Sawmill Setup
Stationary Sawmill Setup
Sawmill Setup
HD-R04doc041910
3-1
3
SECTION 3 SAWMILL SETUP
3.1
Stationary Sawmill Setup
Prepare a firm, level area where the sawmill can be anchored. There should be enough
room around the sawmill for operators, sawdust removal, log loading and board removal.
A cement pad with 5/8” diameter anchor bolts is recommended. The cement pad should
be rated to support 6350 lbs./sq.ft. at each sawmill foot position.
for stationary sawmill foot anchor locations.
for stationary
sawmill with bed extension foot anchor locations.
NOTE:
Make sure the unit is level before securing. It IS possible to twist the mill frame by
jacking one foot higher than the others.
WARNING!
Securely fasten the feet of a stationary sawmill
to the floor before operating the sawmill. Failure to do so
may result in serious injury or death.