VX-2500U Alignment, Page 1/4

Vertex Standard Co., Ltd.

VX-2500U Alignment

The VX-2500U has been carefully aligned at the factory for the specified performance across the
frequency range specified for each version.
Realignment should therefore not be necessary except in the event of a component failure, or alteration
of version. All component replacement and service should be performed only by an authorized Vertex
Standard representative, or the warranty policy may be voided.
The following procedures cover the sometimes critical and tedious adjustments that are not normally
required once the transceiver has left the factory. However, if damage occurs and some parts are
replaced, realignment may be required. If a sudden problem occurs during normal operation, it is likely
due to component failure; realignment should not be done until after the faulty component has been
replaced.
We recommend that servicing be performed only by authorized Vertex Standard service technicians
who are experienced with the circuitry and fully equipped for repair and alignment. Therefore, if a fault is
suspected, contact the dealer from whom the transceiver was purchased for instructions regarding
repair. Authorized Vertex Standard service technicians realign all circuits and make complete
performance checks to ensure compliance with factory specifications after replacing any faulty
components. Those who do undertake any of the following alignments are cautioned to proceed at their
own risk. Problems caused by unauthorized attempts at realignment are not covered by the warranty
policy. Also, Vertex Standard must reserve the right to change circuits and alignment procedures in the
interest of improved performance, without notifying owners. Under no circumstances should any
alignment be attempted unless the normal function and operation of the transceiver are clearly
understood, the cause of the malfunction has been clearly pinpointed and any faulty components
replaced, and the need for realignment determined to be absolutely necessary.  The following test
equipment (and thorough familiarity with its correct use) is necessary for complete realignment.
Correction of problems caused by misalignment resulting from use of improper test equipment is not
covered under the warranty policy. While most steps do not require all of the equipment listed, the
interactions of some adjustments may require that more complex adjustments be performed afterwards.
Do not attempt to perform only a single step unless it is clearly isolated electrically from all other steps.
Have all test equipment ready before beginning, and follow all of the steps in a section in the order
presented.

Required Test Equipment

RF signal generator: calibrated output level at

1000MHz (0dBµ =1.0µV - closed circuit)

Deviation Meter (linear detector)
AF Millivoltmeter
SINAD Meter
Inline Wattmeter with 5% accuracy at 1000MHz
Regulated DC Power Supply: adjustable from 10 to 17 VDC, 15A
50-ohm Non-reactive Dummy Load: 100W at 1000MHz
Frequency Counter: >0.1ppm accuracy at 1000MHz
AF Signal Generator
DC Voltmeter: high impedance
RF Sampling Coupler (attenuation pad)
AF Dummy Load: 4

, 20W

Oscilloscope
Spectrum Analyzer
IBM PC/compatible computer
Vertex Standard VPL-1 programming cable and CE-** channel programming editor.

Содержание VX-2500U

Страница 1: ...ment are not covered by the warranty policy Also Vertex Standard must reserve the right to change circuits and alignment procedures in the interest of improved performance without notifying owners Under no circumstances should any alignment be attempted unless the normal function and operation of the transceiver are clearly understood the cause of the malfunction has been clearly pinpointed and an...

Страница 2: ...mal equalization with the environment before alignment If possible alignments should be made with oscillator shields and circuit boards firmly affixed in place Also the test equipment must be thoroughly warmed up before beginning Before beginning connect the transceiver and PC using the VPL 1 programming cable as described in the EEPROM Programming chapter and downloads the EEPROM data from the tr...

Страница 3: ...mitter and confirm about 1 0V on the voltmeter PLL Reference Frequency With the wattmeter dummy load and frequency counter connected to the antenna jack and select band center frequency channel key the transmitter and adjust TC1001 on the Main Unit if necessary so the counter frequency is within 100Hz of the channel center frequency for the transceiver version Transmitter Transmitter Output Power ...

Страница 4: ...test adapter as described in the box below With the transceiver set to band center frequency channel and the RF signal generator tuned to the same frequency set the generator for 3 0kHz deviation for 25kHz steps with 1kHz tone modulation and set the output level for 1µV at the antenna jack Adjust by control commands for tune from the computer for optimum SINAD reducing signal generator output leve...