To turn on the appliance
1
Verify that all connected storage shelves function correctly. Use the LED
information in the procedure that explains how to turn on the storage shelves.
2
On the front, right, side of the appliance press the Power button.
3
Verify that the bottom LED in all 12 disk drive slots are green.
The following table provides details of the disk drive LEDs.
Description
States
LED number,
name, and
location
No fault
Disk fault
A RAID rebuild is in progress
Off
Solid amber
Blinking amber
1, Status LED, top
Power is on and the disk has spun
down
Power is on but there is no disk activity
Power is on and the disk is spinning up
Commands are processing
Off
Solid green
Blinking green
Blinks green occasionally
2, Activity LED,
bottom
Installation procedures
Turning on the hardware and verifying operation
56
Содержание NetBackup 5240
Страница 1: ...NetBackup Appliance Hardware Installation Guide Release 2 7 3 NetBackup 5240 Document Revision 1 ...
Страница 4: ......
Страница 22: ...Preinstallation requirements Prerequisites for IPMI configuration 22 ...
Страница 42: ...Installation procedures Connecting a 4TB appliance to more than one storage shelf 42 ...
Страница 43: ...43 Installation procedures Connecting a 4TB appliance to more than one storage shelf ...
Страница 66: ...Installation procedures Accessing and using the Veritas Remote Management interface 66 ...
Страница 140: ...Adding storage shelves to an operating 4TB appliance that has at least one storage shelf attached Recabling 140 ...