6.1.3 Connecting the Equipment
Refer to the user/install manuals for each piece of equipment as required.
1.
Make all connections to the UPS BDC cabinets (input power and Liebert® MBX).
•
The UPS requires an upstream over-protection device (a circuit breaker or manual isolation switch.
•
Install the protection device per local codes and agency requirements.
2.
Make all power, coolant and drain connections to the Liebert® CRV equipment.
3.
Connect the Liebert® MC Condenser (if applicable) control wire to the Liebert CRVs and route the wire to the
condenser based on the site-specific application.
4. Using the provided adapter cables, connect power to the Vertiv™ SmartRow™ vNSA and Vertiv™ SmartRow™
fan controller from the Liebert MBX busplug.
NOTICE
Risk of improper power input.
Improper power input can cause equipment damage or degrade performance.
6.1.4 Installing Expansion Channels
Refer to
on page 33 for detailed expansion channel installation instructions.
6.1.5 Finalizing Installation
1.
Install busplugs into the overhead Liebert MBX and align them with the Vertiv™ DCE racks that they power.
2.
Connect the rack PDU plugs into the busplugs.
3.
The 2T temperature sensors are pre-wired to each rack. Connect the sensors to the Liebert® CRVs in the row
and correctly set the 2T sensor DIP switches per the supplied instructions.
4. Cable the Liebert CRV iCOM and monitoring card to the Vertiv™ SmartRow™ network switch.
5.
Cable the UPS monitoring card to the Vertiv SmartRow network switch.
NOTICE
Do not run any cables in the expansion channels. Doing so will reduce the airflow and eliminate the ability to
remove the expansion channels. The expansion channels should not be removed unless absolutely necessary.
6.2 Optional Vertiv™ SmartRow™ DCX Control Panel and Fire Suppression System—Overview
The Vertiv SmartRow DCX must be installed in compliance with all applicable national, state and local fire codes. An
emergency power off (EPO) switch is provided as one means of meeting regulations. Additional field-supplied connections
to the system may be required, depending on the applicable regulations, the equipment configuration and the user’s
operational preference.
The optional Vertiv SmartRow DCX Control Panel and Fire Suppression System has been fully tested and certified at the
factory.
The Vertiv SmartRow DCX Control Panel and Fire Suppression System is shipped with wiring that, if required by local fire
code, must be field-connected to the shutdown circuits of the Liebert® CRV and any connected UPS systems.
Under NFPA regulations, systems protected by a clean fire-suppression agent can be left with the UPS and HVAC systems
operational at the discretion of the owner and local fire officials.
Vertiv
| SmartRow™ DCX Installation Manual |
20
Содержание SmartRow DCX
Страница 1: ...Vertiv SmartRow DCX Installation Manual...
Страница 6: ...Vertiv SmartRow DCX Installation Manual 6 This page intentionally left blank...
Страница 8: ...Vertiv SmartRow DCX Installation Manual 8 This page intentionally left blank...
Страница 26: ...Vertiv SmartRow DCX Installation Manual 26 This page intentionally left blank...
Страница 28: ...Vertiv SmartRow DCX Installation Manual 28 This page intentionally left blank...
Страница 30: ...Vertiv SmartRow DCX Installation Manual 30 This page intentionally left blank...
Страница 32: ...Vertiv SmartRow DCX Installation Manual 32 This page intentionally left blank...
Страница 34: ...Vertiv SmartRow DCX Installation Manual 34 Figure 10 1 Vertiv SmartRow DCX System Submittal Overview typical...
Страница 37: ...Vertiv SmartRow DCX Installation Manual 37 Figure 10 4 Vertiv SmartRow DCX System Submittal Dimensions typical...
Страница 38: ...Vertiv SmartRow DCX Installation Manual 38 Figure 10 5 Vertiv SmartRow DCX System Submittal Clearances typical...
Страница 39: ...Vertiv SmartRow DCX Installation Manual 39 Figure 10 6 Vertiv SmartRow DCX System Submittal One Line typical...
Страница 40: ...Vertiv SmartRow DCX Installation Manual 40 Figure 10 7 Vertiv SmartRow DCX System typical...
Страница 41: ...Vertiv SmartRow DCX Installation Manual 41 Figure 10 8 Vertiv SmartRow DCX Assembly 1 typical...
Страница 42: ...Vertiv SmartRow DCX Installation Manual 42 Figure 10 9 Vertiv SmartRow DCX Assembly 2 typical...
Страница 43: ...Vertiv SmartRow DCX Installation Manual 43 Figure 10 10 Vertiv SmartRow DCX Assembly 3 typical...
Страница 44: ...Vertiv SmartRow DCX Installation Manual 44 Figure 10 11 Vertiv SmartRow DCX Assembly 4 typical...
Страница 45: ...Vertiv SmartRow DCX Installation Manual 45 Figure 10 12 Vertiv SmartRow DCX Fan Control vNSA...
Страница 46: ...Vertiv SmartRow DCX Installation Manual 46 Figure 10 13 Vertiv SmartRow DCX Fan Control vNSA Cabling...
Страница 47: ...Vertiv SmartRow DCX Installation Manual 47 Figure 10 14 Vertiv SmartRow DCX UPS Spacer Kit...
Страница 48: ...Vertiv SmartRow DCX Installation Manual 48 Figure 10 15 Vertiv SmartRow DCX Liebert EXM Installation Pg 1...
Страница 49: ...Vertiv SmartRow DCX Installation Manual 49 Figure 10 16 Vertiv SmartRow DCX Liebert EXM Installation Pg 2...
Страница 50: ...Vertiv SmartRow DCX Installation Manual 50 Figure 10 17 Vertiv SmartRow DCX Liebert EXM Installation Pg 3...
Страница 51: ...Vertiv SmartRow DCX Installation Manual 51 Figure 10 18 Vertiv SmartRow DCX Liebert EXM Installation Pg 4...
Страница 52: ...Vertiv SmartRow DCX Installation Manual 52 Figure 10 19 Vertiv SmartRow DCX Liebert EXM Installation Pg 5...
Страница 61: ...Vertiv SmartRow DCX Installation Manual 61 Figure 10 28 Vertiv SmartRow DCX Racks with Expansion Channels...
Страница 66: ...Vertiv SmartRow DCX Installation Manual 66 Figure 10 33 Vertiv SmartRow DCX Server Rack Isometric Drawing...
Страница 67: ...Vertiv SmartRow DCX Installation Manual 67 Figure 10 34 Vertiv SmartRow DCX Server Rack Outline Drawing...
Страница 68: ...Vertiv SmartRow DCX Installation Manual 68 Figure 10 35 Vertiv SmartRow DCX Network Rack Isometric Drawing...
Страница 69: ...Vertiv SmartRow DCX Installation Manual 69 Figure 10 36 Vertiv SmartRow DCX Network Rack Outline Drawing...
Страница 72: ...Vertiv SmartRow DCX Installation Manual 72 This page intentionally left blank...
Страница 73: ......