Vertiv Tech ECM3 Series Скачать руководство пользователя страница 43

Chapter  3  Testing            37 

ECM3 Series Outdoor Power System    User Manual 

Chapter 3   Testing 

This chapter introduces the testing after installation. The corresponding safety rules shall be adhered to in the testing. 

3.1   Power-on 

 

Note 

1. Test the power subrack (if configured) in the cabinet at the very beginning. 

2. Before test, inform the manufacturer representative. Only trained electrical engineers shall conduct the test.   

3. Remove any metal objects that may cause short-circuit, including finger rings, watches, and so on. 

 
During operation, Watch out for hazardous voltage and avoid personnel injury and property loss. The power system 

must be properly earthed before power-on. Installation check (see Table 2-6) must be conducted before test. 

If a power subrack is configured in the cabinet, you must connect cables according to the user manual of the power 

subrack, and set battery capacity and charge/discharge management parameters according to actual situation. 

Modify the default charge/discharge parameters if they are against battery manufacturer regulations. After the power 

subrack is tested, you can start to test the cabinet system. 

Startup preparation 

Check item 

OK 

Comments 

Ensure that the system AC input and DC input are normal, all AC input MCBs, battery MCBs and load 

MCBs are switched off, and all devices are properly installed 

 

 

Measure the AC input voltage. Make sure that the input voltage is within the rated input range. For the 

system configured with an air conditioner, you need to confirm the AC input range: 220Vac ~ 230Vac/50Hz 

 

Umin

      V 

If batteries are connected, measure with a voltmeter across the connection points of each battery and make 

sure that the polarity is right. For a lead-acid battery with 24 cells, the voltmeter should read 2.0 ~ 2.1V/cell 

or 48V ~ 51V/battery string. If the voltage of certain cell is lower than 2.0V, that cell must be replaced 

 

Umin

      V 

Check with an ohmmeter that there is no short circuit between the positive & negative DC terminals (Note: 

Pull out all modules before the check and restore them after the check) 

 

 

 

Startup 

Check item 

OK 

Comments 

Switch on the system AC input MCB. The run indicator on the rectifier will be on and the fan will start 

running after a certain delay. The controller will show that the output voltage is 54.0V 

 

 

Check the system voltage and busbar polarity with a voltmeter. The voltage difference between the 

measured value and displayed value should be less than ±0.3V 

 

 

Close the MCB of thermal control unit 

 

 

 

3.2   System Operation Status Check 

Check item 

OK 

Comments 

Make sure that the temperature of internal cabinet is the same as that of the actual value. Hold the probe of 

the temperature sensor with hands, which should display the change of the temperature 

 

 

For thermal control unit of heat exchanger type, check if the internal fan runs normally and if the external fan 

runs or stops normally according to thermal control logics 

 

 

For thermal control unit of air conditioner type, check if the air conditioner runs or stops normally according 

to thermal control logics 

 

 

When the door is open, the light will be illuminated and there should be no other alarms except door open 

alarm (if the micro switch is selected) 

 

 

 

Содержание ECM3 Series

Страница 1: ...ntact the nearest Vertiv local sales office or service center Copyright 2017 by Vertiv Tech Co Ltd All rights reserved The contents in this document are subject to change without notice Vertiv Tech Co...

Страница 2: ...g the AC power system The installation personnel must be licensed to operate high voltage and AC power In operation the installation personnel are not allowed to wear conductive objects such as watche...

Страница 3: ...unit of the system or the non grounding pole and the earth The power system is constant voltage DC power equipment and short circuit will result in equipment burning and endanger human safety VI Rever...

Страница 4: ...ance of the cable and cable label with the actual installation prior to cable connection III Binding the signal lines Warning Notice Note The signal lines should be bound separately from heavy current...

Страница 5: ...tions 20 2 2 Preparation 20 2 3 Mechanical Installation 22 2 3 1 Disassembling On Site 25 2 3 2 Opening And Closing Cabinet Door 28 2 4 Electrical Installation 29 2 4 1 Installing Power Subrack 29 2 4...

Страница 6: ...4 Replacing Air Conditioner 42 4 2 5 Replacing LED Lamp 43 4 2 6 Replacing Micro Switch 44 Appendix 1 Spare Part List 45 Appendix 2 Schematic diagram 46 Appendix 3 Wiring diagram 50 Appendix 4 Glossar...

Страница 7: ...400mm ECM3 E14A 4 1 Air conditioner 800mm 800mm 1400mm ECM3 E14A 4 2 650mm 650mm 1400mm ECM3 B14A 1 1 Air conditioner type battery cabinet 800mm 800mm 1400mm ECM3 B14A 8 2 650mm 650mm 1400mm 1 2 Compo...

Страница 8: ...Thermal control unit Intelligent outdoor air conditioner 1 set cooling capacity 1500W no heating function Emergency ventilation unit 1 set max heat exchanging capacity 1000W temperature difference bet...

Страница 9: ...ment Heat exchanger 1 set max heat exchanging capacity 80W K Thermal control unit battery compartment Inteligent outdoor air conditioner 1set cooling capacity 300W no heating function Lighting Unit LE...

Страница 10: ...8 2 power system Component name Configuration Thermal control unit in battery compartment Intelligent outdoor air conditioner 1 set 300W cooling capacity no heating function Lighting unit LED lamp 1...

Страница 11: ...rd configuration Micro switch Power subrack NetSure 731 power subrack 1 set optional AC socket for user One 10A single phase AC socket 1 set standard configuration Environment monitoring FSU 1 set opt...

Страница 12: ...nit 1 set optional DC distribution unit 1 set optional The structure of ECM3 E14A 4 1 power system is same as that of ECM3 E14A 4 2 power system as shown in Figure 1 6 Air conditoner Power subrack AC...

Страница 13: ...Tri cabinet three user Battery compartment 9U 300A Subrack power 11U AC DU 3U FSU 1U Reserved space 2U DC DU 3U BBU 2U Transmission 2U ODF 4U DC DU 3U BBU 2U ODF 4U DC DU 3U BBU 2U ODF 4U Fiber stora...

Страница 14: ...ber cable Tri cabinet three user Battery compartment 9U Battery compartment 9U Battery compartment 9U DC power supply Battery output Fiber cable Battery input Cabling space 2U Cabling space 2U Cabling...

Страница 15: ...tput N AC output L Non priority load user 1 Non priority load user 3 Non priority load user 4 Priority load user 1 Priority load user 2 Priority load user 3 Priority load user 4 Figure 1 10 NetSure 73...

Страница 16: ...2A 1P 8 16A 1P 2 6A 1P 1 AC input MCB Netsure 731 A61 S2 S3 63A 4P 2 Netsure 731 A41 S7 63A 2P 2 AC output MCB Netsure 731 A61 S2 S3 5 16A 1P 4 10A 1P Netsure 731 A41 S7 2 16A 1P 1 10A 1P Battery MCB...

Страница 17: ...220Vac 230Vac 10 Rated input current 95A Max Input MCB 2 125A 2P manualy switch with mechanical mutual interlock AC SPD 60kA Max AC output 5 16A 1P 4 10A 1P 1 2 3 DC Distribution Unit Optional The pow...

Страница 18: ...Micro SD card slot max 32G Micro SD card can be inserted into the slot to expand the storage space of the monitoring equipment USB USB port for connecting modem LAN1 2 3 4 10M 100M self adaptive Ethe...

Страница 19: ...concentration reaches the sensor setting the system will generate a smoke alarm The appearance of the smoke sensor is shown in Figure 1 18 Figure 1 18 Appearance of smoke sensor Water logging sensor T...

Страница 20: ...temperature Without heating 10 C 45 C With heating 40 C 45 C Storage temperature 40 C 70 C Relative humidity Operating relative humidity 5 RH 95 RH 40 C 2 C Storage relative humidity 95 RH 40 C no con...

Страница 21: ...ger dissipates heat through a door mounted heat exchanger The internal circulation is as follows Hot air produced by the equipment goes in from the top passes the heat exchanger cools down goes out fr...

Страница 22: ...hot air is eliminated out from the top The wind direction is shown in Figure 1 23 External circulation Internal circulation Emergent ventialation Figure 1 23 Heat dissipation theory of ECM3 E14A 4 1...

Страница 23: ...ithin two hours In single battery cabinet if the selected air conditioner with heating function then the inside temperature can be heated from 20 C to 5 C within two hours If it needs to meet 40 C amb...

Страница 24: ...equipment compartment Classified into heat exchanger 80W K 190W K and air conditioner 1 5kW according to temperature control modes Meet the installation requirements of ODF DDF BBU and BTS through con...

Страница 25: ...is 300W air conditioner and can accommodate battery It supports 12V narrow type battery and max capacity is 300Ah The right unit is used as equipment compartment and can be of heat exchanger 190W K o...

Страница 26: ...ected properly so that the cables are kept away from the operation and maintenance personnel 6 Connect the field cable and tighten the screw according to the screwing torque shown in Table 2 1 to avoi...

Страница 27: ...mm2 17m 25mm2 71m Note The specifications are applicable at ambient temperature of 25 C If the temperature is too high the CSA of the cable should be increased To prevent the MCB stop working upon ove...

Страница 28: ...l installation holes depth 70mm at the marked positions by using a 16 drill Clean the dust off the holes and insert an expansion pipe into each installation hole Note The cement base should be at leas...

Страница 29: ...l SCALE 1 1 896 0 826 0 750 0 73 0 2694 0 826 0 826 0 72 0 72 0 Figure 2 3 Installation dimensions 800mm 800mm of multi cabinet base Unit mm 746 0 676 0 650 0 73 0 2244 0 72 0 72 0 676 0 676 0 Figure...

Страница 30: ...Installation of parallel connector Move the cabinet to the installation position Make the installation holes on the base coincide with those holes dug on the ground Screw the M12 60 anchor bolts down...

Страница 31: ...not use wrong screws in installation and counter sunk screws can only be used at the positions with counter sunk holes If any screw is missing find a replacement of the same size 4 Prepare ratchet wr...

Страница 32: ...kit from the top of the cabinet and then remove the top frame kit as shown in Figure 2 9 Top frame kit Rack M6 screw 8 pcs M12 screw 4 pcs Figure 2 9 Disassembling top frame kit 6 Disassemble front f...

Страница 33: ...plates 8 Disassemble the rear frame kit and internal rack kit as shown in Figure 2 12 1 Remove the two M10 screws used to fix the rear frame from the rear bottom part of the bottom frame then take of...

Страница 34: ...keyhole and rotate the key clockwise until a handle pops out 3 Turn the handle 120 counterclockwise as shown in Figure 2 14 And then pull the handle out until the door is open 120 120 Figure 2 14 Rot...

Страница 35: ...not need to install it again The position of the power subrack is shown in Figure 2 16 Power subrack Figure 2 16 Position of power subrack 2 4 2 Installing Rectifier Note 1 If there are vacancies amo...

Страница 36: ...ery make sure that the replacement is of the same type and capacity as the replaced battery Otherwise explosions may occur 7 Scrap used batteries according to related local laws 8 The system supports...

Страница 37: ...rol device of the cabinet as shown in Figure 2 18 Take the typical configuration battery cabinet power cabinet equipment cabinet for example when paralleling the cabinets you should connect the power...

Страница 38: ...o the PE bar reliably Plastic coated metal hoses are recommended Position Of Cable Entry Holes There are 16 cable entry holes at the bottom plate of each cabinet for cabling The position is shown in F...

Страница 39: ...e 2 20 in the cabinet and solder the other end to the earth metal base reliably 3 Use nylon cable ties to tie the earth cable to the cable holders Grounding bar Grounding bar Equipment cabinet Battery...

Страница 40: ...re delivery the DC cable connection between power subrack and cabinet should have been done by Emerson Users only need to connect load cables according to the power subrack user manual If the system h...

Страница 41: ...ver plate according to actual requirements after connecting cables The installation procedures are as follows 1 Insert the square nut see Figure 2 23 into the square hole at the cabinet base and drive...

Страница 42: ...tions of all MCBs and cables 2 Check the correctness of busbar connections input and output cable connection and the system earthing 3 Check the correctness of the battery cell number and connection a...

Страница 43: ...confirm the AC input range 220Vac 230Vac 50Hz Umin V If batteries are connected measure with a voltmeter across the connection points of each battery and make sure that the polarity is right For a le...

Страница 44: ...to its original condition and close the cabinet door Check and handover the equipment that the user has purchased Note down all the operations taken including time of the operation and name of the op...

Страница 45: ...this chapter No peels and scratches in paint and galvanization layer Once half a year Visual inspection If there are scratches and peelings paint them immediately Dust proof filter Once half a year V...

Страница 46: ...loosen the nine fixing screws of the heating unit cover and remove the heating unit cover as shown in Figure 4 3 Fixing screw of heating unit cover 9 pcs Remove heating unit cover Fan Fixing screw of...

Страница 47: ...MCBs and DC power supply in thermal control unit and unplug the power input terminals of the heater 2 Disconnect the power input terminals of the heating unit and loosen the four fixing screws of the...

Страница 48: ...4 6 16 16 pcs of combined nut plain washer and spring washer Heat exchanger Figure 4 6 Position of heat exchanger 3 Take out the heat exchanger from the outside of cabinet door 4 Install a new heat ex...

Страница 49: ...door 4 Install a new air conditioner and fix it with screws 5 Restore all cable connections of the air conditioner and switch on the thermal control AC output MCB of power subrack 4 2 5 Replacing LED...

Страница 50: ...amaged If the door is closed but the door open alarm occurs or the LED lamp is illuminated the micro switch may have been damaged and needs to be replaced The position of the micro switch is shown in...

Страница 51: ...60mm axial flow fan 32010478 Forced ventialtion fan 120mm axial flow fan 32010500 PCBA LED lamp board PCBA ECM250001X1 03029134 Heating unit 02357627 Heater 02510041 60mm axial flow fan 32010478 Temp...

Страница 52: ...Battery unit Thermal control unit Environment monitoring Power cabinet Equipment cabinet AC input cable AC cable DC cable DC power cable Battery power cable RS485 signal cable Typical tri cabinet sys...

Страница 53: ...A 6A 25A 63A 10A 10A NPL PL NPL PL NPL PL NPL PL DC power like thermal control lightning PE L3 L2 L1 N Optional Batt 1 2 1 2 1 2 1 2 1 2 1 2 1 2 FSU FSU analog input 1 2 Communication cable Thermal co...

Страница 54: ...Typical HEX power cabinet equipment cabinet themal control COM 48V Heater Heating unit Optional L N PE 0V 48V FU KT1 KT2 Fan2 PTC1 PTC2 Fan1 DCPD ACPD HTR1 LED Lamp Heating unit L N PE 0V 48V FU KT1 K...

Страница 55: ...HEX LED1 LED Lamp HEX AC2 300 W AC Power cabinet thermal control Heater PTC1 PTC2 Fan2 Fan1 L N PE 0V 48V DCPD ACPD ACPD To FSU RS485 RS485 To FSU Thermal contrl 300W AC A B COM NO NC 1 2 PE N L RS485...

Страница 56: ...J2 11 YG 12 WD 13 SJ 14 HW 16 1 2 1 2 L 1 2 M8 M8 W04 W04 W04 W04 W04 W01 W01 W01 W01 W01 ACIN 10 For L1 L2 L3 N PE AC input L1 N B SPD PE L2 L3 N CK L1 CK L3 CK L2 CK N W07 W07 W07 2 1 T8 AC socket 2...

Страница 57: ...V AG DI3 DI4 12V AG DI5 DI6 12V 12 3 12 1 12 4 12 1 12 3 12 1 12 4 AG DI7 DI8 12V AG DI9 DI10 12V AG 12V DI11 DI12 11 1 11 2 11 2 11 2 11 1 11 1 16 3 16 2 16 1 485 A 485 B W18 W18 Brown Black Optional...

Страница 58: ...48V 48V 48V 3 4 5 6 MJ1 30 LED 31 HEX 32 JR 1 33 FANS 34 KT 1 35 MJ1 30 LED 31 PE W03 Cabinet door HEX PE W05 AC PE W06 Cabinet door PE Heater JR 2 41 Heating unit Optional L N PE 0V 48V FU KT1 KT2 F...

Страница 59: ...8V 48V JR 1 33 HEX 32 KT 2 36 KT 1 35 MJ1 30 LED 31 MJ1 30 LED 31 PE W03 Cabinet door LED Lamp LED Lamp Heating unit PTC1 PTC2 HTR1 Optional FU KT1 KT2 Fan2 Fan1 To FSU T6 H RS485 Micro switch LED1 HE...

Страница 60: ...t charge BLVD Battery lower voltage disconnection LCD Liquid crystal display PE Protective earth LLVD Load low voltage disconnection LVD Low voltage disconnection MCB Miniature circuit breaker PWD Pas...

Отзывы: