background image

125

107672-01- 7/17

XII.  Operation 

F. Changing Adjustable Parameters (continued)

“Press” 

 

button to access the following parameters:

Factory 

Setting

Range / Choices

Parameter and Description

180°F

(82.2°C)

60°F to 190°F

(16°C to 87.8°C)

Auxiliary Heat Setpoint

Target temperature for the Auxiliary Heat priority.  Value also used by the outdoor air reset   

 function.

10°F

(5.6°C)

2°F to 25°F

(1.1°C to 14°C)

Auxiliary Heat Diff Above

The boiler stops when the water temperature rises ‘Diff Above’ degrees above the setpoint.

nOTE

Never set the Diff Above such that the Setpoint plus the ‘Diff Above’ is greater than 200°F.  The 

result may be nuisance manual reset hard lockouts.  For example, if the setpoint is 180°F, the 

maximum ‘Diff Above’ is 20°F.  Further, if the setpoint is 190°F, the maximum ‘Diff Above’ is 10°F.

5°F

(2.8°C)

2°F to 25°F

(1.1°C to 14°C)

Auxiliary Heat Diff Below

The boiler starts when the water temperature drops ‘Diff Below’ degrees below the setpoint.

3

1 to 5

Response Speed

This parameter adjusts the Auxiliary Heat temperature controller Proportion Integral Derivative 

(PID) values.  Higher values cause a larger firing rate change for each degree of temperature 

change.  If set too high firing rate “overshoots” required value, increases to high fire causing the 

temperature to exceed the “Diff Above” setpoint and cycle the boiler unnecessarily.  Lower values 

cause a smaller firing rate change for each degree of temperature change.  If set too low, the 

firing rate response will be sluggish and temperature will wander away from setpoint.

Disable

Disable, Enable

Auxiliary Priority Over Central Heat

This parameter allows the Auxiliary Heat demand to be higher or lower priority than Central Heat 

demand.  When both demands are active at the same time the Control uses the Setpoint, Diff 

Above and Diff Below for the demand that has priority.
Disabled               Auxiliary Heat is lower priority than Central Heat demand.

Enable                 Auxiliary Heat is higher priority than Central Heat demand.

DHW 

Demand

Auxiliary Heat, 

DHW Demand

DHW Terminal Use

The Control’s “DHW Temp Switch” input terminal may be used as a Domestic Hot Water (DHW) 

demand or Auxiliary Heat demand.  When the “DHW Terminal Use” is set to Auxiliary Heat a 

contact closure sensed at the DHW terminal will cause an Auxiliary Heat to call for heat.
DHW Demand:     DHW Heat demand may be wired to DHW Terminal.

Auxiliary Heat:  Auxiliary Heat demand may be wired to DHW Terminal.

Supply 

Sensor

Supply Sensor, 

Header Sensor

Modulation Sensor

Heat Demand may respond to the boiler’s Supply Temperature or Header Temperature sensors.  

When Header Sensor is selected the boiler is fired in response to the sensor wired to Header 

Sensor Low Voltage Terminal Block Terminals.

Содержание K2WT-080B

Страница 1: ...ormation consult a qualified installer service agency or the gas supplier This boiler requires a special venting system Read these instructions carefully before installing 9700609 As an ENERGY STAR Pa...

Страница 2: ...stantial property damage CAUTION Indicates a potentially hazardous situation which if not avoided may result in moderate or minor injury or property damage WARNING Indicates a potentially hazardous si...

Страница 3: ...disconnect any components of this boiler without positively assuring the water is cool and has no pressure Always wear protective clothing and equipment when installing starting up or servicing this...

Страница 4: ...ls carbon monoxide nitrogen oxides and or other toxic or harmful substances that can are hazardous to health and life and that are known to the State of California to cause cancer birth defects and ot...

Страница 5: ...Polyflue Vent Systems 56 H Assembly of Centrotherm InnoFlue Vent Systems 60 I Assembly of Stainless Steel Vent Systems 64 J Condensate Trap and Drain 66 K Removing An Existing Boiler From Common Chim...

Страница 6: ...ly with combustion air sup plied from outdoors It is not designed for use in gravity hot water systems or systems containing significant amounts of dissolved oxygen I Product Description 15 A SEE TABL...

Страница 7: ...on of this boiler depends upon installation by a professional heating contractor in strict accordance with this manual and the requirements of the authority having jurisdiction In the absence of an au...

Страница 8: ...e minimum clearances shown in Figure 4 1 These clearances apply to combustible construction as well as non combustible walls floors ceilings and doors 2 Note the recommended service clearances in Figu...

Страница 9: ...07672 01 7 17 Figure 4 1 Minimum Clearances To Combustible Construction IV Locating the Boiler continued LEFT SIDE CLEARANCE MAY BE REDUCED TO 1 2 HOWEVER RELIEF VALVE MUST REMAIN IN SAME SPACE AS BOI...

Страница 10: ...e holes A and B Make sure that the horizontal centerline of these holes is level Holes C and D may also be drilled at this time or after the boiler is hung on the wall If the 5 16 x 2 lag screws are u...

Страница 11: ...11 107672 01 7 17 Figure 5 1 Wall Layout Mounting Hole Location V Mounting The Boiler continued...

Страница 12: ...12 107672 01 7 17 Figure 5 2 Boiler Mounting Bracket Installation Boiler Wall Mounting V Mounting The Boiler continued...

Страница 13: ...ther appliances provide adequate air for combustion and or ventilation air in accordance with the manufacturer s installation manual or applicable code VI Air for Ventilation WARNING Outdoor combustio...

Страница 14: ...y as permitted in this manual All PVC must be listed to ASTM D2665 At least 30 of CPVC pipe and at least one CPVC elbow must be installed between the boiler s vent connection and the PVC pipe Use of f...

Страница 15: ...15 107672 01 7 17 Figure 7 0c Split Venting VII Venting A Vent System Design continued Figure 7 0a Horizontal Twin Pipe Figure 7 0b Vertical Twin Pipe BOILER...

Страница 16: ...addition to the first 90 elbow If more elbows are desired the maximum allowable vent length must be reduced by the amount shown in Table 7 1B for each additional elbow used Termination fittings are n...

Страница 17: ...A a To properly install attenuator insert approximately a 9 length CPVC pipe in vent adaptor b Fit a 3 CPVC coupling on length of pipe Glue coupling to pipe using a field supplied cement and primer th...

Страница 18: ...lengths shown in Tables 7 5 7 13 and 7 21 6 Clearances to Combustibles Maintain the following clearances from the vent system to combustible construction Vent 1 4 also observe clearances through both...

Страница 19: ...C PVC pipe design the vent system shall allow 3 8 of thermal expansion for every 10ft of CPVC PVC pipe The boiler will always act as an anchor to one end of the vent system If at all possible select a...

Страница 20: ...20 107672 01 7 17 VII Venting A Vent System Design continued Figure 7 3 Expansion Loops for CPVC PVC Pipe Figure 7 3b Figure 7 3a Figure 7 4 Wall Penetration Clearances for PVC Vent Pipe Figure 7 3c...

Страница 21: ...ay not be snorkeled Terminal Option B Ipex Low Profile Terminal Acceptable for Vent Options 1 2 This terminal is shown in Figure 7 7 If the terminal is oriented vertically alternate orientation shown...

Страница 22: ...ISEP0239 w screen ISEP03 or ISEP0339 w screen Intake Elbow w screen Note 3 Elbow w screen Note 3 Elbow w screen Elbow w screen Elbow w screen Elbow w screen Elbow w screen Elbow w screen Terminal Opt...

Страница 23: ...rs and relief equipment Do not install vent terminal over this equipment In Canada refer to B149 1 Installation Code for clearance to meters regulators and relief equipment Do not locate the vent term...

Страница 24: ...quirements Unique to Horizontal Twin Pipe Venting Systems continued PITCH INTAKE AWAY FROM BOILER IF POSSIBLE BOILER ROOM PVC AIR INTAKE PIPE CPVC VENT PIPE FIRST 30 ELBOW PVC VENT PIPE PITCH VENT PIP...

Страница 25: ...ravent PolyPro Horizontal Venting with Concentric Terminal Vent Options 3 4 Terminal Option F VII Venting B Design Requirements Unique to Horizontal Twin Pipe Venting Systems continued PITCH INTAKE AW...

Страница 26: ...tal Twin Pipe Venting Systems continued Note Air intake termination not shown Figure 7 11 Location of Vent Terminal Relative to Windows Doors Grades Overhangs Meters and Forced Air Inlets Two Pipe Sys...

Страница 27: ...ns is generally recommended for both terminations Two rodent screens are included within the available 2 and 3 vent kits or can be fabricated from 1 2 stainless steel mesh screen Rodent screens and ar...

Страница 28: ...PPS 36B w Screen 2PF 10UV or 2PF 39UV w Screen 3PF 10UV or 3PF 39UV w Screen ISEP02 or ISEP0239 w Screen ISEP03 or ISEP0339 w Screen Intake 180 Elbow w Screen 180 Elbow w Screen 180 Elbow w Screen 180...

Страница 29: ...t Vent Manufacturer s PN for Flex Termination Components Required 2PPS VFT 2PPS BV 2PPS FLEX 3PPS VFT 3PPS BV 3PPS FLEX IFBK02 IAWP02B IFBK03 IAWP03B Specify size of B vent e g 2PPS BV6 is for use wit...

Страница 30: ...from an outside wall see Section VII D for additional details All venting is Polypropylene supplied by the vent manufacturer shown in Table 7 13b The portion of this venting within the B vent is flex...

Страница 31: ...rotherm InnoFlue Flex 2 0 ft 2 Selkirk Polyflue 2 0 ft 3 DuraVent PolyPro Flex 2 0 ft 3 Centrotherm InnoFlue Flex 2 3 ft 3 Selkirk Polyflue 2 3 ft 3 Duravent FasNSeal Flex 1 0 ft B Vent Air Chase 1ft...

Страница 32: ...C PVC Venting Vent Options 10 11 Terminal Option H Figure 7 16 Vertical CPVC PVC Venting with IPEX Concentric Vent Terminal Vent Options 10 11 Terminal Option I J VII Venting C Design Requirements Uni...

Страница 33: ...otherm InnoFlue Vertical Single Wall PP Venting Vent Options 12 17 Terminal Option H Figure 7 18 Duravent PolyPro Vertical Venting with Concentric Terminal Vent Options 12 13 Terminal Option J VII Ven...

Страница 34: ...Venting C Design Requirements Unique to Vertical Venting Systems continued Figure 7 19 Duravent PolyPro B Vent Air Chase System Vent Options 18 19 Figure 7 20 Centrotherm InnoFlue B Vent Air Chase Sys...

Страница 35: ...e Terminal Location Observe the following limitations on the intake terminal location also see Figures 7 22 7 23 7 24a and 7 25a The bottom of all terminals must be at least 12 above the normal snow l...

Страница 36: ...lexible polypropylene vent installation is not permitted through any of the adjacent flues Asphyxiation Hazard Flexible stainless steel vent must be installed only in an UNUSED chimney flue A chimney...

Страница 37: ...t 135ft 180 135ft 135ft 135ft Rigid Vent Terminals Vent Coupling w Screen Coupling w Screen 2PPS 12B or 2PPS 36B w Screen 3PPS 12B or 3PPS 36B w Screen 2PF 10UV or 2PF 39UV w Screen 3PF 10UV or 3PF 39...

Страница 38: ...Chimney Chase Note 3 Vent Not Permitted 2PPS FK 2PPS FLEX 3PPS FK 3PPS FLEX 2PF FLEX KIT 2PF FLEX 3PF FLEX KIT 3PF FLEX Intake 90 Elbow w Screen 90 Elbow w Screen 90 Elbow w Screen 90 Elbow w Screen F...

Страница 39: ...ow w Screen 90 Elbow w Screen 90 Elbow w Screen Flex Termination Components B Vent Chimney Chase Vent IFBK02 IFBK03 Not Permitted Intake 90 Elbow w Screen 90 Elbow w Screen Specify size of B vent e g...

Страница 40: ...lit Vent Systems continued Figure 7 22 Split Rigid Vent System Vent Options 25 32 Figure 7 23 Split Vent System Flex in B Vent Chase Vent Options 33 38 PVC AIR INTAKE PIPE FIRE STOP LISTED FOR USE WIT...

Страница 41: ...oned Masonry Chimney Vent Options 33 38 CLEAN TIGHT UNUSED CHIMNEY BASE SUPPORT AND ELBOW FOR PPs FLEX PIPE EXTERIOR WALL PLATE PVC AIR INTAKE PIPE DURAVENT POLYPRO VENT PIPE OUTSIDE WALL PPs FLEX PVC...

Страница 42: ...to Split Vent Systems continued Figure 7 24b Flexible PP Masonry Chimney Chase Requirements WITH CROWN 45 MAX BOILER CHIMNEY AND FOUNDATION ARE STRUCTURALLY SOUND BOILER WARNING Venting of Other Appli...

Страница 43: ...nique to Split Vent Systems continued Figure 7 25a Split Vent Systems SS Flex in Abandoned Masonry Chimney Vent Option 39 Figure 7 25b Flexible SS Masonry Chimney Chase Requirements WARNING Venting of...

Страница 44: ...adaptor has three different inside diameters The larger upper inside diameter accepts 3 CPVC pipe and is used in this application the middle inside diameter accepts 3 nominal PolyPro Polyflue or InnoF...

Страница 45: ...side of the air intake adapter Insert the first piece of PVC air intake pipe into the air intake connection and drill a 1 8 tap hole into the PVC which lines up with the 7 32 clearance hole and secur...

Страница 46: ...46 107672 01 7 17 Figure 7 29 Installation of Standard Vertical Terminals Figure 7 28 Installation of Standard Horizontal Terminals VII Venting E Assembly of CPVC PVC Vent Systems continued...

Страница 47: ...g a primer and cement listed for use with PVC c Fasten the vent base to the wall using the supplied screws and anchors The anchors require the drilling of a 3 16 hole x 1 3 16 deep Locate the holes us...

Страница 48: ...7 17 Figure 7 31 Installation of DiversiTech Low Profile Terminal Through Sidewall Figure 7 30 Installation of IPEX Low Profile Terminal Through Sidewall VII Venting E Assembly of CPVC PVC Vent Syste...

Страница 49: ...17 VII Venting E Assembly of CPVC PVC Vent Systems continued Figure 7 33 Installation of IPEX and DiversiTech Concentric Terminal through Sidewall Figure 7 32 Cutting IPEX and DiversiTech Concentric...

Страница 50: ...g For horizontal installations seal the gap between the OD of the outer pipe and the exterior side of the wall with RTV sealant h Cement the rain cap onto the inner pipe If desired the rain cap can b...

Страница 51: ...middle inside diameter accepts 3 nominal PolyPro Figure 7 27 A locking band clamp in the adaptor prevents the vent pipe from coming out of the adaptor once it is installed and tightened Lubricate the...

Страница 52: ...the installation instructions included by the original Polypropylene venting component manufacturer M G DuraVent Polypropylene pipe sections must be disengaged 1 4 to 5 8 in 6 mm to 16 mm per joint t...

Страница 53: ...nstallation of Duravent PolyPro UV Resistant Single Wall Horizontal Terminal Figure 7 37 Installation of Duravent PolyPro UV Resistant Single Wall Vertical Terminal VII Venting F Assembly of DuraVent...

Страница 54: ...e Seal the termination to the exterior wall plate with weather resistant RTV f Slide the interior wall plate over the termination and attach to the wall from inside the room g Attach the interior wal...

Страница 55: ...7 39 Installation of Duravent PolyPro Concentric Vent Terminal Through Sidewall VII Venting F Assembly of DuraVent PolyPro Vent Systems continued Figure 7 40 Installation of Duravent PolyPro Concentr...

Страница 56: ...p using a 2 or 3 electrical conduit lock nut Seal all joints with RTV G Assembly of Selkirk Polyflue Vent Systems WARNING Asphyxiation Hazard When using PolyPro flex observe the following precautions...

Страница 57: ...exhaust coupling and insert Selkirk 2PF HVST or 3PFHVST in its place c A 180 bend or two 90 elbows are installed on the top of the air intake pipe If two 90 elbows are used a rodent screen can be inst...

Страница 58: ...ference the Selkirk Polyflue instruction manual Not all vent configurations shown in the Selkirk vent manual are listed for use with this boiler Refer to Selkirk Polyflue Instructions for assembly of...

Страница 59: ...Assembly of Selkirk Polyflue Vent Systems continued Figure 7 42 Installation of Selkirk Polyflue UV Resistant Single Wall Horizontal Terminal Figure 7 43 Installation of Selkirk Polyflue UV Resistant...

Страница 60: ...re 7 27 A locking band clamp in the adaptor prevents the vent pipe from coming out of the adaptor once it is installed and tightened Lubricate the gaskets in the vent adaptor with water and insert the...

Страница 61: ...venting component manufacturer Centrotherm Polypropylene pipe sections must be disengaged 1 4 in 6mm per joint to allow for thermal expansion 4 Installation of Horizontal Fitting Terminals Terminal Op...

Страница 62: ...tallation of Centrotherm InnoFlue UV Stabilized Single Wall Horizontal Terminal Figure 7 46 Installation of Centrotherm InnoFlue UV Stabilized Single Wall Vertical Terminal VII Venting H Assembly of C...

Страница 63: ...Tables 7 13b or 7 21 for a list of the principle flex components required Rigid vent pipe by the same manufacturer will also be required for the run from the boiler to the base of chimney b Masonry c...

Страница 64: ...iping may be PVC c There is a 0 minimum clearance between the air intake piping and all types of construction d To the extent possible pitch horizontal air intake piping towards the outside WARNING As...

Страница 65: ...ible stainless steel pipe manufacturer installation instructions and Boiler Installation Operating and Service Instructions the more restrictive instructions shall govern WARNING Asphyxiation Hazard F...

Страница 66: ...nd of the extension as shown in Figure 7 47 2 Condensate is slightly acidic Do not use metallic pipe or fittings in the condensate drain line Do not route the drain line through areas that could be da...

Страница 67: ...e ANSI Z223 1 VII Venting K Removing an Existing Boiler From a Common Chimney WARNING Never common vent this boiler with other appliances Au moment du retrait d une chaudi re existante les mesures sui...

Страница 68: ...rom the gas supply system by closing its individual manual shut off valve Locate leaks using an appropriate combustible gas non corrosive leak detector solution VIII Gas Piping WARNING Explosion Hazar...

Страница 69: ...on fitting located on the bottom of the boiler If an additional regulator is used to reduce boiler inlet pressure below 1 2 psig 3 4 kPa it must be at least 6 to 10 ft upstream of the boiler It is ver...

Страница 70: ...important guideline Tap water contains dissolved oxygen which causes corrosion In a tight system this oxygen comes out of solution and is quickly removed from the system through the automatic air vent...

Страница 71: ...water 6 AutomaticAirVent required Atleastoneautomaticairventisrequired Manualairventswillusuallyberequired in other parts of the system to remove air during initial fill 7 Manual Reset High Limit requ...

Страница 72: ...ly effective way to provide such protection Section HG614 c of the 2013 ASME boiler and Pressure Vessel Code recognizes the use of a listed flow switch in lieu of a low water cut off on water tube boi...

Страница 73: ...ping between the expansion tank and secondary connection tees must be at least 1 In order to keep the flow rates in the system and boiler loops independent of each other provide at least 8 diameters o...

Страница 74: ...Air Vent Header Temperature Sensor When Used Y Strainer Recommended To System System Zone Valves Heating System Circulator Boiler Pump Drain Valve Full Port Isolation Valves Unions Tee Plug Recommende...

Страница 75: ...ze the load placed on the Primary Secondary Header connections 3 Components marked are supplied with the boiler All other components are supplied by the installer 4 3 4 coupling and 3 4 x 4 nipple mar...

Страница 76: ...76 107672 01 7 17 Figure 9 3a Piping Method 1 Near Boiler Piping Heating Plus Indirect Water Heater IX System Piping continued...

Страница 77: ...Port Isolation Valves Tee Plug Recommended For Future Heat Exchanger Service Relief Valve Close Nipple Locate Header Sensor As Close As Possible To Downstream Tee Hydraulic Separator May Be Substitut...

Страница 78: ...lso generally provide effective connection points for automatic air elimination devices and an expansion tank These separators are available from several sources and may be used in place of the closel...

Страница 79: ...79 107672 01 7 17 Figure 9 6 Piping Method 1 Near Boiler Piping Shaded Boiler Loop IX System Piping continued...

Страница 80: ...e curve for the pump in each boiler model taking into account the pressure drop through the boiler s heat exchanger and internal piping These curves therefore show the flow that can be achieved throug...

Страница 81: ...st use Speed HI to achieve the flow requirement shown in Table 9 1 Figure 9 8a Taco Net Circulator Performance Curve Note These curves show the flow that can be achieved through the boiler as a functi...

Страница 82: ...ne additions of fresh water Systems which are open to the atmosphere If the boiler is to be used in such a system it must be separated from the oxygenated water being heated with a heat exchanger as s...

Страница 83: ...83 107672 01 7 17 PAGE LEFT INTENTIONALLY BLANK...

Страница 84: ...dlock once power is turned off WARNING All wiring and grounding must be done in accordance with the authority having jurisdiction or in the absence of such requirements with the National Electrical Co...

Страница 85: ...ction XII of this manual for information on setting up the pump operation 2 Low Voltage Connections Low voltage field connections on the low voltage PCB are shown in Figure 10 3 and are listed from to...

Страница 86: ...86 107672 01 7 17 Figure 10 2 High Voltage PCB Terminal Connections Figure 10 3 Low Voltage PCB Terminal Connections X Wiring continued...

Страница 87: ...h as transformers power lines and fluorescent lighting Wire the sensor to the boiler using 22 gauge or larger wire As with the sensor itself the sensor wiring should be routed away from sources of ele...

Страница 88: ...imary Secondary Tee Sensor Clip Header Temperature Sensor Honeywell 32003971 003 U S B C P N 103104 01 Close Nipple Locate Header Sensor As Close As Possible To Downstream Tee Well Should Extend Into...

Страница 89: ...89 107672 01 7 17 X Wiring continued Figure 10 5 Internal Ladder Diagram...

Страница 90: ...90 107672 01 7 17 X Wiring continued...

Страница 91: ...91 107672 01 7 17 Figure 10 6 Internal Wiring Connections Diagram X Wiring continued...

Страница 92: ...2 STRIP 40b BL SPL BL 1 J8 1 15 GR J4 12 GND 41 YE P8 4 J8 3 16 OR IGNITOR 42 YE P8 5 J7 7 17 P G P10 1 J10 7 43 GY P8 12 SPL GY 1 18 YE P10 2 J10 8 43a GY SPY GY 1 THERM 1 19 P G P10 3 J8 11 43b GY...

Страница 93: ...93 107672 01 7 17 Figure 10 8 TACO SR504 or Equivalent Zone Panel Wiring Connection Diagram X Wiring continued...

Страница 94: ...94 107672 01 7 17 X Wiring continued Figure 10 9 Sage Zone Control Circulator Panel Wiring Connection Diagram...

Страница 95: ...ve hose 7 Check all gas piping for leaks and purge piping sections that are filled with air Refer to the National Fuel Gas Code for additional information on testing and purging gas lines 8 Confirm ve...

Страница 96: ...are a blend of glycol for freeze protection and inhibitors to protect the glycol from attacking metallic system components Do not add any more antifreeze than is necessary to protect the system from f...

Страница 97: ...ignition or if the boiler fails to light after six tries for ignition the blinking HELP button is highlighted on the Home screen Figure 11 2c Touching this HELP button will take the user to the Diagno...

Страница 98: ...72 01 7 17 Figure 11 3 Burner Flame XI Start Up and Checkout continued Figure 11 2a Home Screen at Power Up No Call for Heat Figure 11 2b Home Screen on Heat Demand Figure 11 2c Home Screen with Activ...

Страница 99: ...ing Figure 11 4 Gas Valve Detail 80MBH thru 180MBH WARNING Do not attempt to operate this boiler on LP gas without converting it using the proper conversion kit Do not attempt to convert this boiler t...

Страница 100: ...ts of 1 8 and 1 4 turns and allow the boiler at least a minute to respond to each adjustment With the burner at low fire adjust offset regulator as needed to obtain CO2 or O2 setting shown in Table 11...

Страница 101: ...O Air Free Range Target 080 8 7 9 2 9 1 200ppm 100 120 150 180 Low Fire Range and Target values are the same as High Fire above Ensure low fire CO2 reading is less than or equal to high fire CO2 readi...

Страница 102: ...102 107672 01 7 17 Lighting and Operating Instructions XI Start Up and Checkout continued...

Страница 103: ...is boiler is not used for any space heating This boiler is part of a modular or multiple boiler system having a total input of 300 000 BTU hr or greater This boiler is equipped with a combi space heat...

Страница 104: ...accepts a call for heat demand from multiple places and responds according to it s Priority When more than 1 demand is present the higher priority demand is used to determine active boiler settings Fo...

Страница 105: ...is cycled off XII Operation continued If the temperature exceeds 210 F 98 9 C a manual reset hard lockout results If the boiler is responding to theinternalMultipleBoilerControlSequencer Header Sensor...

Страница 106: ...encer Master enabled Control 3 Lead SlaveSequencing EqualizedRunTime One boiler is a Lead boiler and the remaining networked boilers are Slaves When demand is increasing the Lead boiler is the first t...

Страница 107: ...ciency by helping increase the amount of flue gas water vapor condensation The Control maintains a Base Load Common Rate until the last lag boiler is started At this point the Base Load Common Rate is...

Страница 108: ...Running burner On circulator s On After flame is proven the sequence continues with run stabilization and low fire hold time Once the field adjustable low fire hold time is completed normal boiler ope...

Страница 109: ...at Domestic Hot Water Sequencer Control peer to peer Demand or Frost Protection Warm Weather Shutdown status is shown Standby is shown when no demand is present Energy Save On Indication Outdoor Air R...

Страница 110: ...bol These screens are accessed by selected the Status button from the Home screen Figure 12 6 Status Screens Figure 12 7 Boiler Status Screen Definitions NOTE Only visible if Zone Panel is connected Z...

Страница 111: ...reen provides the status of the boiler s demand to connected pumps as well as the status of Frost Protection and pump Exercise functions This screen provides the status of the boilers five 5 possible...

Страница 112: ...l Screens Figure 12 8 Detail Screen Overview Zone Control Status press for zone cycles i Zone Panel 1 Demand Cycles KITCHEN 45 BEDROOMS 20 BASEMENT 12 DOMESTIC HOT WATER 26 Active zones are shown by b...

Страница 113: ...e Of Operation continued 5 Multiple Boiler Sequencer Screens When the Sequence Master is enabled the following screen is available The Sequencer Status screen is selected by pressing Status button fro...

Страница 114: ...and press the return arrow to close the keypad Press the Save button Press the Adjust button to enter Adjustment mode Figure 12 9 Adjust Mode Screens Login to Access Adjustment Mode For Service Contac...

Страница 115: ...nsor is not connected to the boiler the sensor is not monitored for faults Wired Outdoor Sensor is installed directly on the boiler terminal Strip Wireless Outdoor sensor is installed and wireless Ena...

Страница 116: ...lation rate the Control will go to during a Domestic Hot Water call for heat If the rated input of the indirect water heater is less than the maximum output of the boiler change the DHW Maximum Expect...

Страница 117: ...M 8100 8500 8000 Minimum Heat rate RPM 1710 1800 1500 Default Light off RPM 4000 4000 4000 Altitude 6001 7800 FT Model K2WT 080B 67 K2WT 100B 67 N K2WT 120B 67 N K2WT 150B 67 K2WT 180B 67 N Maximum He...

Страница 118: ...he maximum heat rate the Control then measures water temperature and fires the boiler only as hard as required for the heat demand Expected Heat Rate Adjustment Screens HeatMatch Software Example call...

Страница 119: ...emand Never Any Demand Header Sensor Demand CH Off for DHW Boiler Pump run pump for Activates the boiler pump output according to selected function Never Pump is disabled and not shown on status scree...

Страница 120: ...n This piping arrangement permits the system pump to run or not run when there is a domestic hot water call for heat Domestic hot water priority is optional It is permissible for the domestic and syst...

Страница 121: ...lators Optional Full Port Isolation Valves Optional Full Port Isolation Valves To System From System Air Separator Air Vent Expansion Tank Header Temperature Sensor When Used Cold Water Line Y Straine...

Страница 122: ...c hot water call for heat Domestic hot water priority is optional It is permissible for the domestic and system pumps to run at the same time The boiler pump must run for every call for heat Example P...

Страница 123: ...Description Contractor Name User defined Contractor Name Address Line 1 User defined Contractor Address Line 1 Address Line 2 User defined Contractor Address Line 2 Phone User defined Contractor Phone...

Страница 124: ...ure controller Proportion Integral Derivative PID values Higher values cause a larger firing rate change for each degree of temperature change If set too high firing rate overshoots required value inc...

Страница 125: ...g the temperature to exceed the Diff Above setpoint and cycle the boiler unnecessarily Lower values cause a smaller firing rate change for each degree of temperature change If set too low the firing r...

Страница 126: ...xceed the Diff Above setpoint and cycle the boiler unnecessarily Lower values cause a smaller firing rate change for each degree of temperature change If set too low the firing rate response will be s...

Страница 127: ...F 21 1 C 32 F to 100 F 0 C to 37 8 C Central Heat High Outdoor Temperature The High Outdoor Temperature parameter is the outdoor temperature at which the Low Boiler Water Temperature is supplied This...

Страница 128: ...100 F 40 C to 37 8 C Auxiliary Heat Low Outdoor Temperature The Low Outdoor Temperature parameter is also called Outdoor Design Temperature This parameter is the outdoor temperature used in the heat...

Страница 129: ...Setpoint Heating Element Type 180 F to 190 F 82 2 C to 87 8 C Fan Coil 100 F to 140 F 37 8 C to 60 C In Slab Radiant High Mass Radiant 160 F to 190 F 71 1 C to 87 8 C Convection Baseboard Fin Tube Con...

Страница 130: ...ond to rapid load increases 70 50 100 Base Load Common Rate To maximize condensing boiler efficiency the firing rate is limited to an adjustable value Boilers are kept at or below this firing rate as...

Страница 131: ...nd J10 8 is used as the temperature setpoint The following two parameters may be used to adjust the signal range Modbus Modbus is used as the temperature setpoint 130 F 54 4 C 80 F 26 7 C Central Heat...

Страница 132: ...approved respirator 2 Long sleeved loose fitting clothing 3 Gloves 4 Eye Protection Take steps to assure adequate ventilation Wash all exposed body areas gently with soap and water after contact Wash...

Страница 133: ...y metals carbon monoxide nitrogen oxides aldehydes and or other toxic or harmful substances which can cause death or serious injury and which are known to the state of California to cause cancer birth...

Страница 134: ...erify that the gas shutoff shown in Figure 8 1 is closed e Disconnect the flexible gas line at the gas valve flare connection Figure 13 1 f Unplug the electrical connection to the gas valve g Disconne...

Страница 135: ...Gas Line Figure 13 2 Flame Ionization Electrode and Ignition Electrode Location XIII Service and Maintenance continued When disconnecting exible gas line Place a backup wrench on this nut to prevent...

Страница 136: ...on the bottom of the boiler see Figure 2 1 to catch water in the trap as well as the ball and ball support Unscrew the cap being careful not to lose the ball or ball support Flush any debris found in...

Страница 137: ...137 107672 01 7 17 XIII Service and Maintenance continued Figure 13 3 Ignition Electrode Gap Figure 13 4 Condensate Trap Exploded Parts View...

Страница 138: ...r water and the use of boiler water additives NOTICE Do not remove return pipe connection from heat exchanger to service the circulator u Test the flow switch To do this Start with the boiler in stand...

Страница 139: ...Help button flashes and the home screen turns a red color Continue to select flashing buttons to be directed to the Fault cause B Display Faults Indication Condition Possible Cause Display Completely...

Страница 140: ...then Disabled Master s Boiler has been powered down To clear fault restore communication or cycle power Boiler Size Setup Boiler Size Fault WARNING Boiler size setting may not match actual boiler siz...

Страница 141: ...owing messages appear when the firing rate is limited or reduced to help avoid a lockout or save energy Refer to Hard Lockout section for corrective actions High Stack Temperature Limit High Supply Te...

Страница 142: ...witch Special Note Before a call for heat the air pressure switch is closed When there is a call for heat with a blocked vent the air pressure switch will open due to excessive pressure of the blower...

Страница 143: ...for blower speed to match purge and light off setpoint Normal waiting for blower speed to match purge and light off setpoint 27 Undefined Fault Undefined Fault Consult Factory 28 or 53 Air Proving Swi...

Страница 144: ...ed or dirty drain line in trap 18 Light off rate proving failed Blower is not running at Light off rate when it should or blower speed signal not being detected by Control Loose connection in 120 VAC...

Страница 145: ...your local U S Boiler Wholesale distributor Should you require assistance in locating a U S Boiler distributor in your area or have questions regarding the availability of U S Boiler products or serv...

Страница 146: ...5879 01 11A 11B 11C Flame Rod includes flame rod gasket and hardware 105880 01 12A 12B 12C Ignition Electrode includes electrode gasket and hardware 105881 01 13 M6 Serrated Flange Hex Burner Door Nut...

Страница 147: ...147 107672 01 7 17 XV Service Parts continued...

Страница 148: ...871 01 Not Shown LP Gas Conversion Kit excludes M models 107873 01 107874 01 107875 01 27 28 29 Blower Outlet Gasket 106029 01 30 31 34 CSST Gas Line Assembly includes gas line assembly and gasket 106...

Страница 149: ...0 100 120 150 180 51 52 53 Condensate Trap includes gasket bracket and trap ball 105851 01 54 55 56 57 59 Silicone Tubing includes 3 16 and 3 4 tubing spring clamp and vent fitting 105855 01 58 Sump P...

Страница 150: ...50 180 67 68 69 73 Low Voltage Printed Circuit Board PCB includes Low Voltage PCB and hardware 105853 01 67 70 71 72 73 High Voltage Printed Circuit Board PCB includes Line Voltage PCB insulator gaske...

Страница 151: ...151 107672 01 7 17 XV Service Parts continued...

Страница 152: ...Number Qty 080 100 120 150 180 75 Transformer 106034 01 76 Sage 2 3 Boiler Control 107877 01 77 78 82 97 Control Door Parts 107872 01 79 8 18 x 1 2 Self Tapping Screw Obtain locally 80 Programmable Di...

Страница 153: ...153 107672 01 7 17 XV Service Parts continued 85 86 91 95...

Страница 154: ...PVC Intake Coupling with Locknut 105848 01 95 Vent Connector includes connector gasket and hardware 107034 01 96 8 18 x 1 2 Screw Obtain locally 98 1 8 x 1 x 3 Hinge Pin Obtain locally 103 105 Jacket...

Страница 155: ...NPT x 2 Nipple Obtain locally 119 1 NPT Tee with Side Outlet 107895 01 120 1 x 1 4 NPT Hex Reducing Bushing Obtain locally 121 Temperature Pressure Gauge 105894 01 122 1 x 3 4 NPT Hex Reducing Bushin...

Страница 156: ...er 080 100 120 150 180 130 Low Voltage Communication 107876 01 131 High Voltage Harness 105868 01 132 133 135 Trap Flame Trap Ground Circulator Pigtail includes wire harness 105870 01 134 Ignition Cab...

Страница 157: ...s injury and or reduced component life Adjusting Boiler Type must be completed first Select the correct K2WT boiler size altitude and fuel range using the touch screen display as follows 1 Check boile...

Страница 158: ...9 8 9 8 Low Fire Range and Target values are the same as High Fire above Ensure low fire CO2 reading is less than or equal to high fire CO2 reading Model No Fuel Measured O2 Max Co Air Free 2001 6000...

Страница 159: ...proximate Derate per 1000 ft 2001 6000 ft 6001 7800 ft 7801 10 100 ft K2WT 080B NG 0 9 4 0 4 0 LP Not Permitted K2WT 100B NG 1 9 2 6 2 7 LP 3 1 3 8 4 0 K2WT 120B NG 1 2 1 8 2 4 LP 1 7 3 3 Not Permitte...

Страница 160: ...period of thirty 30 days to comply with the above requirements provided however that during said thirty 30 day period a battery operated carbon monoxide detector with an alarm shall be installed 2 AP...

Страница 161: ...rements shall be satisfied by the manufacturer 1 The referenced special venting system instructions shall be included with the appliance or equipment installation instructions and 2 The special ventin...

Страница 162: ...162 107672 01 7 17...

Страница 163: ...163 107672 01 7 17...

Страница 164: ...164 107672 01 7 17...

Страница 165: ...165 107672 01 7 17...

Страница 166: ...166 107672 01 7 17...

Страница 167: ...167 107672 01 7 17...

Страница 168: ...168 107672 01 7 17 U S Boiler Company Inc P O Box 3020 Lancaster PA 17604 1 888 432 8887 www usboiler net...

Отзывы: