41
10.
Open the gas shut-off valve and start the appli-
ance.
Danger
Gas escaping from the test connector leads
to a risk of explosion.
Check gas tightness at test connector
A
.
11.
Fit front panel (see installation sequence).
Supply pressure (flow pressure)
Measures
For natural gas
For LPG
< 13 mbar (1.3 kPa)
< 25 mbar (2.5 kPa)
Do not start the boiler. Notify the gas supply utility or
LPG supplier.
13 - 25 mbar (1.3 -
2.5 kPa)
25 - 57.5 mbar (2.5 -
5.75 kPa)
Start the boiler.
> 25 mbar (2.5 kPa)
> 57.5 mbar (5.75 kPa)
Install a separate gas pressure governor upstream of
the system. Set the pre-charge pressure to 20 mbar
(2.0 kPa) for natural gas and 50 mbar (5.0 kPa) for
LPG. Notify the gas supply utility or LPG supplier.
Function sequence and possible faults
Display
Measure
Control unit issues a heat
demand
No
Increase set value. Ensure
heat transfer.
Yes
Fan starts
No
Fault 59, 457
Check the fan connecting ca-
bles. Check the fan power
supply.
Yes
Ignition
No
Fault 359
Check ignition module (con-
trol voltage 230 V across
plug "X1/54" terminals "L"
and "N" on the HBMU).
Check the gas supply.
Yes
Gas solenoid valve opens
No
Fault 357
Check the gas supply pres-
sure.
Yes
Ionisation current builds
No
Fault 369, 380
Check distance of ionisation
electrode on burner gauze
assembly.
Purge the gas line.
Commissioning, inspection, maintenance
Checking the static pressure and supply pressure
(cont.)
6167586