5.5.4
Pressure control valve
The pressure control valve (PCV) (002,
) is attached to the fuel rail (007) and has the
functions that follow:
•
Usual operation
During usual operation the engine software controls the fuel flow and thus the fuel pressure.
The PCV is closed because the pressure in the fuel rail is lower than necessary to open the
PCV.
•
Operation with a defective item
If an item becomes defective or unserviceable (for example missing or incorrect control
signals, a flow control valve of a fuel pump is unserviceable), the operator must do the
related procedures. Then the engine control sets the fuel pumps to the maximum flow and
the PCV controls the pressure in the fuel rail. The PCV opens to gradually drain sufficient
fuel to keep the adjusted pressure. Prevent a longer engine operation time in this operation
mode to prevent a possible damage to the PCV.
After this operation mode, do a check of the PCV for a tight seal. The seal can be damaged.
You can hear a loud sound like a whistle. Replace the PCV seal if necessary.
•
Engine stand-by
During engine stand-by, the engine software opens the PCV. This gives a constant flow of
fuel through the fuel system.
•
Emergency stop
If an emergency stop is activated, the safety system operates the solenoid valve (001) and
the fuel pressure in the fuel rail decreases immediately to less than 200 bar (usually to 0 bar).
Thus, fuel injection is not possible.
Attached to the PCV are the solenoid valve (001), the relief valve (003) and the fuel return
pipes (004, 005). As a safety device the relief valve opens, if the fuel pressure is more than the
specified pressure.
X92-B
AA00-5562-00AAA-043A-A
Operation Manual
Pressure control valve
Winterthur Gas & Diesel Ltd.
- 168 -
Issue 002 2021-11
Содержание X92-B
Страница 8: ...X92 B Operation Manual Page left intentionally blank Winterthur Gas Diesel Ltd 8 Issue 002 2021 11...
Страница 12: ...X92 B Operation Manual Page left intentionally blank Winterthur Gas Diesel Ltd 12 Issue 002 2021 11...
Страница 113: ...X92 B Operation Manual Page left intentionally blank Winterthur Gas Diesel Ltd 113 Issue 002 2021 11...
Страница 241: ...7 Installation 7 1 Installation 242 X92 B Operation Manual Winterthur Gas Diesel Ltd 241 Issue 002 2021 11...