3.1.
Installation process
Figure 7 - Installation steps
3.2.
Checks before installation
Checking the outer packaging
Packaging materials and components may be damaged during transport. Therefore, please check the
materials of the outer packaging before installing the inverter. Check the surface of the box for external
damage such as holes or tears. If any kind of damage is found, do not open the box containing the inverter
and contact the supplier and transport company as soon as possible.
It is recommended to remove the packaged materials from the box 24 hours before installing the inverter.
Checking the product
After removing the inverter from its packaging, check that the product is intact and complete. If any damage
is found or components are missing, contact the supplier and transport company.
Contents of the packaging
Carefully check the contents of the packaging before installation, making sure that no element inside the
packaging is missing or damaged.
The package should contain the following components:
No.
Pictures
Description
Quantity
1
AZZURRO 3PH 100-136KTL-HV
1 PCS
2
Rear Panel
1 PCS
3
PV+ input connector
100KTL 20PCS
125KTL 20PCS
136KTL 24PCS