top surface of the heater must be at least 3
feet (0.9 m) above any forced air inlet, or intake ducts
located within 10 (3.0 m) feet horizontally.
If the heater is installed under an overhang, there
must be a minimum clearance of 5 feet (1.5 m) above
the top of the heater and the structure should not over-
hang the heater more than 12 inches (0.30 m). The area
under the overhang must be open on three (3) sides.
This prevents combustion gases from being diverted
into living areas through doors, windows, or gravity
inlets.
Ne pas installer ce chauffe-piscine sous une
saillie mesurant moins de 3 pi de hauteur. La partie
sous la saillie doit être ouverte sur 3 côtés.
Figure 3. Outdoor Heater Installation
If the heater is installed close to a structure, pro-
tect it from rain water runoff with rain gutters on the
roof or other measures. Do not locate the heater near
irrigation sprinkler systems that could spray water on
it. Water from sprinklers may cause damage to controls
and electronic components.
In Florida, it is required that the heater be secure-
ly fastened to the equipment pad. Use a size
1/4" x 2-1/4" long galvanized or plated concrete
screws and washers at each of the four (4) tabs located
at the base of the heater. Mounting the appliance in
this manner meets the applicable requirements of the
Florida Building Code.
Mounting screws are not provided with this
heater. After placing the heater on the equipment pad,
drill a hole in the concrete at each of the four (4) tabs
on the feet of the heater. (The correct size drill bit is
usually provided with the concrete screws when pur-
chased). Place a screw in each of the holes and fasten
the heater to the equipment pad, see Figure 4.
Do not
over-torque the screws.
Other jurisdictions may have
similar requirements. Please check your local codes for
relevant details.
1/4” X 2-1/4”
GALVANIZED OR PLATED
CONCRETE SCREWS
Figure 4. Anchor Heater To Equipment Pad
2.3.5 Indoor and Outdoor Shelter
Installations
An outdoor shelter (Canada only) is an unoccu-
pied enclosure which does not communicate directly
with occupied areas. All indoor installations and
outdoor shelter installations require a factory approved
vent collar. The vent collar must be installed without
modification and in accordance with the instructions
provided by the manufacturer. For sidewall venting, a
side vent kit is available from your Zodiac distributor.