6.6.9 Commissioning menu
In the commissioning menu, the engineer can:
interrogate or change commissioning settings,
call up device information,
configure inputs and outputs,
start program for purging and water filling,
carry out BCC updates,
reset system to factory settings.
If a device (Bus participant) is installed at a later date, removed or replaced:
Interrupt and restore voltage supply.
The relevant commissioning wizard starts automatically.
Carry out commissioning steps.
6.6.9.1 System
Commission-
ing
System
Parameters
Setting
10.1.1
Language
Set language.
10.1.2
Date
Set date.
10.1.3
Time
Set time.