Remove all components from crate. It may be to the
1.
installer’s advantage to place the cast iron boiler block
close to where the final installation location will be.
Boiler may be piped and pressurized before
installing jackets & components.
NOTICE
Attach top and bottom rear intermediate panels with
2.
5/16”x1/2” bolts & washers. Be sure top flanges point
toward the front of the boiler. Bottom panel flanges
will point rearward. Hold bottom flange to top of holes
while tightening bolts. See
Figure 1
.
Figure 1
Bottom Intermediate
Top Intermediate
Rear of Boiler
P/N 240007211, Rev. B [06/08]
KNOCKDOWN ASSEMBLY
Instructions for
TriFire Oil Fired Boiler
SUPPLEMENT
AL INSTRUCTIONS
This assembly must be completed by a qualified installer or service agency, in accordance with the
manufacturer’s instructions, and in accordance with all codes and requirements of the authority having
jurisdiction. Failure to follow these instructions could result in fire or explosion resulting in property dam
-
age, personal injury, or loss of life.
WARNING
!
Wrap insulation around boiler with the smooth side out.
3.
Be sure to overlap underneath boiler. Wrap 2 banding
strips around insulation and tie as shown in
Figure 2
,
Cut off excess banding material. The rear insulation is
not installed until step 11.
Figure 2
1