Sageon III Power System
Installation
PM990-8800-00, Rev. 9
2-17
To install a transducer kit:
1
Mount the transducer(s) with user-supplied hardware. Figure 2-15 shows a typical transducer. Often, transducers are mounted on
the battery rack. The location must allow for convenient routing of one or more battery cables, or intercell connectors, through
each of the transducers. The three possible installation options are:
a.
If transducer is installed on the positive lead(s) of the battery string, the arrow will point toward the battery string’s
positive post.
b.
If the transducer is installed on the negative lead of the battery string, the arrow will point toward the power system
– away from the battery string’s negative post.
c.
If the transducer is installed on one of the intercell connectors the arrow on the transducer will always point to the
positive post of the next battery cell in the battery string. If the intercell strap will not fit through the current
transducer, the strap may be replaced with a short cable, lugged on both ends that will fit through the transducer;
consult the factory.
2
Open the distribution door and locate the supplied battery current transducer cables; there is one cable per transducer. The 4-
conductor cables are coiled and tied to the return bus (loads) in the distribution area of the Sageon III Power System. The length
of the supplied cables is 4 ft. (29.1m).
3
Refer to Table 2-5 and connect the battery current transducer cable(s) to the Battery Distribution Module connector(s). See Figure
3-14 for a view of the Battery Distribution Module.
4
Route the cable through overhead cable trays to the transducer. Connect the cable to the transducer.
6 / 152
2.5 / 64
1 / 25
Connector
4-pin
Dimensions are
inches / mm.
C
D
0003
9a
Direction of Positive Current
Flow with Batteries Charging
Top View
Side View
FIGURE 2-15 TYPICAL BATTERY CURRENT TRANSDUCER
TABLE 2-5 BATTERY CURRENT TRANSDUCER CONNECTIONS
Battery Current Transducer Battery Distribution Module Board
1
X22 in Figure 3-12
2
X18 in Figure 3-12
3
X17 in Figure 3-12
4
X12 in Figure 3-12
2.11 SAGEON BATTERY MONITOR (OPTION)
The UNIPOWER Sageon Battery Monitor (SBM) is an add-on System for the Sageon III Control Unit (SCU). It is used to monitor
individual cells of a battery during float or equalization operation, or during a discharge. Each SBM unit is capable of monitoring up
to 24 cells or monoblocks. Up to four SBM units can be used to monitor up to 4 battery strings of 24 cells or monoblocks each.
Содержание Sageon III
Страница 43: ...Installation Sageon III Power System PM990 8800 00 Rev 9 2 22 FIGURE 2 20 SAGEON III BOARD LOCATIONS...
Страница 46: ...Sageon III Power System Commissioning PM990 8800 00 Rev 9 3 3 FIGURE 3 1 SINGLE PHASE FEED PHASE TO NEUTRAL...
Страница 47: ...Commissioning Sageon III Power System PM990 8800 00 Rev 9 3 4 FIGURE 3 2 SINGLE PHASE FEED PHASE TO PHASE...
Страница 50: ...Sageon III Power System Commissioning PM990 8800 00 Rev 9 3 7 FIGURE 3 5 Y THREE PHASE FEED PHASE TO NEUTRAL...