46 | UM-PP-EN-03
6.4.1
Checklist for Before Starting Operation
•
Check sturdiness of the device
•
Check electrical connections
•
Protect all live components against touch
•
Ensure that safety equipment is intact and functional
•
Check emergency stop switch and all control functions
•
Perform a malfunction-free trial run
•
Ensure all operators have received complete and proper instruction
6.5
Replacing Parts
NOTE
The use of NON-original replacement parts may change the characteristics
of the device and interfere with the safe use.
WOODWAY does not accept liability for damages resulting from this.
DANGER
Danger of Death by Electric Shock!
Fatal electrical shock may occur if the unit is not disconnected from the
power supply before assembly or disassembly.
►
The device must be stopped, switched off, and unplugged before being
worked on.
►
Ensure the device cannot be switched back on.
►
After the power is disconnected wait 10 minutes to ensure that live
electrical components (e.g. capacitors) have discharged.
6.5.1
Side Covers Removal
Disconnect the treadmill from the power supply and remove the 2 large screws from the outer cover
using a Phillips head screwdriver. The covers can then be lifted up from the frame of the treadmill.
6.5.2
Replacement
Position the 2 outer coverings on both sides of the frame. Then re-tighten the large screws.
•
Check whether the treadmill scrapes on the covering panels by moving the mat backwards
and forwards.
•
If the treadmill scrapes, loosen the screws and move the covers away from the mat.
6.5.3
Side Handrails
In most cases the WOODWAY
is delivered completely assembled. In some cases, the conditions at
the intended location do not allow for assembly-free delivery (doors, stairs, elevators, etc.) and the
treadmill needs to be partially disassembled.
Содержание ST PPS 43 Med
Страница 22: ...16 UM PP EN 03 2 7 EC Declaration of Conformity Fig 1 EC Declaration of Conformity...
Страница 26: ...20 UM PP EN 03 3 5 Dimensions Fig 3 Device dimensions PPS Bari Mill 43 Fig 4 Device dimensions PPS Bari Mill 55...
Страница 27: ...21 UM PP EN 03 Fig 5 Device dimensions PPS Bari Mill 70 Fig 6 Device dimensions PPS Med 43...
Страница 114: ...108 UM PP EN 03 12 Maintenance Report DATE MAINTENANCE MEASURES FROM REMARKS...