24
Corona process | User Manual
Installing the measuring system
Corona process
4.3 Connecting system components
Warning
ELECTRICAL ENERGY HAZARD
Make sure that the power supply is disconnected.
The entire measuring system must be switched free of voltage.
•
Use only original parts supplied by Carl Zeiss Spectroscopy GmbH
(see Section 7.4 “Accessories and spare parts” on page 55).
•
Have the following tools ready:
– Open-end wrench, 22 mm A/F
(for the union nut on the connector or on the protective cap)
1
Use the Ethernet cable
1
to connect the
Corona process
with your
computer.
Note
The length of the Ethernet cable must be less than 100 m (max. 80 m is
recommended) or a switch must be interposed.
To prevent communication problems, the use of a second network card
for the Corona process is recommended.
2
If required, you can connect up to four digital inputs/outputs via the "Digital
IN OUT" port.
First remove the protective cap
2.1
from the "Digital IN OUT" port.
Then connect the Digital - IN / OUT cable
2
.
3
Use the power supply cable
3
to make a connection between the
Corona process
and a safety extra-low voltage source of 12 – 24 V DC
(power consumption = 40 W, inrush current < 4 A).
Note
The minimum diameter is AWG 16 for a cable length of 15 m.
With a voltage of 12 V DC, we recommend a max. length of 3 m (for
accessories, see Section 7.4 “Accessories and spare parts” on page 55).
Requirements
Procedure