Three other methods are also approved by the NFPA:
•
Using a section of double-wall chimney with a
9 mm (9”) clearance to combustibles.
•
Placing a section of chimney connector inside
a ventilated thimble, which in turn is separated from
combustibles by 15 mm (6”) of fiberglass insulating
material.
•
Placing a section of chimney connector inside a
section of 9 mm (9”) diameter, solid-insulated, facto-
ry-built chimney, with 51 mm (”) of air space between
the chimney section and combustibles.
Figure 10 shows one method of passing a connector
through a wall. All combustible material in the wall is cut
away to provide the required 457 mm (18”) clearance
* Check These
Clearances
ST244
Plymouth
fplc over mantel
12/99
*
*
Chimney
Connector Shields
Mantel
Seal Damper
to Air Flow
ST44
fig. 7
In this installation, the chimney connector is attached
to the chimney above the fireplace opening.
ST245
fireplace
flex connector
12/99
Flexible Connector
Mantel Shield
Fireplace Adapter
Kit “Positive Con-
nection”
ST45
fig. 8
In this installation, the chimney connector enters the
firepalce opening and then connects to the chimney.
through the fireplace
If your fireplace opening height is at least 675 mm
(6
¹⁄₂
"), you may install an Encore through the opening
using a “positive connection” kit, available from your lo-
cal dealer. These positive connection kits ensure a tight
fit between the stove flue collar and the chimney flue.
(Fig. 8)
Fireplace installations, whether connected to the flue
above or through the fireplace opening, have special
clearance requirements to adjacent trim and the mantel.
You’ll find the required safe clearances for Encore fire-
place installations on Page 1 and Figure 14.
Floor protection requirements also apply to fireplace
installations. This information is on Page 19.
wall pass-throughs
Whenever possible, design your installation so the con-
nector does not pass through a combustible wall. If you
are considering a wall pass-through in your installation,
check with your building inspector before you begin.
Also, check with the chimney connector manufacturer
for any specific requirements.
Accessories are available for use as wall pass-
throughs. If using one of these, make sure it has been
tested and listed for use as a wall pass-through.
Figure 9 shows one recommended method. All combus-
tible material in the wall is cut away from the single-wall
connector to provide the required 305 mm (1”) clear-
ance. Any material used to close up the opening must
be noncombustible.
T
ST494
steel
wall pass thru
11/00
18” (460mm) clear
space all around
the pipe
ST494
fig. 9
An approved wall pass-through for Canada.