Chapter 2 Installation Instruction
7
NetSure 731 A91 Subrack Power System
User Manual
2.4.2 Connecting AC Input Cables
Danger
Danger
1. Switch off all MCBs before the electrical connection.
2. Only the qualified personnel can do the mains cable connection.
For NetSure 731 A91-S1 power system, the position of the connection terminals are shown in Figure 2-6.After
connecting AC cables, fixing cables on top or side cable banding area by using cable ties.
Earthing screw
AC input terminal N
AC input terminal L3
AC input terminal L2
AC input terminal L1
Figure 2-6 Illustration of NetSure 731 A91-S1 connection terminal
Note
1. Recommended tightening torque of user grounding screw is 11N*M.
2. In case system earthing cable lessen, please add another fixing point except for the earthing screw.
2.4.3 Connecting Load Cables
Connect the negative load cable to the upper terminal of load MCB and then connect the positive load cable to
positive terminal. As shown in Figure 2-7.
Non- prority load
Prority load
Positive terminal
Figure 2-7 Illustration of the load cable connection terminal
Содержание NetSure 731 A91
Страница 2: ......
Страница 6: ......
Страница 8: ......
Страница 35: ...Appendix 3 Wiring Diagram 27 NetSure 731 A91 Subrack Power System User Manual Appendix 3 Wiring Diagram...
Страница 37: ...Appendix 3 Wiring Diagram 29 NetSure 731 A91 Subrack Power System User Manual...