Sageon III Power System
Installation
PM990-8800-00, Rev. 9
2-1
2.0 INSTALLATION
This chapter describes installing a Sageon
™
III Power system. If questions or problems arise during installation, please refer to Section
1.6 Product Support and contact a UNIPOWER Field Service technician for assistance.
The Power system is factory assembled and tested. GJ1 circuit breakers specified on the order are factory installed. AM1 circuit
breakers specified on the order are shipped in protective packaging for on-site installation. Rectifiers specified on the order are
shipped in separate, protective packages for on-site installation.
The Power system is designed for top-entry of distribution and battery cabling. AC input cabling can enter the plant through any lower
side/rear panels or through the bottom of the plant when the plant is located on an elevated floor. All cabling is user-supplied.
WARNING
Electrical shock hazard
Hazardous voltage can cause death or serious injury.
Remove power from all wires and terminals before working on equipment.
IMPORTANT:
All wiring must meet the National Electrical Code and other applicable industry and local codes.
The Breaker/Fuse Layout label on the inside of the door to the distribution area lists all distribution positions. The label provides space
for you to write breaker/fuse current rating and part number. Label entries should be completed before beginning the installation to
help ensure that the correct breaker/fuse is inserted in each position.
Rectifier Position Address
Each rectifier position is factory-assigned a unique, sequential address within the Sageon III Power System. The System operator uses
this address when configuring and operating the System to identify and access a specific Rectifier. The AC Backplane board at each
rectifier position has one DIP switch on which the address is set. See the illustration below.
IMPORTANT:
Do not change the factory-set switches. If inadvertently changed, go to Section 6.6 for a procedure to set the
switches to the proper address.
Opening the Distribution Area Door
During installation, it will be necessary to open the distribution area door to install load supply and return cables, battery cables, and
alarm wires. Lift the paddle surrounding the key lock, rotate it 90 degrees, and open the door. Keys are tied just inside the door.
2.1 INSTALLATION SUMMARY
A typical installation sequence is provided below. References to appropriate sections in this manual are included.
6.
Review the list of user-supplied tools and accessories in Section 2.2.
7.
Select a location for the Power system. See Section 2.3.
8.
Select battery, AC input, and distribution wire sizes based on current and length of run. See Section 2.2.
Содержание Sageon III
Страница 43: ...Installation Sageon III Power System PM990 8800 00 Rev 9 2 22 FIGURE 2 20 SAGEON III BOARD LOCATIONS...
Страница 46: ...Sageon III Power System Commissioning PM990 8800 00 Rev 9 3 3 FIGURE 3 1 SINGLE PHASE FEED PHASE TO NEUTRAL...
Страница 47: ...Commissioning Sageon III Power System PM990 8800 00 Rev 9 3 4 FIGURE 3 2 SINGLE PHASE FEED PHASE TO PHASE...
Страница 50: ...Sageon III Power System Commissioning PM990 8800 00 Rev 9 3 7 FIGURE 3 5 Y THREE PHASE FEED PHASE TO NEUTRAL...