B) Monorail Assembly for Tension Strut Backup
Locate the Tension Strut Backup on foundation with side of Monorail on the construction
line on page 46 (Figure 52). Verify that any applicable Transition Panels fit properly before
anchoring Backup. Drill anchor holes in foundation using the Backup as template. Anchor
the Backup to the concrete foundation using the approved adhesive kit supplied with the
QuadGuard
®
(p. 12).
Warning:
Every borehole and slot in Backup and Monorail must be anchored by
a stud using an approved adhesive
.
Monorail Alignment
It is important to align each segment of Monorail from the back to the front of the system
(±1/4” [6 mm]). Anchor each Monorail section using the provided Valtir approved adhesive
kit. See Figure(s) 50, 52 - 54 and the approved adhesive instructions included with the
adhesive kit (p. 12).
Drill 0.78” [20 mm] diameter by 5 3/4” [145 mm] boreholes using the Monorail as a template.
Do not drill through foundation.
Figure 49
Anchoring Tension Strut Backup to Foundation
Top surfaces
must
be flush
Tongues must be
Fully Inserted
and Flush
Detail A
Figure 50
Rail Height and Alignment
Detail A
VERTICAL ADHESIVE KIT
WITH 3/4” X 7” STUD
TENSION STRUT BACKUP
Содержание QuadGuard
Страница 1: ...VALTIR QuadGuard CRASH CUSHION ASSEMBLY MANUAL PN 115348 REVISION D NOVEMBER 2022...
Страница 40: ...Valtir com 39 Revision D November 2022 Wide System Identification Figure 39 Wide Systems and Model Numbers...
Страница 65: ...Valtir com 64 Revision D November 2022 Notes...
Страница 66: ...Valtir com 65 Revision D November 2022 Notes...
Страница 67: ...Valtir com 66 Revision D November 2022 Notes...
Страница 68: ......