10.18
Temporary isolate the HP SCR system
Periodicity
Description
Unscheduled
Duration for performing preliminary requirements
0.0 man-hours
Duration for performing the procedure
4.0 man-hours
Duration for performing the requirements after job completion
0.0 man-hours
Personnel
Description
Specialization
QTY
Engine crew
Intermediate
1
Support equipment
Description
Part No.
CSN
QTY
Cover
2
Supplies
Description
QTY
None
Spare Parts
Description
Part No.
CSN
QTY
None
SAFETY PRECAUTIONS
PRELIMINARY OPERATIONS
•
The engine must be stopped and prepared for maintenance, refer to section
the engine after stop - general
X72-B
AA00-9270-00AAA-720C-A
Operation Manual
Temporary isolate the HP SCR system
Winterthur Gas & Diesel Ltd.
- 454 -
Issue 003 2021-12
Содержание X72-B
Страница 8: ...X72 B Operation Manual Page left intentionally blank Winterthur Gas Diesel Ltd 8 Issue 003 2021 12...
Страница 18: ...X72 B Operation Manual Page left intentionally blank Winterthur Gas Diesel Ltd 18 Issue 003 2021 12...
Страница 137: ...X72 B Operation Manual Page left intentionally blank Winterthur Gas Diesel Ltd 137 Issue 003 2021 12...
Страница 301: ...7 Installation 7 1 Installation 302 X72 B Operation Manual Winterthur Gas Diesel Ltd 301 Issue 003 2021 12...