Installation note & suggestion
Note:
During installation and construction, relevant circuits should be disconnected to ensure that all circuits are correct before
energizing.
►►
Installation Suggestion:
1)
For cables, suggest laid 60mm deep, over 50mm, and connector area be bending to avoid water.
2)
If the turnstiles install in the outside, suggest installed in concrete deep 100-200mm to avoid natural damaged.
3)
All the operation should be done when power off.
4)
Wear the strong electric cable and the weak electric cable are respectively with 3/4 "PVC pipe and buried to the
corresponding position with cement.
5)
After adjusting the foundation surface, arrange the equipment in good order.
6)
After the hole location is determined, drill the hole and embed the anchor bolt or expansion bolt of M12.
7)
Open the case, select one of the equipment as the reference (preferably choose the middle one as the reference), align
the base bolt hole with the corresponding anchor bolt, and pre-tighten the nut.
8)
Connect the power line and control line according to the wiring diagram, and connect the system protection ground wire.
9)
Check the mains wiring according to the wiring diagram, check the power wiring and other wiring of the whole equipment
are correct, and the power can be adjusted after confirmation.
10)
After completion of the installation, check the connection condition of earth wire, connector assembly for connecting line
and all moving parts with the device. Make sure the connection is firm in order to prevent failure caused by long time
operation. If any screw or part is not tightened, please tighten.
11)
After the equipment status check is normal, the following functions can be debugged.