When the power regenerative unit detects a fault, the fault code is displayed on the Digital Operator and the fault contact output operates.
When a fault has occurred, refer to the following table to identify and correct the cause of the fault.
Use one of the following methods to reset the fault after restarting the power regenerative unit.

• Turn ON the fault reset signal.

• Press the RESET Key on the Digital Operator.

• Turn the main circuit power supply OFF and then ON again.

Table 6.1  Fault Displays and Processing

Fault Display

Meaning

Probable Causes

Corrective Actions

PUF
IGBT, Fuse Failure

Fuse Blown
The fuse in the main circuit is blown.
The main transistor has damaged.

The output transistor has failed because 
of a short-circuit or overcurrent.

Replace the power regenerative unit 
after correcting the cause.

UV1
Dc Bus Undervolt

Main Circuit Undervoltage
The main circuit DC voltage is below 
the undervoltage detection level 
(L2-05).
200 V class: Approx. 190 VDC 
400 V class: Approx. 380 VDC

• An open-phase occurred with the 

input power supply.

• A momentary power loss occurred.
• The wiring terminals for the input 

power supply are loose.

Reset the fault after correcting its cause.

UV2
CTR PS Undervolt

Control Power Fault
The control power supply voltage 
dropped.

• Try turning the power supply off and 

on.

• Replace the power regenerative unit if 

the fault continues to occur.

UV3
MC Answerback

Inrush Prevention Circuit Fault
A fault occurred in the inrush 
prevention circuit.

• Try turning the power supply off and 

on.

• Replace the power regenerative unit if 

the fault continues to occur.

AUv
Ac Undervoltage

AC Power Undervoltage
AC power undervoltage occurred 
during running.
200 V class: Approx. 150 VAC or less
400 V class: Approx. 300 VAC or less

• An open-phase occurred with the 

input power supply.

• A momentary power loss occurred.
• The wiring terminals for the input 

power supply are loose.

Reset the fault after correcting its cause.

FdVe
Power F Fault

Power Supply Frequency Fault
AC power supply frequency has 
exceeded the setting value (F1-10).

• The power supply fluctuations 

occurred during running.

• Power loss occurred during running.

Reset the fault after correcting its cause.

SrC
Power Supply Flt.

Power Supply Fault
The phase of the input power supply has 
changed after turning ON the control 
power supply.

• An open-phase occurred with the 

input power supply.

• A momentary power loss occurred.
• The wiring terminals for the input 

power supply are loose.

Reset the fault after correcting its cause.

OC
Over Current

Overcurrent
The output current of the power 
regenerative unit exceeded the 
overcurrent detection level.
(200% of rated current)

• A short-circuit occurred at the power 

regenerative output.

• Power supply drop
• Faulty wiring

Reset the fault after correcting its cause.

SC
Short Circuit

IGBT Short-circuit
The IGBT gate signal was short-
circuited.

A short-circuit of the PWM signal 
occurred.

Replace the control card.

OV
Dc Bus Overvolt

Main Circuit Overvoltage
The main circuit DC voltage exceeded 
the overvoltage detection level.
200 V class: Approx. 400 VDC 
400 V class: Approx. 800 VDC

The deceleration time is too short and 
the regenerative energy from the motor 
is too large.

• Increase the deceleration time.
• Check the capacity of the power 

regenerative unit.

• (Increase the capacity.)

The power supply voltage is too high.

Decrease the voltage so it is within 
specifications.

OH
Heatsink Overtmp

Heatsink Overheating
The temperature of the power 
regenerative unit’s cooling fins 
exceeded the setting in L8-02.
(Stopping method can be changed by 
L8-03.)

The ambient temperature is too high.

Install a cooling unit.

There is a heat source nearby.

Remove the heat source.

The cooling fan of the power 
regenerative unit has stopped.

Replace the cooling fan. (Contact our 
sales representative.)

OH1
Heatsink Max temp

Heatsink Overheating
The temperature of the power 
regenerative unit’s cooling fins 
exceeded 105°C.
(Stopping method: Coast to stop)

The ambient temperature is too high.

Install a cooling unit.

There is a heat source nearby.

Remove the heat source.

The cooling fan of the power 
regenerative unit has stopped.

Replace the cooling fan. (Contact our 
sales representative.)

Содержание CIMR-R5U23P71A

Страница 1: ...710656 01C Models 200 V Class Three Phase Input 3 7 to 37 kW 400 V Class Three Phase Input 3 7 to 75 kW To properly use the product read this manual thoroughly and retain for easy reference inspection...

Страница 2: ...herwise without the prior written permission of Yaskawa No patent liability is assumed with respect to the use of the information contained herein Moreover because Yaskawa is constantly striving to im...

Страница 3: ...wer Regenerative Unit from Foreign Matter 17 2 3 Clearances 18 2 4 Dimensions 19 Models of 200 V 400 V 30 kW and Lower 19 Models of 200 V 400 V 37 kW and Higher 19 2 5 Removing and Replacing the Front...

Страница 4: ...9 Navigating Digital Operator Modes 40 Operation Mode 42 4 6 Power On Off Sequence 43 4 7 Run Command Selection 44 Auto Run 44 Manual Run 44 5 MAINTENANCE AND INSPECTION 45 5 1 Section Safety 46 5 2 P...

Страница 5: ...t which has both braking and regenerative functions This instruction manual describes installation maintenance and inspection troubleshooting and specifications of the RC5 Read this instruction manual...

Страница 6: ...MENT Motor Controllers Miscellaneous CLASS 2411 02 ELEVATOR EQUIPMENT Enclosed Elevator and Escalator Electrical Equipment Applicable Requirements CAN CSA C22 2 No 0 4 04 Bonding of Electrical Equipme...

Страница 7: ...ake sure all covers and shields are replaced before operating this product This manual may be modified when necessary because of improvement of the product modification or changes in specifications Su...

Страница 8: ...24 Make sure to ground the ground terminal before connecting the other terminals Failure to observe this warning can result in an electric shock or a fire Refer to page 24 Install adequate branch sho...

Страница 9: ...enerative unit may be damaged Refer to page 34 WARNING Never touch high voltage terminals in the power regenerative unit Failure to observe this warning can result in an electric shock Refer to page 4...

Страница 10: ...656RC5 WARNING Risk of electric shock Read manual before installing Wait 5 minutes for capacitor discharge after disconnecting power supply To conform to requirements make sure to ground the supply n...

Страница 11: ...SKAWA ELECTRIC TOEP C710656 01C YASKAWA RC5 Instruction Manual 11 1 Receiving This chapter describes how to verify the RC5 after delivery to the user 1 1 SECTION SAFETY 12 1 2 INSPECTION CHECKPOINTS 1...

Страница 12: ...RC5 Instruction Manual 1 1 Section Safety 1 1 Section Safety CAUTION Do not install or operate any power regenerative unit which is damaged or has missing parts Failure to observe this caution may re...

Страница 13: ...a standard building not necessarily enclosed in a control panel The protective structure conforms to the standards of NEMA 1 in the USA Checkpoints Description Does the power regenerative unit model...

Страница 14: ...1 2 Inspection Checkpoints 14 YASKAWA ELECTRIC TOEP C710656 01C YASKAWA RC5 Instruction Manual This page intentionally blank...

Страница 15: ...This chapter describes the configuration location and space when mounting the RC5 2 1 SECTION SAFETY 16 2 2 CHECKING INSTALLATION SITE 17 2 3 CLEARANCES 18 2 4 DIMENSIONS 19 2 5 REMOVING AND REPLACING...

Страница 16: ...t cover or the front panel Otherwise the main unit may be dropped causing damage to the unit Mount the power regenerative unit on nonflammable material i e metal Failure to observe this caution can re...

Страница 17: ...oid using outdoors Corrosive gases or liquids Dust or metallic particles in the air For enclosed wall mounted type Physical shock vibration Magnetic noise Example welding machines power devices etc Hi...

Страница 18: ...op and bottom covers to use the open chassis type of 200 V 400 V 30 kW or less 3 When installing the models of 200 V 400 V 37 kW or more equipped with eyebolts extra spacing will be required on either...

Страница 19: ...200 V 3 7 kW model Use open chassis type 200 V 400 V 30 kW and lower with the top and bottom covers removed Figure 2 2 Figure 2 2 Dimensions of RC5 Models of 200 V 400 V 37 kW and Higher Figure 2 3 sh...

Страница 20: ...200 7 87 300 11 81 205 8 07 186 7 32 285 11 22 8 0 0 32 5 5 M6 2015 6 2018 250 9 84 380 14 96 225 8 86 236 9 29 365 14 37 7 5 0 30 10 2022 2030 400 15 75 27 5 1 08 11 2037 325 12 80 450 17 72 285 11...

Страница 21: ...oth sides and lift in the direction shown by arrow 3 Figure 2 4 Figure 2 4 Removing and Replacing the Front Cover Note Do not replace the front cover with the LCD monitor digital operator connected Th...

Страница 22: ...nitor digital operator from the front cover Figure 2 5 Figure 2 5 Removing the LCD Monitor Digital Operator Replacing the LCD Monitor Digital Operator Engage the LCD monitor digital operator on claws...

Страница 23: ...TRIC TOEP C710656 01C YASKAWA RC5 Instruction Manual 23 3 Wiring 3 1 SECTION SAFETY 24 3 2 CONNECTION DIAGRAM 25 3 3 SELECTING PERIPHERAL DEVICES 26 3 4 WIRING MAIN CIRCUIT TERMINALS 29 3 5 EXTERNAL T...

Страница 24: ...ass or equivalent to the SCCR rating of the VFD to which it is connected whichever value is less R5 Series of Power Regenerative devices shall be connected to a VFD which incorporates Solid State Shor...

Страница 25: ...ctor fuse and fuse holder 5 The sequence input terminal of RC5 is the same as terminal S1 6 The wiring distance between the power coordinating reactor and RC5 and a Yaskawa AC Drive should be 10 m or...

Страница 26: ...onds maximum on time of every 240 seconds The overload rating is 150 braking torque for 30 seconds Please note the peak torque should be less than 200 The RC5 requires selecting Power Coordination and...

Страница 27: ...FU 002055 30323 1 45P51A 3 7 7 5 FU 002030 A60Q15 2 3 FU 002055 30323 1 47P51A 5 5 10 FU 002030 A60Q15 2 3 FU 002055 30323 1 40111A 7 5 15 FU 002032 A60Q30 2 3 FU 002055 30323 1 40151A 11 20 FU 002032...

Страница 28: ...twisted shielded or twisted pair shielded wire for the control circuit line and connect the shielded sheath to inverter terminal E See Figure 3 3 Figure 3 3 Figure 3 3 Shielded Wire Termination Groun...

Страница 29: ...ent r1 11 1 21 t1 31 25P5 R L1 S L2 T L3 M4 3 5 to 5 5 12 to 10 r1 11 1 21 t1 31 2 to 5 5 14 to 10 3 5 to 5 5 12 to 10 27P5 R L1 S L2 T L3 M4 5 5 10 r1 11 1 21 t1 31 2 to 5 5 14 to 10 3 5 to 5 5 12 to...

Страница 30: ...S L2 T L3 M5 3 5 to 5 5 12 to 10 r1 11 1 21 t1 31 2 to 5 5 14 to 10 4015 R L1 S L2 T L3 M5 5 5 10 r1 11 1 21 t1 31 2 to 5 5 14 to 10 5 5 10 4018 R L1 S L2 T L3 M6 8 to 14 8 to 6 r1 11 1 21 t1 31 M4 2...

Страница 31: ...s calculated as follows If there is a possibility of excessive voltage drop use a larger wire suitable to the required length Line voltage drop V 3 x wire resistance km x wire length m x current A x 1...

Страница 32: ...of the control card Signal Input Function Function Signal Level Sequence Input S1 MANUAL RUN Run when CLOSED stops when OPEN 24 VDC 8 mA Photocoupler isolation S2 AUTO RUN Auto run regenerative operat...

Страница 33: ...Manual 33 4 Operation 4 1 SECTION SAFETY 34 4 2 CHECKS PRIOR TO MAIN POWER APPLICATION 35 4 3 SETTING THE POWER SUPPLY VOLTAGE JUMPER 36 4 4 USING THE DIGITAL OPERATOR 37 4 5 DIGITAL OPERATOR MODES 39...

Страница 34: ...your hand is wet Failure to observe this warning can result in an electric shock Never touch the terminals while current is flowing even if the power regenerative unit stops Failure to observe this w...

Страница 35: ...0 V class 200 to 230 VAC 50 60 Hz 400 V class 380 to 460 VAC 50 60 Hz Make sure that the power regenerative unit and the Drive are connected correctly Make sure that the phase sequence of the main cir...

Страница 36: ...mance of the power regenerative unit The jumper is factory set to 460 V when shipped If the power supply voltage is not 460 V use the following procedure to change the setting 1 Turn OFF the power sup...

Страница 37: ...Operator Component Names and Functions LOCAL REMOTE MENU DIGITAL OPERATOR JVOP 130 ESC DATA ENTER JOG FWD REV RESET RUN STOP DRIVE FWD REV REMOTE SEQ REF Dc Bus Voltage U1 02 300 VDC Keys Execute ope...

Страница 38: ...ey Not used FWD REV Key Not used RESET Key Set the number of digits for parameter settings Also acts as the reset Key when a fault has occurred Increment Key Selects menu items groups functions and pa...

Страница 39: ...ion or displaying the fault history Initialize mode Use this mode when selecting the language displayed on the Digital Operator selecting the access level for reading setting user parameters selecting...

Страница 40: ...tal operator press the MENU Key to enter the operation mode and then press the DATA ENTER Key from the operation mode display to bring up the monitor display Run commands can t be received from any ot...

Страница 41: ...rminals to the operator Step Key Sequence Digital Operator Display Remarks 1 MENU Main Menu Operation 2 Press twice Main Menu Programming 3 DATA ENTER Group b Application 4 DATA ENTER Function b1 Sequ...

Страница 42: ...ion mode appears when the power is turned ON Operations in Operation Mode Key operations in operation mode are shown in Figure 4 4 Figure 4 4 Figure 4 4 Operations in Operation Mode All modes paramete...

Страница 43: ...ommands of the drive and the power regenerative unit should be turned ON at the same time Never turn the run command of the power regenerative unit OFF while the drive output during run is ON Run outp...

Страница 44: ...1 sec Figure 4 6 Figure 4 6 Time chart of the Auto Run Mode Manual Run Manual run is the mode in which the RC5 starts running when the terminal S1 SC is closed and stops one second after S1 SC is ope...

Страница 45: ...YASKAWA ELECTRIC TOEP C710656 01C YASKAWA RC5 Instruction Manual 45 5 Maintenance and Inspection 5 1 SECTION SAFETY 46 5 2 PERIODIC INSPECTION AND MAINTENANCE 47...

Страница 46: ...ed to perform maintenance inspections or parts replacement Remove all metal objects watches bracelets etc before operation Use tools which are insulated against electric shock Failure to observe this...

Страница 47: ...as screws inside the RC5 Failure to observe this caution may result in a short circuit and a fire Periodic inspection standards vary depending the installation environment and usage conditions of the...

Страница 48: ...5 2 Periodic Inspection and Maintenance 48 YASKAWA ELECTRIC TOEP C710656 01C YASKAWA RC5 Instruction Manual This page intentionally blank...

Страница 49: ...YASKAWA ELECTRIC TOEP C710656 01C YASKAWA RC5 Instruction Manual 49 6 Troubleshooting 6 1 FAULT DETECTION 50 6 2 MINOR FAULT DETECTION 52 6 3 OPERATION ERRORS 53...

Страница 50: ...cause FdVe Power F Fault Power Supply Frequency Fault AC power supply frequency has exceeded the setting value F1 10 The power supply fluctuations occurred during running Power loss occurred during r...

Страница 51: ...again Try setting the constants again CPF00 COM ERR OP CONV Control Circuit Error 1 Operator Communications Error Communications with the digital operator were not established within 5 seconds after...

Страница 52: ...ass Approx 400 VDC 400 V class Approx 800 VDC The regenerative energy from the motor is too large Check the capacity of the power regenerative unit Increase the capacity The power supply voltage is to...

Страница 53: ...ther When an operation error has occurred refer to the following table to identify and correct the cause of the errors Table 6 3 Operation Error Displays and Incorrect Settings Display Meaning Incorre...

Страница 54: ...6 3 Operation Errors 54 YASKAWA ELECTRIC TOEP C710656 01C YASKAWA RC5 Instruction Manual This page intentionally blank...

Страница 55: ...YASKAWA ELECTRIC TOEP C710656 01C YASKAWA RC5 Instruction Manual 55 7 Specifications...

Страница 56: ...ED 187 5 for 30 s max torque 250 Standard Duty 80 cont 100 for 60s 25 ED 150 for 30s max torque 200 Input Power Supply Voltage Frequency 200 to 220 VAC 50 Hz 200 to 230 VAC 60 Hz Allowable Voltage Fl...

Страница 57: ...uctuation 3 Hz 3 phase rotation Control Characteristics Control Method 120 current conduction Input Power Factor 0 9 or more Rated current Overload Capacity Standard Duty 150 for 30 seconds Heavy Duty...

Страница 58: ...58 YASKAWA ELECTRIC TOEP C710656 01C YASKAWA RC5 Instruction Manual This page intentionally blank...

Страница 59: ...YASKAWA ELECTRIC TOEP C710656 01C YASKAWA RC5 Instruction Manual 59 A Parameter List...

Страница 60: ...01 Hz AC Frequency U1 10 Input terminal status Shows input ON OFF status Cannot be output Input Term Sts U1 11 Output terminal status Shows output ON OFF status Output Term Sts U1 12 Operation status...

Страница 61: ...atus when the last fault occurred Same format as U1 12 Regen Unit Sts U2 14 Cumulative operation time at fault Elapsed operating or power on time when the last fault occurred 1 H Elapsed Time U2 20 Vo...

Страница 62: ...to 50 0 V 2 0 x A For 400 V class power regenerative units double the initial setting and setting range V Bias of Run C8 19 Hysteresis voltage width at operation start stop 0 5 to 50 0 V 3 0 x A For 4...

Страница 63: ...s reactance may be necessary Consult the factory before changing this parameter setting PUV Det Level L5 01 Number of auto restart attempts 0 to 10 0 x A Sets the counter for the number of times the U...

Страница 64: ...digits of the model number This parameter only needs to be set when installing a new control board Do not change for any other reason Regen Unit Model o2 06 Operation selection when digital operator i...

Страница 65: ...lt Normally Closed During Run Alarm Only Setting value Function H2 02 03 Remarks 0 During run During RUN 1 Closed When a run command is input or the Unit is outputting voltage 6 Regenerative unit read...

Страница 66: ...r supply voltage AC Voltage 200 V class 200 V 5 V 400 V class 400 V 5 V 0 to 10 V output 100 400 800 Vdc depending on the Unit voltage rating 5 Current at power side AC Current Rated current 10 V 100...

Страница 67: ...ng Installation Site Chapter 3 Addition Note on UL standard in Closed Loop Connectors Size Revision Note on Short Circuit Current Rating SCCR in Section Safety Closed Loop Connectors Sizes Table Septe...

Страница 68: ......

Страница 69: ...04 01 New Tech Park 556741 Singapore Phone 65 6282 3003 Fax 65 6289 3003 http www yaskawa com sg YASKAWA ELECTRIC SHANGHAI CO LTD No 18 Xizang Zhong Road 17F Harbour Ring Plaza Shanghai 200001 China...

Отзывы: