12
2. PRE-OPERATION PROCEDURES
Installation
8. Install the pre-process cartridge.
●
Turn power off and close water tap before installing or replacing the pre-process
cartridge.
●
Install procedure:
(1) Remove rubber cap from the process
cartridge.
(2) Place pre-process cartridge into
designated
bracket,
inside
the
WE200 unit. (See Figure 4)
(3) Connect the pre-process coupler,
“PWF OUT” to the “OUT” fitting on
the pre-process cartridge, while
sliding the light blue coupler tip back.
(See Figure 5 & 6)
(4) Connect the pre-process coupler,
“PWF OUT” to the “OUT” fitting on
the pre-process cartridge, while
sliding the light blue coupler tip back.
(See Figure 5 & 6)
●
Removal procedure:
(1) Remove the pre-process coupler
simply by holding it by the light blue
tip and pulling upward. (See Figure
6.)
(2) Remove from the
“IN” side first,
followed by the
“OUT” side.
Figure 4
Figure 5
Figure 6
※
Once pre-process hoses are installed, give each coupler a gentle tug to verify that they are
securely in place..
※
When removing pre-process couplers, water may drip from the pre-process cartridge fittings.
Be careful not to let water get on the leak sensor.