8.7
Do regular safety checks
Periodicity
Description
Months
3
Unscheduled
After maintenance work
Duration for performing preliminary requirements
0.0 man-hours
Duration for performing the procedure
4.0 man-hours
Duration for performing the requirements after job completion
0.0 man-hours
Personnel
Description
Specialization
QTY
Engine crew
Intermediate
1
Support equipment
Description
Part No.
CSN
QTY
Pressure calibration hand-
pump
94050
1
Smoke test instrument
N/A
1
Ampere meter
N/A
1
Supplies
Description
QTY
None
Spare Parts
Description
Part No.
CSN
QTY
None
SAFETY PRECAUTIONS
CAUTION
Equipment Hazard: Leaks can cause faults in the engine control systems and damage to
engine components. Leaks that are found during the engine control system checks must
be repaired to prevent damage to equipment.
PRELIMINARY OPERATIONS
•
The engine must be prepared for operation, refer to section
•
The engine must be stopped.
X72-B
AA00-0000-00AAA-340A-A
Operation Manual
Do regular safety checks
Winterthur Gas & Diesel Ltd.
- 324 -
Issue 003 2021-12
Содержание X72-B
Страница 8: ...X72 B Operation Manual Page left intentionally blank Winterthur Gas Diesel Ltd 8 Issue 003 2021 12...
Страница 18: ...X72 B Operation Manual Page left intentionally blank Winterthur Gas Diesel Ltd 18 Issue 003 2021 12...
Страница 137: ...X72 B Operation Manual Page left intentionally blank Winterthur Gas Diesel Ltd 137 Issue 003 2021 12...
Страница 301: ...7 Installation 7 1 Installation 302 X72 B Operation Manual Winterthur Gas Diesel Ltd 301 Issue 003 2021 12...