7. Commissioning and Operation of the Lynx Smart BMS
7.1. Commissioning the Lynx Smart BMS
Commissioning sequence:
Check polarity of all battery cables.
Check cross sectional area of all battery cables.
Check that each battery has the most up to date firmware.
Check that if batteries have been connected in series, that each battery has been fully pre-charged (refer to battery
manual).
Check if all battery cable lugs have been crimped correctly. Check if all battery cable connections are tight (don’t
exceed maximum torque). Tug slightly on each battery cable and see if the connections are tight.
Check all BMS cable connections and make sure the connector screw rings are screwed all the way down.
Check if each paralleled battery is fused or that each paralleled battery series string is fused.
If a GX device is used, check if the VE.Can cables and terminator have been placed and the device is powered
from the AUX voltage output of the Lynx Smart BMS.
Power the Lynx Smart BMS by connecting the battery supply or placing the battery fuses and, if applicable, by
switching the remote on/off switch to “on”.
Check that the load pre-charge is complete, the contactor is closed, and the loads are energised.
Connect to VictronConnect and make sure the Lynx Smart BMS has the latest firmware and that all settings have
been made, in particular that the battery capacity and the number of paralleled batteries is set correctly.
Check that the system voltage has been set correctly.
Check if the fuse names of the Lynx Distributor (if applicable) are correctly named.
If a GX device is connected, check that it is powered from the Lynx Smart BMS AUX terminals.
Check that the Lynx Smart BMS displays correctly on the GX device.
Disconnect a random BMS cable and verify that the BMS is turning off all charge sources and all loads. Reconnect
the BMS cable.
Turn on a load and check that the current is a negative current displayed on the GX device or the VictronConnect
app.
Charge batteries fully and check that a 100% state of charge is displayed
7.2. Powering up
The Lynx Smart BMS will power up when a battery is connected to the battery terminals and the Remote on/off switch is turned
on (or the wire loop is placed in the remote on/off terminal).
The power up sequence follows these steps:
•
System check
: A self-test that checks the internal and external voltages and contactor.
•
Pre-charge loads
: The pre-charge circuit will pre charge capacitive loads such as inverters or inverter/ chargers before the
contactor closes to prevent very high inrush current.
•
Contactor closes
: The Lynx Smart BMS is operational and the power to the Lynx Distributor(s) is turned on.
Operational
Once powered up, the contactor is closed. The green status LED together with the blue Bluetooth LED on the Lynx Smart BMS
and the green power LED on Lynx Distributor(s) are illuminated.
Lynx Smart BMS
Page 18
Commissioning and Operation of the
Lynx Smart BMS
Содержание Lynx Smart BMS 500
Страница 1: ...Lynx Smart BMS ENGLISH ...
Страница 20: ...Lynx Smart BMS Page 17 Configuration and settings ...