RECOMMENDED SEQUENCE WHEN
INSTALLING SPM
®
FSR COMPONENTS
Different situations require different installation sequences. The
possibilities are myriad and each scenario cannot be discussed
in this manual. Should you have anything other than a standard
installation, it is strongly recommended you contact Weir Oil & Gas
Engineering before proceeding. A standard installation sequence
is as follows:
FIRST
Install SPM
®
FSR Anchor Crossover Assemblies within the flow
line where applicable. See page 27 for more information. This is
critical because they require installation into the flow line. If these
are not included, the flow line must be disassembled and these
components installed at a later point.
NOTE:
Anchor Crossovers may be included at various points
in the flow-line to allow disassembly of a smaller section
of the SPM
®
FSR to access the flow iron. This may be
necessary in order to replace internal components.
SECOND
Install the SPM
®
FSR Ribs next. See pages 14-17 of this guide for
more information.
TIP -
It is most efficient to have one person lay out all the
SPM
®
FSR Ribs at appropriate locations along the flow line
prior to installing them.
TIP -
It is recommended that one person lift the flow
line with the pipe jack (or similar leverage) while another
individual installs the Rib at each wing union connection.
Содержание SPM Flow Line
Страница 1: ...SPM Flow Line Safety Restraint System FSR Installation Guide...
Страница 32: ...32 Step 2 Step 3 Step 1 SPM FSR Rib...
Страница 41: ...41 NOTES...
Страница 42: ...42 Document P N 2P37221M Release Date 9 25 2014 Revision 6 Date 2 4 2015...