STANDARD OPERATING PROCEDURE 
String Inverter Installation – Zeverlution Series 

 

Version 1.2 Effective date 02/08/2017

 

 

Page 11 of 15 

An AC isolator must be installed adjacent to the inverter if the inverter is more than 3 meters away 
from the switchboard or it is out of line of sight. The AC isolator must have a current rating equal to 
or greater than the MCB current rating.  

 

MCB’s must be sized correctly according to the cable cross section used to connect the inverter 
to the switch board. Please refer to the inverter datasheet or sections 5.2.1 and 5.2.2 to determine 
the appropriate MCB rating. 

 

 

 

SYSTEM COMMISSIONING 

 

Commissioning Tests 

 

 

 

It is extremely important that all mandatory tests are done before commissioning the PV system. 
Please make yourself familiar with Appendix D of AS/NZS 5033:2014 and follow the instructions 
outlined in the standard. 
Attached to this document you’ll find a commissioning sheet which you may use to record the test 
results. A completed and signed copy of the commissioning sheet together with the CCSC must 
be provided to solarcity.  

 

 

 

Grid Protection Settings 

AS4777.2:2015 defines specific grid protection requirements for New Zealand. Before 
commissioning the PV system, you must ensure that the inverter is set to the correct standard.  
 

6.2.1

 

Adjusting grid protection settings using the inverter display 

 

To change these settings, the inverter must be powered by DC only. 
Keep in mind that the inverters need a minimum DC input power of 30Watts from the array to start 
up. If the irradiance is insufficient in the late evening, you might not be able to access the inverters 
settings menu. 

 

 

1.

 

With the AC isolator turned off, turn on the DC 
isolator(s) and wait for the inverter to start. This 
may take a few seconds. The display will show an 
error code. 
 

 

Содержание Zeverlution 2000S

Страница 1: ...2 BEHAVIOURAL 2 SAFETY 2 INSTALLATION PROCEDURE 3 String Design Guidelines 3 5 1 1 String Layout Without Optimisers 3 5 1 2 String Layout with Optimisers 3 5 1 3 Shading 3 5 1 4 Maximum String Voltage...

Страница 2: ...d electrical part of the inverter installation instruction The focus of this SOP lies on the physical installation of Zeverlution 2000s and Zeverlution 4000 inverters and any associated switch gear DC...

Страница 3: ...4000 inverters and for arrays with or without optimisers the minimum and maximum strings lengths are as follows minimum number of modules per string is 3 maximum number of modules per string is 10 5 1...

Страница 4: ...systems with a peak output between 1 5kWp and 3kWp 6 to 10 modules where the peak performance rating per panel at STC does not exceed 295Wp For further details please refer to the Zeverlution 2000s da...

Страница 5: ...et which is used to fix the units to a suitable wall Please refer to the solarcity wall cladding guide for suitable wall claddings to mount the inverter on 1 Use the wall bracket as a drilling templat...

Страница 6: ...ble The inverter must not be installed in a location where it is exposed to direct sunlight Wiring 5 3 1 DC Wiring All wiring must be installed and sized in accordance with the relevant requirements o...

Страница 7: ...ted as per AS5033 The table below shows the maximum cable length one way between array and inverter with JA 290W panels allowing for a 2 voltage drop Panels per string 3 4 5 6 7 8 9 10 Max cable lengt...

Страница 8: ...to maintain the correct polarity the connectors are also marked with and symbols The steps below explain how to assemble SUNCLIX connectors Ensure that the array cable is de energized before installin...

Страница 9: ...lled on an appropriate roof penetration kit must be used Roof penetrations must always be located under the solar panels where an attic space is accessible for the cable run Where cable s pass through...

Страница 10: ...mm which is usually too short for leapfrog wiring Please use standard daisy chain wiring for all optimised array sections 5 3 3 AC Wiring The inverter is connected to the switchboard using double insu...

Страница 11: ...S 5033 2014 and follow the instructions outlined in the standard Attached to this document you ll find a commissioning sheet which you may use to record the test results A completed and signed copy of...

Страница 12: ...To confirm wait for approximately 10 seconds until the inverter automatically returns to the initial display showing the error code Connecting the inverter to the Internet The inverter needs to be co...

Страница 13: ...before setting up the WIFI connection 2 With the inverter powered up use a smartphone or laptop to search for the inverter s wireless access point This will display as ZEVERSOLAR XXXX Connect to this...

Страница 14: ...omer s wireless network 6 After approximately one minute the inverter should connect to the customers wifi network and the status indicator on the wireless page will show a green tick 7 Take a photo o...

Страница 15: ...rnet cable through the comms gland on the bottom of the inverter ensuring that the cable entry is sealed from dust and moisture 3 The inverter automatically obtains an IP address from the router via D...

Страница 16: ...rod MEN link removed Earth continuity 2 Main earth conductor to array frame Polarity check and PV open circuit voltage Polarity Voltage V String 1 String 2 if applicable PV array at switch disconnect...

Отзывы: