11 FUNCTION TEST AFTER REPAIR WORK
After all repairs, the device must be checked for safe condition before recommissioning.
The necessary scope of inspection and testing depends on the repair carried out and must
be documented by the repair personnel.
12 DISPOSAL
NOTICE
Do not dispose of used electrical equipment with household
refuse!
In accordance with European Directive 2012/19/EU on the disposal
of used electrical equipment and its implementation in national
law, this product may not be disposed of with the household
refuse, but must be recycled in an environmentally correct manner.
WAGNER or one of our dealers will take back your used WAGNER
electric or electronic equipment and will dispose of it for you in an
environmentally-friendly way. To arrange this, please contact one
of our service centers, one of our representatives or us directly.
The consumable products (lacquers, adhesives, solvents) must be disposed of in accordance
with the applicable specific standards.
13 INSPECTIONS
13.1 INSPECTIONS IN ACCORDANCE WITH DIN 50176
If the system is used for electrostatic coating with ignitable liquid coating products
(solvent-based lacquers), the inspection in accordance with DIN EN 50176: 2010-04 as per
table 3 must be performed.
13.1.1 OVERVIEW OF INSPECTIONS
Section
Type of inspection
Requirements
1
Inspection for safe operational
condition
Safe operational condition of the complete system
2
Inspection of technical ventilation
Effectiveness of technical ventilation
3
Switch-off of the high voltage in
voltage-controlled and constant
voltage operating modes
Safe switch-off of high voltage
4
Switch-off of high voltage in
constant current operating mode
Safe switch-off of high voltage
5
Protection against excessively high
discharge energy
Safe discharge of all high-voltage conducting parts after
switching off high voltage
6
Protection against ignition of
cleaning agents
After switching off the high voltage and before using
ignitable solvents, safely discharge all parts carrying high
voltage.
7
Protection against direct contact
Safe switch-off of the high voltage for access to live
system parts
8
Grounding inspection
Grounding of the complete system