background image

Installation Guide

7x7

4.25 m²

130mm

130mm

2110mm

2124mm

56mm

50mm

Содержание Bao Basic

Страница 1: ...Installation Guide 7x7 4 25 m 130mm 130mm 2110mm 2124mm 56mm 50mm...

Страница 2: ...that the location is level Be careful when handling parts with steel edges For the construction and handling of the WPC shed please only use tools that are listed in the assembly instructions Always w...

Страница 3: ...8mm Garden Shed Three view Drawing Tools Required for Installation 3 2370 2124 123 123 2124 2230 1964 2008 2370 2124 2222 1875 2124 56 50 2222 1875...

Страница 4: ...ront 59x59 L 2222mm Aluminum Column Right Front 1 1 59x59 L 2008mm Aluminum Column Left Rear 59x59 L 2008mm Aluminum Column Right Rear 1 1 59x30 L 1350mm Aluminum Threshold 1 30x27 L 1875mm 30x27 L 18...

Страница 5: ...Screws Screws 1350X1830 8X80 1 4X16 220 18 A 4X10 B C 5X20 5X45 Rivet 12 45 5X60 12 Connector 50X50 6 D Latch 2 Hinge 4 E Plastic Cap for Aluminum Verge Board 4 80 F H I J K G Door Lock Kit 1 18 19 20...

Страница 6: ...hould be installed on the hard ground like concrete foundation the surface of ground should be flat and the size should follow the dimension of drawing Bottom Beam Dimension Drawing 6 2200 2124 2124 3...

Страница 7: ...ll aluminum bottom frames according to dimensions and positions as the sketch map shown above then fix them with plastic expansion bolts Please make sure the leveling of the bottom frames A 16x 1 1 1...

Страница 8: ...m bottom frames then fasten column and planks with screws Two operators are required for this step one needs to hold the column so as to avoid any broken caused by tilt We suggest to install garden sh...

Страница 9: ...Install the WPC plank wall one by one Install the column left rear into place 19 19 2 1 1 1 1 1 1 1 1 4 2 19 9...

Страница 10: ...Install the WPC plank wall one by one Insert the aluminum H shaped beam left right into the column then install WPC plank wall into the place one by one 2 2 9 9 1 1 1 1 1 1 1 1 4 4 19 20 19 10...

Страница 11: ...place then insert the aluminum H shaped beam rear into the column Install the aluminum column right front into the place then insert the aluminum H shaped beam left right into the column 19 19 19 19...

Страница 12: ...Install front WPC plank wall and aluminum H shaped beam front into the place X2 19 X2 19 19 19 9 9 9 9 9 2 5 4 3 12...

Страница 13: ...uminum threshold and adjust perpendicularity and dimension between the two frames shown as the above sketch map After adjustment please fix WPC plank wall aluminum bottom frame and aluminum H shaped b...

Страница 14: ...15 14 16 Install window into the place Please note different sides of window the side with rivets should be toward the inside Fasten the window with columns and H shaped beams by using screws 14...

Страница 15: ...Connect the aluminum beams with window left right side by using rivets C D 13 13 13 13 13 13 13 13 Connect the aluminum beams with L brackets by applying rivets in advance C D 15...

Страница 16: ...he extension length of roof tile should be 60mm in the shed s front side while the left and right side should be 130mm Please note that the length of screws for roof tiles xing is different from those...

Страница 17: ...17 17 17 Install roof tiles one by one please pay attention to the connection method shown as the above sketch map 17...

Страница 18: ...Install all aluminum verge boards in line with the diagram as above J J J J J 12 11 11 12 12 10 10 10 18...

Страница 19: ...e position where needs to install it Put a subplate with a thickness of 5mm under the door Insert the other side of hinge into the place and mark the position with a pencil Remove the door then fix hi...

Страница 20: ...ed the screws when packing so the door handle cannot be used as default when you unpack it firstly 2 Please unscrew the screw see picture above firstly then rotate the handle by 90 clockwise or anti c...

Отзывы: