FORM 155.32-ICOM2.EN.UL
SECTION 9 - DECOMMISSIONING, DISMANTLING, AND DISPOSAL
ISSUE DATE:1/10/2018
JOHNSON CONTROLS
171
SECTION 9 - DECOMMISSIONING, DISMANTLING,
AND DISPOSAL
Unless otherwise indicated, the operations described below can be performed by any
properly trained maintenance technician.
1. Isolate all sources of electrical supply to the unit, including any control system supplies
switched by the unit. Make sure that all points of isolation are secured in the OFF po-
sition.
2. Disconnect and remove the supply cables. For connection points, see
3. Fill the interior of the unit with N2 gas to pressurize up to approximately 1.5 ~ 3PSI
(0.01~0.02 MPa.G.).
4. Prepare a suitable container. See
and
the remainder of the solution and refrigerant in the unit from each service valve as
completely as possible into a container. Dispose of them in a suitable and safe man-
ner.
5. Isolate the unit heat exchanger from the external water systems and drain the heat
exchanger section of the system. If no isolation valves are installed it may be neces-
sary to drain the complete system.
6. If glycol was used in the water system, or chemical additives are contained, dispose
of the solution in a suitable and safe manner.
7. After draining, disconnect and remove the water.
8. Remove fixing down bolts, and then lift the unit from position, using the points provid-
ed and equipment with adequate lifting capacity
See
for unit installation instructions. See
for unit weights.
Units, which cannot be removed in one piece after disconnection, must be dismantled in
position. Handle each component carefully. Where possible, dismantle units in the reverse
order of installation.
Make sure that while components are being removed, the remaining parts are supported in
a safe manner.
After removing the unit from position, dispose of the unit parts according to local laws and
regulations.
NOTE: Under NO circumstances should any system containing glycol be drained di-
rectly into domestic waste or natural water systems.
Caution: Use only lifting equipment if adequate capacity.
Содержание YHAU-CGH
Страница 14: ...FORM 155 32 ICOM2 EN UL ISSUE DATE 1 10 2018 14 JOHNSON CONTROLS THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 38: ...FORM 155 32 ICOM2 EN UL ISSUE DATE 1 10 2018 38 JOHNSON CONTROLS THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 55: ...FORM 155 32 ICOM2 EN UL ISSUE DATE 1 10 2018 JOHNSON CONTROLS 55 THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 57: ...FORM 155 32 ICOM2 EN UL SECTION 4 TECHNICAL DATA ISSUE DATE 1 10 2018 JOHNSON CONTROLS 57 LD27463...
Страница 59: ...FORM 155 32 ICOM2 EN UL SECTION 4 TECHNICAL DATA ISSUE DATE 1 10 2018 JOHNSON CONTROLS 59 LD27465...
Страница 61: ...FORM 155 32 ICOM2 EN UL SECTION 4 TECHNICAL DATA ISSUE DATE 1 10 2018 JOHNSON CONTROLS 61 LD27471...
Страница 63: ...FORM 155 32 ICOM2 EN UL SECTION 4 TECHNICAL DATA ISSUE DATE 1 10 2018 JOHNSON CONTROLS 63...
Страница 65: ...FORM 155 32 ICOM2 EN UL SECTION 4 TECHNICAL DATA ISSUE DATE 1 10 2018 JOHNSON CONTROLS 65 LD27477...
Страница 67: ...FORM 155 32 ICOM2 EN UL SECTION 4 TECHNICAL DATA ISSUE DATE 1 10 2018 JOHNSON CONTROLS 67 LD27479...
Страница 69: ...FORM 155 32 ICOM2 EN UL SECTION 4 TECHNICAL DATA ISSUE DATE 1 10 2018 JOHNSON CONTROLS 69 LD27475...
Страница 160: ...FORM 155 32 ICOM2 EN UL ISSUE DATE 1 10 2018 160 JOHNSON CONTROLS THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 170: ...FORM 155 32 ICOM2 EN UL ISSUE DATE 1 10 2018 170 JOHNSON CONTROLS THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 172: ...FORM 155 32 ICOM2 EN UL ISSUE DATE 1 10 2018 172 JOHNSON CONTROLS THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 181: ...FORM 155 32 ICOM2 EN UL APPENDIX 1 CHECKLIST ISSUE DATE 1 10 2018 JOHNSON CONTROLS 181 NOTES...