SECTION 5 - COMMISSIONING
FORM 155.30-ICOM2.EN.UL
ISSUE DATE: 12/21/2018
5
Chiller
Chilled Water Pump
Sequential
Operation
AND
Air Conditioner
Cooling Water Pump
Cooling Tower
.
AND
Interlock
Sequential
Operation
(2)
(3)
Sequential
Operation
Interlock
Other interlocks, including earthquake sensor, abnormal room temperature sensor, and so on.
NOTES:
1
. Be sure to implement sequential operation of the chilled water pump, the cooling water pump, and the hot water pump from the chiller.
2. If there is only one air conditioner, secure interlock for the air conditioner operation (the part indicated by broken lines).
3. Implement sequential operation in such a way that when the chilled water pump stops, the cooling water pump, and the hot water pump
also stop.
4. If the hot, chilled and cooling water system is the common system, you must install the isolation valve on the hot water, chilled water and
cooling water inlet pipe entering the chiller, and interlock these isolation valves with the chiller control panel. It is important for safe and
reliable operation of the chiller as well as to prevent potential crystallization of lithium bromide solution and freezing of the evaporator tubes.
AND
Sequential
Operation
Hot Water Pump
Interlock
FIGURE 45 -
SEQUENTIAL OPERATION FLOWCHART
Not completed
AND
Chiller dilution
operation begins
Chiller dilution
operation completed
Stop the absorption
chiller
Completed
Air conditioner and
chilled water pump stop
NOTE:
1. Verify that the air conditioner has stopped after the chiller dilution operation is complete. Otherwise, the chiller may become damaged due to
freezing of the chilled water and/or crystallization of the solution.
2. The installation and interlocking of these valves with the chiller control panel is mandatory for safe and reliable operation of the chiller
and to prevent potential crystallization of lithium bromide solution and freezing of the evaporator tubes.
3. Close the hot water supply manual valve.
Stop the air
conditioner
FIGURE 46 -
STOP THE ABSORPTION CHILLER FLOWCHART
Содержание YHAU-CL Series
Страница 14: ...JOHNSON CONTROLS 14 FORM 155 30 ICOM2 EN UL ISSUE DATE 12 21 2018 THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 20: ...JOHNSON CONTROLS 20 FORM 155 30 ICOM2 EN UL ISSUE DATE 12 21 2018 THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 47: ...JOHNSON CONTROLS 47 SECTION 4 TECHNICAL DATA 4 THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 102: ...JOHNSON CONTROLS 102 FORM 155 30 ICOM2 EN UL ISSUE DATE 12 21 2018 THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 128: ...JOHNSON CONTROLS 128 FORM 155 30 ICOM2 EN UL ISSUE DATE 12 21 2018 THIS PAGE INTENTIONALLY LEFT BLANK...