107672-01- 7/17
C. Near Boiler Piping Design
Proper operation of this boiler requires that the water flow rate through it remain within the limits shown in Table 9.1
any time the boiler is firing. At flow rates below the minimum shown, the boiler’s flow switch and/or temperature rise limit
function may prevent the boiler from firing. Flow rates through the boiler in excess of the maximum shown in Table 9.1 can
result in excessive noise or erosion damage to piping
There are two basic methods that can be used to pipe this boiler into the system. Method #1 (primary-secondary piping)
is always preferred. Additional information on hydronic system design can be found in the
I=B=R
Guide RHH published by
the Air-Conditioning, Heating and Refrigeration Institute (AHRI).
Model
Flow (GPM)
Minimum
Maximum
080
5.0
13.3
100
5.1
13.3
120
6.2
13.3
150
7.7
13.3
180
9.3
13.3
Method 1: Primary/Secondary Piping (Strongly Recommended)
This method can be used in heat-only applications as shown in Figures 9.2 and 9.2a or with an indirect water heater as shown
in Figure 9.3a or 9.3b. In this system, the flow rate through the boiler (“secondary loop”) is completely independent of the
flow rate through the system (“primary loop”). Use the following guidelines to ensure that the boiler will have the required
flow shown in Table 9.1 regardless of the flow in the heating system.
1) System Loop Piping - Size the system circulator and piping to obtain the design flow rate through the heating system
as you would on any other heating system. All piping between the expansion tank and secondary connection tees must
be at least 1”. In order to keep the flow rates in the system and boiler loops independent of each other, provide at least
8 diameters of straight pipe upstream of the first tee and 4 diameters downstream of the second tee. Keep the distance
between the expansion tank and the first secondary tee as short as practical.
2) Boiler Loop Piping – All boilers are supplied with a built in circulator which will deliver the flow required by Table 9.1
provided both of the following conditions are met:
• All piping in the boiler loop has a nominal size of at least 1”
• The equivalent length of all piping in the boiler loop is 60 ft or less.
To verify that the 60 ft, equivalent length is not exceeded, do the following:
a) Count all fittings in the planned boiler loop (the shaded piping in Figure 9.6). In doing so, do not count the
secondary connection tees, unions, or the fittings supplied with the boiler (these have already been accounted for).
b) Using Table 9.4, find the equivalent lengths of all fittings in the secondary loop. Total these equivalent lengths and
add them to the total length of planned straight pipe in the secondary loop.
c) The result is the total equivalent length of the planned boiler loop. If the equivalent length calculated in (b) is
under the limit shown in Table 9.5, the boiler pump will achieve a flow rate and temperature rise approximately
equal to that shown in this table. Otherwise, the equivalent length must be reduced.
IX. System Piping
(continued)
nOTiCE
Use of antifreeze increases boiler and system head loss and may require larger circulators. Consult
antifreeze manufacturer for proper antifreeze concentration and head loss calculation.
Содержание K2WT-080B
Страница 11: ...11 107672 01 7 17 Figure 5 1 Wall Layout Mounting Hole Location V Mounting The Boiler continued...
Страница 79: ...79 107672 01 7 17 Figure 9 6 Piping Method 1 Near Boiler Piping Shaded Boiler Loop IX System Piping continued...
Страница 83: ...83 107672 01 7 17 PAGE LEFT INTENTIONALLY BLANK...
Страница 89: ...89 107672 01 7 17 X Wiring continued Figure 10 5 Internal Ladder Diagram...
Страница 90: ...90 107672 01 7 17 X Wiring continued...
Страница 91: ...91 107672 01 7 17 Figure 10 6 Internal Wiring Connections Diagram X Wiring continued...
Страница 93: ...93 107672 01 7 17 Figure 10 8 TACO SR504 or Equivalent Zone Panel Wiring Connection Diagram X Wiring continued...
Страница 94: ...94 107672 01 7 17 X Wiring continued Figure 10 9 Sage Zone Control Circulator Panel Wiring Connection Diagram...
Страница 102: ...102 107672 01 7 17 Lighting and Operating Instructions XI Start Up and Checkout continued...
Страница 147: ...147 107672 01 7 17 XV Service Parts continued...
Страница 151: ...151 107672 01 7 17 XV Service Parts continued...
Страница 153: ...153 107672 01 7 17 XV Service Parts continued 85 86 91 95...
Страница 162: ...162 107672 01 7 17...
Страница 163: ...163 107672 01 7 17...
Страница 164: ...164 107672 01 7 17...
Страница 165: ...165 107672 01 7 17...
Страница 166: ...166 107672 01 7 17...
Страница 167: ...167 107672 01 7 17...
Страница 168: ...168 107672 01 7 17 U S Boiler Company Inc P O Box 3020 Lancaster PA 17604 1 888 432 8887 www usboiler net...