Operation manual PEK
Page 17 of 25
B0053
6. Transportation, installation, commissioning and shutdown
6.1 Transportation
Transport the PEK to its destination carefully and by using suitable aids (e.g. hand-carts or
the like).
6.2 Unpacking
Lift the PEK out of its packaging carefully and put it on a stable and plane base.
Note!
The PEK and the components attached in accordance with the
scope of delivery may still contain residues of blue-dyed test oil.
6.3 Installation
The pump unit is ready for wall mounting and is mounted with two M8 screws. The mounting
surface must be sufficiently stable in order to be capable of carrying the PEK´s weight inclu-
ding the filled reservoir.
The PEK must not be exposed to any atmosphere that could be capable of reacting with the
materials used for the pump.
Drill scheme:
Mount the PEK such that it cannot be exposed to unintentional impacts.
50