SECTION 5 - COMMISSIONING
GENERAL GUIDELINES FOR USE
Before Operation
Charge the solution and the refrigerant water if the solution and refrigerant water is in the
barrels during the delivery.
During commissioning, check the motor’s rotating direction of the solution pump, refrigerant
pump, and purge pump.
The rotation direction can be tested by using a rotation detector (Bell and Gosset or WILO
DKG). If a rotation detector is not available, use the procedure shown below:
1. Remove the plugs at the solution and refrigerant sampling valves.
2. Make sure the valves are completely closed.
3. Confirm that the absorber and refrigerant tank contain enough solution and refriger-
ant.
4. Connect a compound gauge (NPT 1/2 of an inch) to the sampling valve with Teflon
tape.
5. Operate the pump.
6. Open the valve.
7. Read and record the delivery pressure of the solution pump and the refrigerant pump.
8. Close the valve.
9. Check the pressure readings, see
to see if your pump rotation
is in the right direction. The correct direction shows a higher discharge pressure.
10. Remove the compound gauge.
11. Put the plugs back on the valves.
12. Clean the gauge with water.
13. For refrigerant, confirm the correct rotation by looking at the refrigerant spray through
the sight glass.
NOTE: The flow of fluid cannot be seen because the solution and refrigerant pumps are
hermetically sealed.
CAUTION: Do not run the solution pump without solution. Do not run the refrigerant
pump without refrigerant water .
NOTE: The gauge scale must be -760 mm Hg. to 2 Kg. / cm2g, or -30 inches Hg. to 30
psig. To prevent corrosion of the gauge, clean it thoroughly, and check it for leaks after
each use.
NOTE: The delivery pressure reflects the high vacuum condition of the machine. If the
inside pressure is atmospheric, add 1.0 kg / cm (14.3 psig) to the standard value found
in
Table 29 on page 76.
Содержание YHAU-CGH
Страница 14: ...FORM 155 32 ICOM2 EN UL ISSUE DATE 1 10 2018 14 JOHNSON CONTROLS THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 38: ...FORM 155 32 ICOM2 EN UL ISSUE DATE 1 10 2018 38 JOHNSON CONTROLS THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 55: ...FORM 155 32 ICOM2 EN UL ISSUE DATE 1 10 2018 JOHNSON CONTROLS 55 THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 57: ...FORM 155 32 ICOM2 EN UL SECTION 4 TECHNICAL DATA ISSUE DATE 1 10 2018 JOHNSON CONTROLS 57 LD27463...
Страница 59: ...FORM 155 32 ICOM2 EN UL SECTION 4 TECHNICAL DATA ISSUE DATE 1 10 2018 JOHNSON CONTROLS 59 LD27465...
Страница 61: ...FORM 155 32 ICOM2 EN UL SECTION 4 TECHNICAL DATA ISSUE DATE 1 10 2018 JOHNSON CONTROLS 61 LD27471...
Страница 63: ...FORM 155 32 ICOM2 EN UL SECTION 4 TECHNICAL DATA ISSUE DATE 1 10 2018 JOHNSON CONTROLS 63...
Страница 65: ...FORM 155 32 ICOM2 EN UL SECTION 4 TECHNICAL DATA ISSUE DATE 1 10 2018 JOHNSON CONTROLS 65 LD27477...
Страница 67: ...FORM 155 32 ICOM2 EN UL SECTION 4 TECHNICAL DATA ISSUE DATE 1 10 2018 JOHNSON CONTROLS 67 LD27479...
Страница 69: ...FORM 155 32 ICOM2 EN UL SECTION 4 TECHNICAL DATA ISSUE DATE 1 10 2018 JOHNSON CONTROLS 69 LD27475...
Страница 160: ...FORM 155 32 ICOM2 EN UL ISSUE DATE 1 10 2018 160 JOHNSON CONTROLS THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 170: ...FORM 155 32 ICOM2 EN UL ISSUE DATE 1 10 2018 170 JOHNSON CONTROLS THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 172: ...FORM 155 32 ICOM2 EN UL ISSUE DATE 1 10 2018 172 JOHNSON CONTROLS THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 181: ...FORM 155 32 ICOM2 EN UL APPENDIX 1 CHECKLIST ISSUE DATE 1 10 2018 JOHNSON CONTROLS 181 NOTES...