LubeMizer Installation
Control Box Wiring
LubeMizer Installation
LMS99doc032619
1-3
1
1.2
Control Box Wiring
LT30 Super
Rev. G9.00+
LT40 Super
Rev. H1.00+
LT30HD/40HD Super
Rev. H4.00+
LX450
Rev. A1.00+
DANGER!
The key switch should still be off, the key
removed and the negative battery cable disconnected as
stated at the beginning of this section. The incoming power
supply of electric-powered sawmills should be discon-
nected and locked out. Failure to do so will result in serious
injury or death.
IMPORTANT!
Avoid pinch and pivot points, unnecessary
wire bending and open spaces where the wire could get
caught by a log, etc. If you have any questions, call
Wood-Mizer customer service.
Refer to the appropriate wiring diagram while performing the wiring steps below.
Locate red wire #19 inside the sawmill control box. Disconnect wire #19 from the
red jumper wire connected to the feed drum switch (or terminal #T13 of the wireless
interface on wireless sawmills).
Connect red lube wire #251 to red wire #19. Connect red lube wire #250 to the red
jumper wire.
Locate black wire #20 inside the sawmill control box. Disconnect wire #20 from the
black jumper wire connected to the ground stud at the back of the control box.
Connect blue lube wire #257 to black wire #20. Connect black lube wire #259 to the
black ground jumper wire.
7.
Using the existing mounting bolts, install the lube control assembly to the sawmill control
box. Replace the rear control box panel.
STOP! You have completed Control Box
Wiring. Proceed to Section 1.5 Pump
Installation And Wiring (All LT30/LT40
Sawmills) or Section 1.6 Pump Installa-
tion And Wiring (LX450 Sawmills).