User Guide
4. Part Replacement
4.8 Rails Replacement
Step 24 :
Now that the drives are installed into the chassis, test the installation by sliding the enclosure
in and out of the rack a minimum of three times. If the enclosure binds, catches, or displays any
incorrect motion or behavior retry the installation of the drives and chassis.
Step 25 :
If the chassis is being installed into a rack that will be shipped fully assembled, you
must
install
eight (four per side) of the included M5 x 12mm T15 Flat Head Torx screws into the two brackets
at the front of the chassis in the following locations. These screws should be tightened to
3.38-3.61 Nm / 30-32 in-lbf using a Long T15 Torx Screwdriver. If this chassis will not be installed
into a rack for shipping purposes, skip this step and move on to the next one.
Figure 89:
Shipping Bracket Screw Locations
Step 26 :
Plug the enclosure power cords into a PDU to power the enclosure.
Step 27 :
Double check the power indicators and other LEDs to ensure that the system is booting.
4.8
Rails Replacement
Table 43:
Procedure Info
Required Tools
Required Parts
# of People Required Time Required
•
Long T15 Torx
Screwdriver
•
# 2 Philips Screwdriver
•
Long T10 Torx
Screwdriver
•
Cable Ties (for
configurations
with greater than
10 total cables)
•
Tape Measure
•
Level
•
Reuse:
M5 x 12mm T15
Flat Head Torx screws
•
Reuse:
Included Washers
•
Low-Profile M4 x 3.2mm
Philips screws (included
with rail assembly)
•
Optional (if using
CMA Tray):
M3 x
8mm T10 Torx screws
3 Total (2 for Team
Lifting Purposes and
1 to Guide and Spot)
~1h
93