background image

Installation, Operation and Maintenance

Electronic Control Valve (for Electric Valve Positioning)

Sizes: 11/4" to 24" 

NOTICE

For Australia and New Zealand: Pipeline strainers should be 

installed between the upstream shutoff valve and the inlet of  

the backflow preventer.

It’s important that this device be tested periodically in compli-

ance with local codes, but at least once per year or more as 

service conditions warrant. If installed on a fire sprinkler system, 

all mechanical checks, such as alarm checks and backflow  

preventers, should be flow tested and inspected internally in  

accordance with NFPA 13 and NFPA 25.

WARNING

!

Read this Manual BEFORE using this equipment.
Failure to read and follow all safety and use information 

can result in death, serious personal injury, property 

damage, or damage to the equipment.
Keep this Manual for future reference.

Table of Contents  

Page

Introduction .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  . 2

Installation   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  . 2

Setting the Solenoid Control Valve .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  . 3

Maintenance Schedule .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  . 6

Trouble Shooting Guide   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  . 6

Valve Disassembly Instructions  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  . 8 

ACV Schematic   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  . 11

  

Local building or plumbing codes may require modifica-

tions to the information provided.  You are required to  

consult the local building and plumbing codes prior 

to installation.  If the information provided here is not 

consistent with local building or plumbing codes, the 

local codes should be followed.  This product must be 

installed by a licensed contractor in accordance with 

local codes and ordinances.

WARNING

!

Need for Periodic Inspection/Maintenance:

  This product 

must be tested periodically in compliance with local codes, 

but at least once per year or more as service conditions 

warrant .  All products must be retested once maintenance 

has been performed .  Corrosive water conditions and/or 

unauthorized adjustments or repair could render the product 

ineffective for the service intended .  Regular checking and 

cleaning of the product’s internal and external components 

helps assure maximum life and proper product function . 

WARNING

!

Model 933GD / 633GD

IOM-A-ACV-933_633

Содержание AMES 633GD

Страница 1: ...Setting the Solenoid Control Valve 3 Maintenance Schedule 6 Trouble Shooting Guide 6 Valve Disassembly Instructions 8 ACV Schematic 11 Local building or plumbing codes may require modifica tions to th...

Страница 2: ...talled according to factory recommendations Consult factory for detailed engineering review prior to order ing if valve is to be installed other than horizontally in line 5 If valve is equipped with a...

Страница 3: ...valve bleed air by loosen ing a fitting on the valve or a plug at the highest point of the valve assembly STEP 5 Pressure the line by opening the upstream isolation valve slowly Air is vented through...

Страница 4: ...r of the main valve If the main valve is opening too slowly turn the adjustment screw OUT counterclockwise increasing the rate of opening See Figure 2B If the main valve is opening too quickly turn th...

Страница 5: ...ve specification sheets for approximate cover capacity A continuous flow of water from the open port indicates a damaged diaphragm or loose disc diaphragm assembly Disassemble valve and replace diaphr...

Страница 6: ...ck isolation valves ensure open Diaphragm is damaged Conduct diaphragm seal test repair and replace if necessary Main valve stem assembly corroded damaged Inspect stem assembly clean replace if necess...

Страница 7: ...Remove cover nuts and washers 3 Remove the cover If cover is not free to be removed loosen it by tapping upward along its outside edge with a dull cold chisel pic tured above a Large valves may requi...

Страница 8: ...e brush or by using a Mineral Dissolving Solution Inspect parts for wear and replace if necessary 7 Inspect valve seat If seat is not damaged removal is not necessary Valve seats 6 and smaller are thr...

Страница 9: ...r Nuts in a crossing pattern to ensure even distribution Test the Disc and Diaphragm Assembly for smooth travel by following the Freedom of Movement Test procedure in previous section 11 Test the inte...

Страница 10: ...s Steel 10 Diaphragm Washer ASTM A536 65 45 12 Epoxy Coated Ductile Iron 11 Diaphragm Buna N Nitrile 12 Disc Retainer ASTM A536 65 45 12 Epoxy Coated Ductile Iron 13 Seat Disc Buna N Nitrile 14 Spacer...

Страница 11: ...IOM A ACV 933_633 2115 EDP 1917088 2021 Watts 11 NOTES...

Страница 12: ...sts resulting from labor charges delays vandalism negligence fouling caused by foreign material damage from adverse water conditions chemical or any other circumstances over which the Company has no c...