Web Server
~
26
~
The Fig. 6-6 Set parameters based on the AC capacity
Table 6-1: The indicator of the Item
Parameter Definition
a
The sum of the rated power of all inverters in the PV
plant (Wac)
b
The percentage of power output limitation based on
parameter b
Power Limitation Based on the Energy Meter Reading
In this method the export power of the PV system at the point of connection will
not exceed the set value. For example, if 0 kWac export limit has been set in
“limit output power based on the energy meter reading ” then a 33 kWp PV
system connected to Zeverlution Pro 33K(33 kWac inverter) will reduce its AC
output power to ensure the export power at the smart meter won’t exceed 0
kWac.
Fig. 6-7
shows the system diagram of power limitation based the energy meter
reading.
Example for 0-export setting:
Please make sure all wire connection is correct before doing the settings on web
server.
Step 1: Tick “Active Power Limit” and fill in the total Inverter AC capacity to active
Power limit function.